工程ZJTLSG-2標(biāo)段
(12+16+12)m剛構(gòu)連續(xù)梁
施工方案
中國(guó)建筑第八工程局有限公司鄭濟(jì)鐵路(山東段)工程項(xiàng)目部五分部
2023年5月
目錄
1編制依據(jù)......................................................................................................................1
1.1編制依據(jù)...................................................................................................................1
1.2編制范圍...................................................................................................................2
2工程概況......................................................................................................................2
2.1工程概況...................................................................................................................3
2.2工程施工條件............................................................................................................3
交通運(yùn)輸情況..........................................................................................................3
2.2.2當(dāng)?shù)亟ㄖ牧戏植?.........................................................................................3
2.2.3水電燃料等可用資源情況..............................................................................3
2.2.4其他說(shuō)明情況..................................................................................................3
2.2.5工程地質(zhì)條件..................................................................................................4
2.2.6水文地質(zhì)特征..................................................................................................4
2.2.7不良地質(zhì)和特殊地質(zhì)......................................................................................4
2.3剛構(gòu)連續(xù)橋基本概況................................................................................................4
2.3.1茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋簡(jiǎn)介......................................4
2.3.2茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋簡(jiǎn)介......................................5
2.3.3結(jié)構(gòu)形式..........................................................................................................6
2.3.4主要工程數(shù)量..................................................................................................7
3施工安排......................................................................................................................9
3.1現(xiàn)場(chǎng)管理組織............................................................................................................9
3.2現(xiàn)場(chǎng)管理目標(biāo)..........................................................................................................12
4施工進(jìn)度計(jì)劃.............................................................................................................13
4.1茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋工期計(jì)劃......................................13
4.2茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋工期計(jì)劃......................................13
5施工準(zhǔn)備與資源配置計(jì)劃..........................................................................................14
5.1施工準(zhǔn)備.................................................................................................................14
