TABLEOFCONTENTS
TOC\o
1. INTRODUCTION.
1
1.1. DefinitionsAndInterpretations.
1
1.2. Distribution.
1
1.3. ProjectPhilosophy.
1
1.4. BriefDescriptionofProjectScope.
2
2. CONTRACTOR’SORGANIZATION.
5
2.1. Contractor’sOverallOrganizationChart.
5
2.2. ProjectTeamOrganizationChart.
5
2.3. EngineeringPlan.
5
2.4. Attachments.
5
3. DETAILEDWORKSCHEDULE.
6
3.1. Attachments.
6
4. CORRESPONDENCEPROCEDURE.
7
4.1. CorrespondenceNumbering.
7
4.1.1. CompanytoContractor
7
4.1.2. ContractortoCompany.
7
4.1.3. ContractortoSupervisingCompanyor“Jianli”.
7
4.2. ContactAddresses&Numbers.
8
4.2.1. Owner’sAddress&ContactNo.
8
4.2.2. OffshoreContractor’sAddress&ContactNo.
8
4.2.3. OnshoreContractor’sAddress&ContactNo.
8
4.2.4. Contractor’sTentativeContactParticular:
9
4.2.5. SupervisingCompanyAddress&ContactNo.
9
5. PROJECTDOCUMENTCONTROLPROCEDURE.
10
5.1. EngineeringDocuments.
10
5.1.1. OutgoingDocuments.
10
5.1.2. IncomingVendor’sDocuments.
10
5.1.3. ReturnOfVendor’sDocuments.
10
5.2. OtherDocuments.
10
5.3. Filing.
10
5.4. ControlofRevisedDocuments.
11
6. DescriptionofOrganizationChartandKeyPersonnel.
12
6.1. ProjectOrganization.
12
6.1.1. PrinciplesofProjectManagementAndExecution.
12
6.2. Implementation.
12
6.3. ProjectCommittee.
12
6.4. ProjectManager.
13
6.5SiteManager.
14
6.6 ConstructionManager.
14
6.7 ConstructionAdvisor
15
6.8 SHEManager.
16
6.8 OtherKeyPersonnel.
16
6.8.1OffshoreOffice.
16
a) EngineeringManager.
16
b) LogisticsManager.
17
c) ProjectEngineer
17
6.8.2 OnshoreOffice.
17
a) AdministrationManager.
17
b) ProcurementandContractsManager.
17
c) QA/QCManager.
18
6.9 OfficeLocations.
18
6.9.1 OffshoreOffice.
18
6.9.2 OnshoreOffice.
19
7 ENGINEERINGPLAN.
20
7.1. General.
20
7.1.1. EngineeringPlan.
20
7.1.2. DisciplineandInterdisciplinaryCheck.
21
7.1.3. TechnicalEvaluationandVendorDocumentsReview.
21
7.1.4. SeamlessTeamCommunication.
21
7.2. BasicEngineering.
21
7.3. DetailedEngineering.
22
7.4. ComputerAidedEngineering.
22
7.5. HAZOPStudy.
22
8. DRAWING&DOCUMENTAPPROVALPROCEDURE.
23
8.1. General.
23
8.2. ApprovalItems.
23
8.3. LocalAuthoritiesApproval.
23
8.4. TimeforApproval.
23
8.5 DocumentFlowControl.
23
8.6 Vendor/SupplierDocument.
23
8.7 Definition.
23
8.7.1 ForApproval.
24
8.7.2 ForInformation.
24
8.7.3 ApprovedForConstruction/Final.
24
8.7.4 Owner’sComment
24
8.8 Indication.
25
8.9 Attachments
26
9 PROCUREMENTPROCEDURE.
31
9.1 SpecificPlansForProcurement.
31
9.2 ProcurementProcedure.
31
9.2.1 PreparationOfVendorList.
31
9.2.2 VendorPre-Qualification.
31
9.2.3 RequestForQuotation.
32
9.2.4 BidAnalysis.
32
9.2.5 PlacingOrders.
32
9.2.6 SpareParts.
32
9.2.7 ProcurementProcessFlow.
33
9.3 ATTACHMENTS
33
10 EXPEDITINGPROCEDURE
34
10.1 ResponsibilityAndDuties.
34
10.2 PrincipleOfExpediting.
34
10.3 Inspection.
35
10.4 Report.
35
10.4.1 ShopVisitReport.
35
10.4.2 Expediting/ShippingStatusReport.
35
10.4.3 ProgressTracking.
35
10.5 ImportandCustomsClearance.
36
10.6 Attachments.
36
11 CONSTRUCTIONWORKPLAN.
40
11.1 WorkPlanOfFieldConstruction.
40
11.1.1 Principles.
40
11.1.1.1 SafePerformanceOfWork.
40
11.1.1.2 CloseCommunicationwithOwner.
40
11.1.2 Subcontracting.
40
11.1.2.1 SelectionofSub-contractors.
40
11.1.2.2 ControlofSub-contractors.
41
11.1.2.3 RecordEvaluation.
41
11.1.3 TemporaryFacilities.
41
11.1.4 ConstructionUtilities.
41
11.2 SHEPlan.
41
11.2.1 General.
41
11.2.2 SHEPolicy.
41
11.2.3 SHEObjective.
42
11.2.4 SHETarget
42
11.2.5 MajorItemsofSHESystem.
42
11.3 Materials.
44
11.3.1 MaterialsPurchased.
44
11.3.2 MaterialsSchedule.
44
11.4 Mobilization.
44
11.4.1 MajorConstructionEquipmentMobilization.
44
11.4.2 ProjectPersonnelPlan.
44
11.4.3 TemporaryFacilityPlan.
44
11.5 Attachments.
44
12 QA/QCPLAN.
45
12.1 QualityObjective.
45
12.2 QualityPolicy.
45
12.3 InspectionandTestingPlan.
45
12.4 GeneralInspectionProcedure
45
13 PROGRESSREPORTINGPROCEDURE.
46
13.1 General.
46
13.2 ProgressReporting.
46
13.3 ContentsofReport.
46
13.4 ProgressReportForm.
47
13.4.1 ProjectProgressReport(Form01)
47
13.4.2 EngineeringProgressReport(Form02).
47
13.4.3 ProcurementProgressReport(Form03).
47
13.4.4 FieldConstructionProgressReport(Form04).
48
13.5 Attachments.
48
14 SCHEDULECONTROLPROCEDURE.
55
14.1 General.
55
14.2 PlanningSoftware.
55
14.3 ControlMethod.
55
14.3.1 StepsOfControl.
55
14.3.2 OverallControl.
55
14.3.3 PlanningandControlFlow.
56
14.4 ProgressReporting.
56
14.5 WeeklySchedule.
56
14.6 Attachments.
56
15 CHANGEINWORKPROCEDURE.
57
15.1 General.
57
15.2 Change.
57
15.3 ChangeProposalFormat.
57
16 TURN-OVERPROCEDURE.
62
16.1 General.
62
16.2 IndividualTurn-Over.
62
16.3 Definitions.
62
16.3.1 Turn-Over.
62
16.3.2 MechanicalCompletion.
62
16.3.3 Unit.
62
16.4 WorkLists.
62
16.4.1 DetailedListOfOutstandingWork.
62
16.4.2 PunchList.
63
16.5 Notices.
63
16.5.1 MechanicalCompletion.
63
16.5.1.1 Contractor’sNotice.
63
16.5.1.2 Owner’sComments.
63
16.5.1.3 RepairWork.
63
16.5.2 CertificateOfMechanicalCompletion.
64
16.6 PreparationForOperation.
64
16.7 CommissioningAndOperationalTest.
64
16.8 FlowOfTurnoverProcedure.
64
16.9 Attachments.
65
INTRODUCTION.
ThisProjectExecutionPlanprescribestheschemetheContractorproposestoemployforexecutingtheWork.Namely,itoutlinestheorganization,andtheprinciples,location,andmannerofperformingtheWorkandgivingdetailedprocedures.
DefinitionsAndInterpretations.