技術(shù)準(zhǔn)備................................................................................................................15
5.1.2施工現(xiàn)場(chǎng)準(zhǔn)備................................................................................................16
1
5.2資源配置計(jì)劃..........................................................................................................17
勞動(dòng)力配置計(jì)劃....................................................................................................17
5.2.2工程主要施工機(jī)具配置計(jì)劃........................................................................17
5.2.3測(cè)量設(shè)備配置計(jì)劃........................................................................................18
5.2.4試驗(yàn)設(shè)備配置計(jì)劃........................................................................................18
5.2.5周轉(zhuǎn)材料配置計(jì)劃........................................................................................18
6施工方法及工藝要求..................................................................................................19
6.1施工總體部署及施工工藝流程..............................................................................20
6.1.1施工總體部署................................................................................................20
6.1.2施工工藝流程................................................................................................20
6.2施工方法及控制要點(diǎn)..............................................................................................21
6.2.1剛臂墩施工....................................................................................................21
6.2.2基礎(chǔ)處理........................................................................................................27
6.2.3支架搭設(shè)........................................................................................................27
6.2.4支座安裝........................................................................................................33
6.2.5主梁模板安裝................................................................................................35
6.2.6堆載預(yù)壓........................................................................................................36
6.2.7主梁鋼筋及預(yù)埋件施工................................................................................39
6.2.8混凝土施工....................................................................................................41
6.2.9支架拆除........................................................................................................44
6.2.10橋面系及附屬工程......................................................................................45
6.3質(zhì)量標(biāo)準(zhǔn).................................................................................................................45
6.3.1模板及支架....................................................................................................45
6.3.2鋼筋...............................................................................................................47
6.3.3混凝土...........................................................................................................50
7進(jìn)度保證措施.............................................................................................................53