InthisProjectExecutionPlanthefollowingwordsandphrasesshallhavethemeaningsasfollows
“Company”shallbeinterpretedasVopakShanghaiLogisticsCo.,Ltd.
“Owner”,wherevermentionedshallhavethesameinterpretationas“Company”andviceversa.
“Contractor”shallbeinterpretedasRotaryEngineeringLimitedandChinaInternationalWater&ElectricCorp.(S)PteLtdConsortium.
“RCC”,wherevermentionedshallhavethesameinterpretationas“Contractor”andviceversa.
“SupervisingCompanyor“Jianli”shallbeinterpretedasAudexPteLtd/ShanghaiCoking&ChemicalProjectConstructionSupervisionCo.Ltd.
“LDI”shallbeinterpretedasZhejiangTITANDesign&EngineeringCo.,Ltd.
Distribution.
ThisProjectExecutionPlanshallbedistributedtothekeypersonnelintheProjectasfollows:
Company’sProjectManager/DeputyProjectManager/SHEManager(2EnglishCopyand2ChineseCopy)
Contractor’sProjectManagerandSiteManager
Contractor’sConstructionManager
SupervisingCommittee’sChiefSupervisorandDeputyChiefSupervisor(1EnglishCopyand1ChineseCopy)
Others(SiteManagerwilldecidethedistributionrequirements)
ProjectPhilosophy.
SafetyFirst
Emphasisonqualityofdesignsmaterialsandworkmanship
Successfulon-scheduleexecutionandperformance
Controlofconstructionandoperationcosts
Easeofoperationandmaintenanceoftheplant
BriefDescriptionofProjectScope.
VopakShanghaiLogisticsCo.,LtdintendstorealizeaproductlogisticsterminalatShanghaiCaojingChemicalPark.
Theterminalwillbecompletedwithtanker,coasterbargeberthingandloadingfacilitiesandwillbeusedforstorageanddistributionofliquidchemicalproductsforthelocaland exportmarket.Eachproductwillhavetheoptionsofbeingtransportedinandouteitherbyship,coasterbarge,truck,railcarordrums.
Theterminalwillbebuiltinphasesoveraperiodtobedecidedbymarketdevelopment.Thisdescriptiononlycoversthefacilitiesasrequiredfortheinitialphase.Theterminallayoutsaswellasthelocationforberthingplacesarearrangedinsuchawaythatsmalladaptationscanbemadetosatisfyalternativerequirementsandfutureextensionscanberealizedoptimallyatminimumcost.
Theoffshorefacilitiesareforreceivingproductsfromoceanvesselsandarealsofordischargingproducttosmallervesselsandbargesfordistribution.Theoffshorefacilitiesshallconsistoftwojettieswhichcanbertha5,000DWTto25,000DWTvessels,twojettieswhichcanbertha1,000DWTto12,000DWTvesselandtwojettieswhichcanbertha1,000DWTto5,000DWTvesselsberthingsimultaneously.
Theonshorefacilitiesconsistofproductstoragefacilities,chemicalspumpingfacilities,drummingandwarehousingfacilities,truckandrailloadingfacilitiesfordedicatedclients.
Theutilityfacilitiesshallconsistofpotablewatersystem,plantairsystem,instrumentairsystem,nitrogensystem,firefightingsystem,wastewatertreatmentandslopsystem,andoffgastreatmentsystemforhazardouschemicalsshallbeprovidedfortheonshoreandoffshorefacilities.Airconditioningandventilationshallbeprovidedforthebuildings.Refrigerationsystemshallbeprovidedforrefrigeratedwarehousesandcontrolledtemperaturewarehouse.
Theterminalshallhaveamainofficebuildingattachedwiththecentralcontrolroom,aworkshop,afoamtruckbuilding,anintegrateddrummingandwarehousebuilding,truckloadingsheds,aircompressorshed,mainsubstationandguardhouse.
VopakShanghaiLogisticsCoLtd.(hereinaftercalledEmployer)shallbethemanagingcompanyandprovidetheknow-howandtechnologyfortheoperationoftheterminal.
Thescopeofworkshallincludeengagingalocaldesigninstituteforallgovernmentauthorityapprovalandliaisonwithgovernmentauthority,detailedengineering,procurementofallequipmentandmaterialandfieldinstallationanderectionaspercontractdocumentrequirement.
Thefollowingaregeneraldescriptionsoftheworkelements.Theseworkelementsdescriptionisjustaguidelineandthedetailedscopeofworksshallbeaspercontractrequirement:
a.Projectmanagement
-- LiaisonwithEmployer
-- Projectcontrolandreporting
-- Schedulecontrolforengineering,procurementandconstruction
b.Engagedesigninstitute
-- EndorsementofalldrawingforsubmissiontoGovernmentAuthority
-- LiaisonwithallGovernmentAuthority
c.Detailedengineering
-- PreparationofP&IDiagram,plotplan,areaclassificationdrawingandsinglelinediagram.
-- Preparealldesigncalculationsforallfunctionalengineeringofonshorefacilities
-- Preparealldesigncalculationsforstructure(i.e.operatingplatform,piperack,pipesupport),mechanicalequipment,piping,electricalandinstrumentationengineeringofoffshorefacilities
-- Prepareallconstructiondrawingsforallfunctionalengineeringofonshorefacilities
-- Prepareallconstructiondrawingsforstructure(i.e.operatingplatform,piperack,pipesupport),embeddedsteel,mechanicalequipment,piping,electricalandinstrumentationengineeringofoffshorefacilities.
-- Preparematerialspecificationandrequisitionofallmaterials,equipmentandotheritemstobesuppliedforonshoreandoffshorefacilities
-- Reviewandapproveofvendors'documents.
-- Prepareasbuiltdrawingsanddocument
-- Preparemechanicalcatalogandoperationmanual
-- Co-ordinationwithmarinestructuredesigninstitute
d.Procurement
-- Procurementofallfunctionalengineeringbulkmaterial
-- Procurementofallequipment
-- Recommendedsparepartsforoneyearoperation
-- Packing
-- Shippingandtransportation
-- Portclearanceandhandlingcharge
-- Loadingandunloading
e.Construction
-- Alltemporaryfacilitiessuchassiteoffice,utilities,storagefacilities,laborcamp,accessroad,drainageandfencing
-- Sitesecurityservices
-- Constructionmanagement
-- Constructionlabor
-- Constructionequipment
-- Temporarymaterials
-- Consumables
-- Handtools
-- Safetyequipmentandpersonalprotectivewear
-- Landandmarinetransportation
-- Pre-commissioning
-- Constructionspares
CONTRACTOR’SORGANIZATION.
UnderContractor’spermanentorganization,theContractorshallorganizetheProjectTeam,whichwillco-ordinatebetweentheOwner,SupervisingCompanyandtheContractor’spermanentorganization.
Contractor’sOverallOrganizationChart.
OverallOrganizationChartofRotaryEngineeringLimitedisattachedasAttachment2.1.
OverallOrganizationChartofChinaInternationalWater&ElectricCorp.(S)PteLtdisattachedasAttachment2.2.
ProjectTeamOrganizationChart.
InordertoexecutetheWorkeffectivelyandsmoothly,theContractorwillorganizetheProjectTeamshownintheProjectTeamOrganizationChartattachedasAttachment2.3.
TheProjectTeamshallbeamatrixorganization.
EngineeringPlan.
DedicatedEngineeringTeamstoexecutebasicanddetailedengineeringactivities:
BasicdesignandengineeringinRELSingaporeOffice.
DetaildesignandengineeringwillbecarriedoutatLocalDesignInstitute(LDI)inHangzhou,China.
AlldetaildrawingswillbeendorsedbythelocalauthorityorqualifiedAccreditChecker.
Attachments.
Attachment2.1
OverallOrganizationChartofRotaryEngineeringLimited(REL)
Attachment2.2
OverallOrganizationChartofChinaInternationalWater&ElectricCorp.(S)PteLtd(CIWE)
Attachment2.3
ConsortiumProjectTeamOrganizationChart
DETAILEDWORKSCHEDULE.