7.1工期保證體系..........................................................................................................53
7.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工......................................................................53
7.3工期保證措施..........................................................................................................54
8質(zhì)量保證措施.............................................................................................................56
2
8.1質(zhì)量目標(biāo).................................................................................................................56
8.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工..........................................................................56
8.3質(zhì)量保證體系..........................................................................................................57
8.4質(zhì)量通病及控制措施..............................................................................................58
8.4.1原材料通病及控制措施................................................................................58
8.4.2鋼筋加工與安裝的質(zhì)量通病及控制措施....................................................59
8.4.3模板施工質(zhì)量通病及控制措施....................................................................60
8.4.4混凝土拌和質(zhì)量通病及控制措施................................................................60
8.4.5混凝土澆筑質(zhì)量的控制................................................................................61
8.4.6混凝土養(yǎng)護(hù)質(zhì)量的控制................................................................................62
9安全文明施工措施.....................................................................................................63
9.1職業(yè)健康安全管理目標(biāo)..........................................................................................63
9.2建立安全組織機(jī)構(gòu),明確安全職責(zé)和權(quán)限..........................................................63
9.3職業(yè)健康安全重大危險(xiǎn)源分析..............................................................................64
9.4施工現(xiàn)場(chǎng)安全生產(chǎn)管理制度..................................................................................66
9.4.1班前活動(dòng)記錄................................................................................................66
9.4.2機(jī)械設(shè)備管理制度........................................................................................67
9.4.3特種作業(yè)持證上崗制度................................................................................69
9.4.4安全設(shè)施、設(shè)備驗(yàn)收制度............................................................................69
9.4.5臨時(shí)用電管理制度........................................................................................70
9.5安全保證措施..........................................................................................................71
支架施工安全保證措施........................................................................................71
9.5.2焊接施工安全保證措施................................................................................71
9.5.3吊裝施工安全保證措施................................................................................72
9.5.4機(jī)械設(shè)備安全保證措施................................................................................73