TheProjectScheduleemployingGanttcharttechniqueisshownonAttachment3.1
Attachments.
Attachment3.1
PreliminaryMasterSchedule
CORRESPONDENCEPROCEDURE.
AllcorrespondenceinexecutionofWorksundertheProjectshallbebetweenCompany’sProjectManagerorhisRepresentative(ifCompany’sProjectManagerdirectsso)andContractor’sProjectManager.TheContractorProjectManagerorhisRepresentativeshallalsocorrespondwithSupervisingCompany(SC)orJianli’sRepresentative.
DocumentsinvolvingdesigndrawingshallbesubmittedtoOwnerandcctoSCwhileanydocumentsdealingwithconstructionshallbesubmittedtoSCandcctoOwner.
CorrespondenceNumbering.
Correspondencenumberingshallbeasfollows:
CompanytoContractor
ContractNo. :
Corresp.No. :
Attention :Mr.KhinMM
ContractortoCompany.
ProjectNo. :
Corresp.No. :RCC/CL-xxx/301P0688/FC
Attention :Mr.LeeHoiChuen
WhereRCCstandsforREL/CIWEConsortium
e.g.
L
=
Letter
F
=
Facsimile
T
=
DocumentTransmittal
MM
=
Memorandum
MOM
MinutesofMeeting
xxx
=
SerialNumber
FC
=
FilingCode
ContractortoSupervisingCompanyor“Jianli”.
ProjectNo. :
Corresp.No. :RCC/SL-xxx/301P0688/FC
Attention :Mr.SongYangGeun
WhereRCCstandsforREL/CIWEConsortium
e.g.
L
=
Letter
F
=
Facsimile
T
=
DocumentTransmittal
MM
=
Memorandum
MOM
=
MinutesofMeeting
xxx
=
SerialNumber
FC
=
FilingCode
ContactAddresses&Numbers.
Owner’sAddress&ContactNo.
TownOffice
VopakShanghaiLogisticsCo.,Ltd
Room7004,NovelBuilding
887,HuaihaiZhongLu
Shanghai20
P.R.China
Tel: (86)2164315002
Fax: (86)2164747409
SiteOffice
ShanghaiChemicalIndustrialParkC1-2-1
FengxianDistrict,Shanghai07,
P.R.China
Tel: (86)21
Fax: (86)21
OffshoreContractor’sAddress&ContactNo.
RotaryEngineeringLimited
No.17,TuasAve20.
Singapore638828
Tel: (65)68611155
Fax: (65)68623306
OnshoreContractor’sAddress&ContactNo.
ChinaInternationalWater&ElectricCorporation(s)PteLtd
80,MarineParadeRoad,
09-09ParkwayParade
Singapore449269
Tel:(65)64405186
Fax:(65)64407959
Contractor’sTentativeContactParticular:
Mr.KhinM.M
ProjectManagerofCaojingProject
Unit2802B,No800DongfangRoadBaoAnBuilding
PudongShanghai,P.R.China22
Tel:(86)58204466CellPhone:
Fax:(86)68752850
TheabovecontactnumberandaddressaresubjecttochangeswhenthesiteofficeisreadybymidOct.
SupervisingCompanyAddress&ContactNo.
AudexPteLtd/ShanghaiCoking&ChemicalProjectConstructionSupervisionCo.Ltd.
No.4319LongWuRoad
Shanghai41,PRC
Tel: (86)02164345011
Fax: (86)02164340535
PROJECTDOCUMENTCONTROLPROCEDURE.
Allincomingandoutgoingprojectdocumentsshallbecontrolledanddistributedaccordingtothisprocedure.
EngineeringDocuments.
OutgoingDocuments.
AllengineeringdocumentsgeneratedbyLDIshallbeissuedtoCompanyforreviewandapprovalbytheRCC.nagementTeam(PMT).AcopyofthedocumenttransmittalwithouttheattachmentsshallbedistributedtoContractor’sEngineeringDepartmentforinformation.
IncomingVendor’sDocuments.
OffshorePurchaseItems:
IncomingVendor’stechnicalandengineeringdocumentsforapprovalshallbereceivedbyContractor’sProcurementDepartment.ProjectEngineerorbuyerwillrecordtheVendor’sincomingdocumentsanddistributeonecopytoSeniorPM/PMandonecopytotheleadengineeronsite.Afterreviewbythedisciplineengineer,acopyofthecommenteddocumentsshallbehandedtoSeniorPM/PMwhowillreviewandinputfurthercommentsifnecessary.TwocopiesofthecommenteddocumentsshallbesubmittedtoCompanyforreview/approval.
OnshorePurchaseItems:
(Theaboveprocedurealsoappliesinprincipletotheonshorepurchaseitems).
ReturnOfVendor’sDocuments.
Vendor’sdocumentsreturnedfromCompanywithorwithoutcommentsshallbenotedandsentbacktotheRespectiveVendorsforre-submissionorincorporationwithin14calendardaysafterreceivingofthedocumentsasperITBrequirements.
OtherDocuments.
IncomingdocumentsfromCompany,Vendors,Subcontractorsetc.otherthanabovementionedshallbereceivedbyContractor’sSeniorPM/PMandcopiesdistributedtoContractor’srelevantDepartment’sconcernedforactionorforinformation.
Filing.
AlldocumentsrelatedtotheProjectshallbefiledaccordingtotheattachedProjectFileNumberingDocNo.:PRO-FIL-001.
Attachment5.1:PRO-FIL-001ProjectFileNumbering.
ControlofRevisedDocuments.
Anydocumentsordrawingsthathadbeenrevisedandreissuedasapprovedrevisionshallsupersedethepreviousdocuments.Anysupersededdocumentsshallbeappropriatelyidentifiedandberemovedfromprojectfile.Acopyofsupersededdocumentshallbekeptseparatelyforreferenceorforcontractualpurposes.However,theseshallbeclearlyidentifiedandseparatedfromlatestreviseddocument.
Alldocuments/drawingsusedatsiteshallbeapprovedforconstruction.
DescriptionofOrganizationChartandKeyPersonnel.
ProjectOrganization.
InordertoexecutetheWorkeffectivelyandsmoothlyfromtheviewpointofqualityandschedule,theContractorwillorganizetheProjectTeamshownintheProjectTeamOrganizationChartattachedasAttachment2.3
TheProjectTeamshallbeamatrixorganization.
PrinciplesofProjectManagementAndExecution.
ThefollowingprincipleswillapplytoeachphaseofProcurementandConstructionfortheWork.
Emphasisonqualityofdesignmaterialsandworkmanship.
Onscheduleperformance.
MinimumconstructionandoperationcostsfortheTerminal.
EaseofoperationandmaintenanceoftheTerminal.
Implementation.
Inordertoimplementtheaboveprinciples,theContractorplanstoexecutetheWorkby:
OrganizingaProjectTeamforthesolepurposeofexecutingtheWork.Asufficientnumberoffullyqualifiedpersonnel,especiallythosewithexperienceinterminalprojects,shallbeassigned.
AbsorbingandfullyunderstandingthespecificationsandrequirementsoftheOwnerandtakingadvantageoftheContractor’sfamiliaritywiththecodesandstandardstobeappliedtothisProject.
Makingeffectiveuseoftheinformationtechnologyformaintainingthescheduleandqualityofwork.
ProjectCommittee.
Projectcommitteeistheimplementation’schampions.TheirsupportsareessentialtothesuccessfortheWorks.Membersmeetregularly(monthlyforfirstthreemonth)todiscussimportantissues,reviewprogress,providesolutionsandmakekeydecisions.
ThecommitteemembersarecomposedprimarilyoftopmanagementoftheConsortium.
ProjectManager.
ProjectManagershallbeassignedfromamongstaffpersonnelwithabundantexperienceinmanagementofProject.Heshall:
ProjectManagerwillbeauthorizedandresponsibleforalltheprojectactivitiesagainsttherequirementsoftheEmployerwiththeassistanceandsupportoftheprojectstaffsconsistingofProjectCoordinator,ProjectEngineer,PlanningEngineerandProcurement/Engineering/ConstructionTeam..