用電安全保證措施................................................................................................73
9.5.6模板施工安全措施........................................................................................74
9.5.7冬期安全措施................................................................................................74
10綠色施工措施...........................................................................................................75
10.1環(huán)境保護(hù)及文明施工管理措施............................................................................76
3
10.1.1環(huán)境保護(hù)及文明施工管理原則..................................................................76
10.1.2環(huán)境保護(hù)主要控制指標(biāo)..............................................................................76
10.2資源利用管理........................................................................................................76
10.2.1資源利用管理目標(biāo)......................................................................................76
10.2.2資源利用管理機(jī)構(gòu)和職責(zé)分工..................................................................76
10.3“五節(jié)”實(shí)施措施....................................................................................................78
10.3.1節(jié)能措施.....................................................................................................78
10.3.2節(jié)材措施.....................................................................................................78
10.3.3節(jié)水措施.....................................................................................................79
10.3.4節(jié)地措施.....................................................................................................79
10.3.5人力節(jié)約措施..............................................................................................79
11成品保護(hù)措施...........................................................................................................79
11.1成品保護(hù)制度........................................................................................................79
11.2成品保護(hù)措施........................................................................................................80
12應(yīng)急預(yù)案...................................................................................................................82
12.1危險(xiǎn)源與風(fēng)險(xiǎn)分析................................................................................................83
12.2應(yīng)急組織機(jī)構(gòu)及職責(zé)............................................................................................83
12.3預(yù)防與預(yù)警措施....................................................................................................86
12.4應(yīng)急響應(yīng)...............................................................................................................86
12.5信息發(fā)布...............................................................................................................89
12.6后期處置...............................................................................................................89
12.7保障措施...............................................................................................................89
12.8應(yīng)急救援路線........................................................................................................92