ResponsibleandauthorizetodecideallfundamentalmanagementmattersoftheprojectandensurethatProjectExecutionProcedureisdocumented,understoodandimplementedbyallemployees.
CoordinationwithEmployerandEmployer’srepresentativeSupervisingCompany.
OverallProjectBudgeting.
OverallControlandManagementofEngineering,ProcurementandConstructionSchedule.
Engineering.
Planning/SchedulinginengineeringmattersincludingDocumentRegister.
Basic/DetailedDesignandEngineering.
Preparationofrequisitionofequipmentwithpriorityoncriticallongleaddelivery.
TechnicalBidEvaluationofequipmentwithpriorityoncriticallongleaddelivery.
Checkingofdisciplinevendor’sprintsandincorporatingintodesignwithitsresultsfordisciplineworks.
DeliveryofIFA(IssueForApproval),IFC(IssueForConstruction)drawingsanddocuments.
Supervisingoninitialdesignandconversiondesign.
FieldEngineeringSupports.
LocalAuthorityApproval.
As-BuiltDrawings/MechanicalCatalogues.
ManagementandControlofEngineeringSchedule.
g) Procurementservices.
ConfirmationonSpecificationsofEmployer’spreferredVendorsandApproval.
Pre-qualificationofVendorsnotlistedinrecommendedlistbyEmployerandproposeforEmployer’sApproval.
Commercialevaluation,selectionofVendors/Manufacturers.
Releasepurchaseorderofmaterials.
Forwardingandexpeditingofmaterials.
ManagementandControlofProcurementSchedule.
h) Pre-commissioningandCommissioningAssistance.
6.5SiteManager.
SiteManagershallberesponsibleforfollowingactivities:
a) SiteManagerwillbeauthorizedandresponsibleforallconstructionactivitiesagainsttherequirementsoftheEmployerwiththeassistanceandsupportoftheconstructionteam.
b) CoordinationwithEmployer,Employer’srepresentativeSupervisingCompanyandsub-contractors.
c) OverallConstructionScheduleManagementassistedbyPlanningControlEngineers.
PlanningandSchedulingconsistsofConstructionMasterSchedule,ThreeMonthsLook-aheadConstructionSchedule,MonthlyConstructionScheduleandWeeklySchedule.
MonitoringandAnalysis.
StudyofCountermeasuresandReportingwillconfirmtheschedulevarianceincomparisonwiththeoriginaltargetandmaycallsomerequirementsofnecessarycountermeasurestosuccessfullyattaintheoriginalcompletiontargetontime.
ProgressMeasurement.
ControlofSubcontractorPlanningTeams.
Reportingontheconstructionprogress,qualityissueandSHEissuetoProjectManagement,EmployerandSupervisingCompany.
Preparingandcontrollingmanpower,equipmentandmaterialsineachdisciplineinaccordancewithconstructionscheduleandprogress.
ConstructioncostcontrolandBudgeting.
SubcontractSourcingandManagement.
Safety,QA/QC,SHE.
FieldMaterialControl.
ManageSiteConstructionmattersandlocalengineeringactivitiesbysubcontractors.
ManagingLocalProcurement.
CustomsClearanceandonlandtransportationtoSite.
6.6 ConstructionManager.
Immediatelyuponawardofcontract,theConstructionManagerwillbeappointedtotakecontrolofallsiteconstructionactivities.
a)HewillberesponsibletoSiteManager.Refertositeorganizationalchart,histeamconsistsof:(tobeupdatedasrequired)
Civil&StructureTeam
MechanicalTeam
ElectricalTeam
I&CTeam
PaintingandInsulationTeam
ShopFabricationTeam
EachteamisheadedwithaspecialtyteammanagerwhoreportstoConstructionManager.
b)TheConstructionManagerwillworkcloselytocontrolscheduleandqualityofsiteworks.Heshalltakeadjustmentforanydeviationfromkeycompletiondate.
Hewillcoordinatetheworksequenceofeachteammanagerandeachspecialtyengineer.
Hewillbeinchargeintheimplementationofprojectsafetyprocedures.Safetyistheprimaryconcernofhisworks.
HeshallliaisewithQA/QCManagerfordailyconstructioninspections.
HewillbefullyresponsiblefortechnicalcommunicationandcoordinationwiththeProjectManager/SiteManagerandengineer,developingandreviewingthetechnicaldocumentsuchasdrawings,specificationsandprocedures,interpretingandclarifyingallthetechnicaldetailstotheprojectmembers,providingtechnicaldirectionorinstructiontoqualitypersonnelinvolved,proposingandreviewingcorrectiveactions,conductingfieldengineeringsuchastechnicaladaptation.
ConstructionAdvisor
ConstructionAdvisorwillbethechairmanoftheConstructionManagementTeamthatincludestheSiteManager,ConstructionManager,SHEmanagerandQA/QCManager.
a)ConstructionAdvisorshalloverviewtheconstructionstatusandhighlight/adviseonSafety,QualityandDeliveryaspectswhiletheconstructionmanagerandteamwillcarryoutconstructionexecutionundertheguidanceofSiteManager.
b) ConstructionManagerandteamwillcarryoutconstructionexecutionunderguidanceofSiteManager.ConstructionAdvisorwilloverviewtheconstructionstatusandhighlight/adviseonSafety,QualityandDeliveryaspects.
TheconstructionadvisorwillcoordinatewithEmployerandSupervisingCompanyforbetterachievementofoverallproject.
ConstructionAdvisorwillhaveregularmeetingwiththeconstructionteamtoresolveanyissuesthatmighthavecausedhinderingoftheconstructionprogress.
ConstructionAdvisorshallcoverthedutiesofprojectmanagerduringhisabsence.
Heshallalsobeattendingtheweeklymeetingonbehalfoftheprojectmanager,whowillattendonlyifnecessary.
CAshallalsoberesponsibleforcontrolofmaterialusageandwastage(formaterialssuppliedbyREL).
CAshallassistPMinprocurementservices.
SHEManager.
TheSHEManagershallberesponsiblefortheoverallprojectsafety,healthandenvironmentalprotectionobjective.Hewillbeassistedbysafetyengineerand/orsupervisorsandshallberesponsibletoensurethatallsafety,healthandenvironmentalregulationsandproceduresofOwnersarestrictlycompliedwith.TheSHEManagershall
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 江蘇省揚州市儀征市2019-2020學年八年級下學期期中物理試題【含答案、解析】
- 2025版圖書館圖書出版資助合同規(guī)范模板3篇
- 2025版二手豪華轎車買賣及保養(yǎng)維修增值合同3篇
- 廣東省韶關市2024-2025學年八年級上學期期末地理試題(含答案)
- 2025年度木材廠租地合同與生態(tài)補償協(xié)議書4篇
- 2025年代購物品委托合同
- 2025年醫(yī)療信息軟件開發(fā)協(xié)議書
- 2025年學員就業(yè)服務合作協(xié)議
- 2025年分期付款美食餐飲外賣協(xié)議
- 2025年加盟經(jīng)營合同簽署簽訂
- 2025-2030年中國草莓市場競爭格局及發(fā)展趨勢分析報告
- 奕成玻璃基板先進封裝中試線項目環(huán)評報告表
- 廣西壯族自治區(qū)房屋建筑和市政基礎設施全過程工程咨詢服務招標文件范本(2020年版)修訂版
- 人教版八年級英語上冊期末專項復習-完形填空和閱讀理解(含答案)
- 2024新版有限空間作業(yè)安全大培訓
- GB/T 44304-2024精細陶瓷室溫斷裂阻力試驗方法壓痕(IF)法
- 年度董事會工作計劃
- 《退休不褪色余熱亦生輝》學校退休教師歡送會
- 02R112拱頂油罐圖集
- 2021年新教材重慶生物高考真題(含答案解析)
- 酒店協(xié)議價格合同范文(8篇)
評論
0/150
提交評論