13新型冠狀病毒肺炎疫情防控預(yù)案.............................................................................92
13.1風(fēng)險(xiǎn)分析...............................................................................................................92
13.2防護(hù)及應(yīng)急救援組織機(jī)構(gòu)及職責(zé)........................................................................93
13.3預(yù)防疫情防控措施................................................................................................96
13.4監(jiān)測(cè)與預(yù)警...........................................................................................................97
13.5應(yīng)急響應(yīng)...............................................................................................................98
13.6后期處置...............................................................................................................99
4
13.7應(yīng)急保障.............................................................................................................100
14附件........................................................................................................................101
14.1施工橫道圖、網(wǎng)絡(luò)圖..........................................................................................101
14.2相關(guān)設(shè)計(jì)圖紙(另附冊(cè))..................................................................................102
14.3檢算書(shū)(另附冊(cè))..............................................................................................102
附圖1茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁施工橫道圖......................103
附圖2茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁施工網(wǎng)絡(luò)圖......................104
附圖3茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁施工橫道圖......................105
附圖4茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁施工網(wǎng)絡(luò)圖......................105
5
6
1編制依據(jù)
1.1編制依據(jù)
表1.1編制依據(jù)
序
類(lèi)別文件名稱編號(hào)
號(hào)
1中華人民共和國(guó)安全生產(chǎn)法
國(guó)家法律法
2規(guī)、行政文中華人民共和國(guó)環(huán)境保護(hù)法
件
3建設(shè)工程質(zhì)量管理?xiàng)l例
4混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范GB50204-2015
5混凝土結(jié)構(gòu)工程施工規(guī)范GB50666-2011
6建設(shè)工程施工現(xiàn)場(chǎng)供用電安全規(guī)范GB50194-2014
7鋼筋混凝土用鋼第2部分:熱軋帶肋鋼筋GB/T1499.2-2018
8鋼筋混凝土用鋼第1部分:熱軋光圓鋼筋GB∕T1499.1-2017
9高速鐵路工程測(cè)量規(guī)范TB10601-2009
10高速鐵路橋涵工程施工技術(shù)規(guī)程Q/CR9603-2015
11高速鐵路橋涵工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)TB10752-2018
規(guī)程、規(guī)范
12鐵路工程結(jié)構(gòu)混凝土強(qiáng)度檢測(cè)規(guī)程TB10416-2023
13鐵路橋梁施工機(jī)械配置技術(shù)規(guī)程Q/CR9225-2015
14鐵路混凝土工程施工技術(shù)規(guī)程Q/CR9207-2017
15鐵路混凝土工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)TB10414-2018
16鐵路混凝土強(qiáng)度檢驗(yàn)評(píng)定標(biāo)準(zhǔn)TBl0425-2023
17鐵路橋涵工程施工安全技術(shù)規(guī)程TB10303-2023
18鐵路工程基本作業(yè)施工安全技術(shù)規(guī)程TB10301-2023
建筑施工承插型盤(pán)扣式鋼管支架安全技術(shù)
19JGJ231-2010
規(guī)程
新建鄭州至濟(jì)南鐵路山東段茌平特大橋(左
20鄭濟(jì)(魯)施橋-05-H
線)
新建鄭州至濟(jì)南鐵路山東段茌平特大橋(右
21鄭濟(jì)(魯)施橋-05-H
線)
22鐵路橋梁球型支座(TJQZ)TJQZ-8360
設(shè)計(jì)文件
23鐵路綜合接地系統(tǒng)通號(hào)(2016)9301
單線無(wú)砟軌道鋼筋砼剛構(gòu)連續(xù)梁
24鄭濟(jì)橋通-I-03
(12+16+12)m
加強(qiáng)新型冠狀病毒感染的肺炎疫情監(jiān)控工
25
作的通知
1
序
類(lèi)別文件名稱編號(hào)
號(hào)
262018】872
27國(guó)家文件新型冠狀病毒肺炎防控方案國(guó)家衛(wèi)健委
28地方性文件山東省突發(fā)公共衛(wèi)生事件一級(jí)響應(yīng)
29區(qū)域性大氣污染物綜合排放標(biāo)準(zhǔn)DB37/2376-2023
其他
30類(lèi)似項(xiàng)目的施工經(jīng)驗(yàn)
1.2編制范圍
本方案適用于xx站前工程ZJTLSG-2標(biāo)茌平特大橋(左線)1113#-1116#墩、茌平
特大橋(右線)1115#-1118#墩規(guī)劃西關(guān)街(12+16+12)m剛構(gòu)連續(xù)橋施工。
2工程概況
2
2.1工程概況
xx工程ZJTLSG-2DK109+179.16(茌平特大橋左線905#橋墩)~DK119+508.91(跨
316特大橋左線濟(jì)南臺(tái)),正線線路長(zhǎng)度9.94公里。
2.2工程施工條件
交通運(yùn)輸情況
五分部線路所經(jīng)區(qū)域路網(wǎng)交錯(cuò),交通運(yùn)輸便利,線路經(jīng)過(guò)地區(qū)國(guó)道、省道四通八達(dá),
各縣鄉(xiāng)均有公路相通,村村通公路工程在各鄉(xiāng)鎮(zhèn)開(kāi)展,村級(jí)公路大幅增加,并且標(biāo)準(zhǔn)有
所提高,已形成由高速公路、國(guó)道、省道、縣級(jí)公路構(gòu)成的縱橫交錯(cuò)、多層次的公路網(wǎng)
絡(luò),為五分部材料運(yùn)輸提供了便利條件。
區(qū)域內(nèi)主要國(guó)道、省道有G309、S706、S804、S316、S258、S254;高速公路有
G309X044、鳳凰路、閆梁路、聊鄭路、湖南路等。省道路面寬度為約20m,縣鄉(xiāng)道路
面寬度為7~14m,大部分道路為瀝青路面,部分土質(zhì)鄉(xiāng)間路寬度在4~5m之間,經(jīng)過(guò)
拓寬、整修后可以作為臨時(shí)便道加以利用。
2.2.2當(dāng)?shù)亟ㄖ牧戏植?/p>
1施工用砂
計(jì)劃采用泰安大汶河的河砂。
2石料
計(jì)劃采用平陰地區(qū)的石料。
3水泥
水泥擬定來(lái)源為聊城山水水泥。
2.2.3水電燃料等可用資源情況
1施工用水
五分部施工范圍內(nèi)無(wú)大的河流,施工用水可用灑水車(chē)運(yùn)至現(xiàn)場(chǎng)作為施工用水。
2施工用電
本工程附近其它跨箱梁采用預(yù)制架橋機(jī)架橋施工。考慮到只有一個(gè)剛構(gòu)連續(xù)橋鋼筋
安裝、混凝土澆筑等需要用電,本著用電量較小、用電靈活的原則,現(xiàn)場(chǎng)每個(gè)現(xiàn)澆剛構(gòu)
連續(xù)橋處配置一臺(tái)100kW發(fā)電機(jī)作為臨時(shí)用電電源。
3油燃料
施工所需油燃料可由當(dāng)?shù)厥凸竟?yīng)。
2.2.4其他說(shuō)明情況
3
1五分部沿線目前無(wú)典型的地方流行病,地方各級(jí)衛(wèi)生防疫系統(tǒng)健全,防治措施
行之有效。但由于流動(dòng)人口眾多,流感、甲肝、乙肝等常見(jiàn)傳染病仍然存在,施工時(shí)應(yīng)
注意保持生活和生產(chǎn)環(huán)境衛(wèi)生,堅(jiān)持殺蟲(chóng)滅鼠,注射流感、甲肝、乙肝等相應(yīng)疫苗。
2五分部沿線村莊密集,居民較多,該地區(qū)保留著較多的中國(guó)傳統(tǒng)文化和傳統(tǒng)民
俗,施工期間應(yīng)尊重當(dāng)?shù)仫L(fēng)俗習(xí)慣,遵守鄉(xiāng)規(guī)民約,處理好與當(dāng)?shù)鼐用竦年P(guān)系。
2.2.5工程地質(zhì)條件
nl
五分部橋址區(qū)上覆土層主要為:第四系全新統(tǒng)沖擊層(Q4)淤泥質(zhì)黏土、黏土、
al
粉質(zhì)黏土、粉土、粉砂、細(xì)砂及中砂;第四系上更新統(tǒng)沖積層(Q3)黏土、粉質(zhì)黏土、
ml
粉土、粉砂、細(xì)砂及中砂。局部表層為第四系全新統(tǒng)人工堆積層(Q4)素填土、填筑
土、雜填土。
2.2.6水文地質(zhì)特征
DK113+379.86~DK116+296.13橋址區(qū)范圍內(nèi)地表水零星分布于小水溝及水渠內(nèi)。
地下水類(lèi)型為第四系孔隙潛水,受大氣降水及地下水側(cè)向徑流補(bǔ)給,以地下水側(cè)向徑流
和人工開(kāi)采為排泄條件,勘測(cè)期間地下水位埋深4.5~7.7m(高程24.79~27.92m),水位季
節(jié)變化幅度1~3m,局部地段受人工抽水影響,水位變幅大于3m。
2.2.7不良地質(zhì)和特殊地質(zhì)
填筑土:黃褐色~灰褐色,中密~密實(shí),成分以黏性土、中細(xì)砂及碎石為主。
雜填土:主要由煤灰、粉土、黏性土、生活垃圾和建筑垃圾等組成,該層僅在
17-ZD-6341及17-ZD-6371孔表層分布,層厚1.8~5.5m。
淤泥質(zhì)粉質(zhì)黏土:褐灰色~黑褐色,流塑~軟塑,勘測(cè)期間揭示層厚0.3~1.5m。
2.3剛構(gòu)連續(xù)橋基本概況
2.3.1茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋簡(jiǎn)介
1113#-1116#墩所處區(qū)域?yàn)樵瓲钷r(nóng)田,地勢(shì)平坦,原地面標(biāo)高。橋墩墩高7m,剛構(gòu)
連續(xù)梁底距離原地面約6.2m,剛構(gòu)連續(xù)橋?yàn)閱畏?、橋面寬度?.4m。中墩正交,中墩
與梁部固結(jié),橋臺(tái)設(shè)活動(dòng)支座。
4
圖2.3.1茌平特大橋(左線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁布置
2.3.2茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋簡(jiǎn)介
1115#-1118#墩所處區(qū)域?yàn)樵瓲钷r(nóng)田,地勢(shì)平坦,原地面標(biāo)高約32.77m。橋墩墩高
7m,剛構(gòu)連續(xù)梁底距離原地面約6.2m,剛構(gòu)連續(xù)橋?yàn)閱畏蛎鎸挾葹?.4m。中墩正
交,中墩與梁部固結(jié),橋臺(tái)設(shè)活動(dòng)支座。
圖2.3.2茌平特大橋(右線)規(guī)劃西關(guān)街剛構(gòu)連續(xù)橋梁布置
5
2.3.3結(jié)構(gòu)形式
本剛構(gòu)連續(xù)橋計(jì)算跨度為(12+16+12)m,邊支座中心線至梁端0.55m,梁全長(zhǎng)
41.1m,橋梁寬7.4m,跨中截面最低點(diǎn)處梁高1.0m,墩頂截面最低點(diǎn)處梁高1.5m。橋
墩與主梁正交,1、2號(hào)墩墩高均為7.0m,梁端與線路正交,剛臂墩橫橋向與梁底同寬,
順橋向壁厚為0.9m。
。
圖2.3.3-1剛構(gòu)連續(xù)橋面布置示意
圖2.3.3-2剛構(gòu)連續(xù)橋縱斷面示意
6
圖2.3.3-3剛構(gòu)連續(xù)橋平面示意
本橋?yàn)閱尉€,位于直線,左線位于豎曲線上,右線位于平坡。梁體、剛臂墩、防護(hù)
墻以及電纜槽蓋板均采用C40混凝土,碳化環(huán)境T2級(jí)。主梁采用HPB300、HRB400鋼
筋,剛臂墩采用HRB400鋼筋,施工時(shí)鋼筋保護(hù)層必須滿足凈保護(hù)層厚度除頂板頂層為
30mm外,其余均為35mm的要求。支座采用鐵路橋梁球形支座,型號(hào)為
TJQZ-8360-2500-ZX-0.15g。本橋采用CRTSⅢ型板式無(wú)砟軌道,軌頂至梁頂0.738m。
2.3.4主要工程數(shù)量
表2.3.4單個(gè)剛構(gòu)連續(xù)梁主要工程數(shù)量
序號(hào)部位材料及規(guī)格單位數(shù)量
1C40鋼筋混凝土m3241.6
梁體
2HRB400鋼筋/HPB300鋼筋t53.65/0.016
3C40鋼筋混凝土m375.6
剛臂墩
4HRB400鋼筋t10.5
5支座TJQZ-8360-2500-ZX-0.15g個(gè)4
6聚氨酯防水涂料m2127.1
橋面防水層
7高聚物改性瀝青防水卷材m2180.4
8橋面保護(hù)層C40纖維混凝土m318.1
9梁端防水聚氨酯防水涂料m211.2
10C40鋼筋混凝土m313.7
11防護(hù)墻HRB400鋼筋t5.882
12PVC套管m22.9
13C40鋼筋混凝土m311.9
豎墻
14HRB400鋼筋t3.652
7
序號(hào)部位材料及規(guī)格單位數(shù)量
15C40鋼筋混凝土m34.6
蓋板
16HPB300鋼筋t0.704
17C40鋼筋混凝土m311.5
18HPB300鋼筋t0.577
19遮板HRB400鋼筋t1.182
20Q235鋼料t0.153
21U型螺栓t0.091
22C40鋼筋混凝土m319.2
23欄桿HRB400鋼筋t0.817
24HPB300鋼筋t3.572
25耐候鋼t0.055
26彈性體伸縮縫防水橡膠條t0.017
27錨固鋼筋t0.01
28HPB300鋼筋t0.41
綜合接地接地端子
29個(gè)11
(GB00Cr17Ni14M02)
30外徑110mmPVC泄水管m95.0
31PVC管蓋個(gè)12
橋面排水
32PVC管篦個(gè)12
33管卡套69
34Q235鋼板t0.177
35HRB400t0.028
36橡膠板Kg4.56
防落梁擋塊
37螺栓M27個(gè)10
38Φ50套筒個(gè)10
39M12螺栓、螺母?jìng)€(gè)4
40C50混凝土m30.9
41M24螺栓t0.019
42接觸網(wǎng)支柱M39螺栓t0.076
43HRB400t0.755
44鋼料t0.123
8
3施工安排
3.1現(xiàn)場(chǎng)管理組織
為完成本工程任務(wù),加強(qiáng)項(xiàng)目施工標(biāo)準(zhǔn)化管理,確保工程建設(shè)工期、質(zhì)量、安全目
標(biāo),項(xiàng)目部組建橋梁施工的架子二隊(duì),由生產(chǎn)經(jīng)理鄒金瀟負(fù)責(zé),技術(shù)由總工程亮負(fù)責(zé),
由工程技術(shù)部、安全部、質(zhì)量部、財(cái)務(wù)資金部、計(jì)劃合同部、物資設(shè)備部、征地拆遷部、
綜合辦公室、測(cè)量部、試驗(yàn)室共10個(gè)職能部室配合,現(xiàn)場(chǎng)由王世國(guó)等專業(yè)工程師負(fù)責(zé)。
現(xiàn)場(chǎng)組織機(jī)構(gòu)見(jiàn)下圖:
項(xiàng)目經(jīng)理
(游珈驊)
商務(wù)經(jīng)理生產(chǎn)經(jīng)理項(xiàng)目總工協(xié)調(diào)經(jīng)理
(張龍)(鄒金瀟)(程亮)(訾乃強(qiáng))
綜合辦公室物資設(shè)備部計(jì)劃合同部工程技術(shù)部測(cè)量部安全部質(zhì)量部財(cái)務(wù)資金部征地拆遷部工地試驗(yàn)室
(王學(xué)寧)(周長(zhǎng)江)(劉慶冰)(喬守靖)(朱友基)(王建耀)(張建立)(李杰)(商廣彬)(劉海洋)
第二架子隊(duì)
(王世國(guó))
圖3.1現(xiàn)場(chǎng)組織結(jié)構(gòu)
表3.1崗位職責(zé)分工
序
部門(mén)職責(zé)
號(hào)
1)負(fù)責(zé)五分部全過(guò)程施工組織、指導(dǎo)、協(xié)調(diào)與監(jiān)控,對(duì)建設(shè)單位負(fù)全責(zé)。
2)建立、實(shí)施與保持質(zhì)量、安全、進(jìn)度、投資、文明、穩(wěn)定、環(huán)境和職業(yè)
1項(xiàng)目經(jīng)理健康安全綜合管理體系。
3)全面履行施工合同,確保按期、優(yōu)質(zhì)、安全、高效地完成工程任務(wù)與缺
陷修復(fù)工作,達(dá)到顧客滿意。
1)貫徹執(zhí)行國(guó)家、行業(yè)、地方政府有關(guān)工程建設(shè)的方針、政策、法律、法
規(guī)、標(biāo)準(zhǔn)、規(guī)范。
2)負(fù)責(zé)項(xiàng)目工程技術(shù)管理工作。組織、參與工程項(xiàng)目技術(shù)交底、施工組織
組設(shè)計(jì)的編制,組織圖紙會(huì)審和專項(xiàng)技術(shù)方案的編制工作。
3)參與編制工程項(xiàng)目質(zhì)量計(jì)劃、工程創(chuàng)優(yōu)規(guī)劃和專項(xiàng)安全技術(shù)措施,解決
2項(xiàng)目總工
施工生產(chǎn)過(guò)程中存在的技術(shù)問(wèn)題。
4)負(fù)責(zé)對(duì)工程施工技術(shù)組織科技攻關(guān),積極推廣使用新技術(shù)、新工藝、新
材料、新設(shè)備,提高工程項(xiàng)目施工的科技含量。
5)組織、參與工程項(xiàng)目的變更設(shè)計(jì)工作。
6)負(fù)責(zé)組織編寫(xiě)工程技術(shù)總結(jié)。
1)協(xié)助項(xiàng)目經(jīng)理抓好現(xiàn)場(chǎng)管理,對(duì)管理體系文件的貫徹實(shí)施情況進(jìn)行檢查
3生產(chǎn)經(jīng)理和監(jiān)督。
2)有效組織施工生產(chǎn),確保質(zhì)量、進(jìn)度、安全等既定目標(biāo)的實(shí)現(xiàn)。
9
序
部門(mén)職責(zé)
號(hào)
3)協(xié)調(diào)各方因素,確保實(shí)現(xiàn)工程環(huán)境、職業(yè)健康、環(huán)保等目標(biāo),實(shí)現(xiàn)優(yōu)質(zhì)
服務(wù)。
4)負(fù)責(zé)施工用地的征拆工作,確保施工的順利進(jìn)行。
1)認(rèn)真研究與分析合同條款,組織商務(wù)合同交底。
2)編制招標(biāo)文件、合同,組織招標(biāo)工作,主持項(xiàng)目合同評(píng)審:負(fù)責(zé)報(bào)價(jià)審
核、合同簽訂、合同管理及結(jié)算工作。
4商務(wù)經(jīng)理3)負(fù)責(zé)項(xiàng)目經(jīng)營(yíng)報(bào)價(jià)、進(jìn)度款結(jié)算及工程竣工結(jié)算;負(fù)責(zé)編制請(qǐng)款單、結(jié)
算單;負(fù)責(zé)編制項(xiàng)目預(yù)算成本實(shí)施計(jì)劃并負(fù)責(zé)檢查計(jì)劃的落實(shí)。
4)掌握施工動(dòng)態(tài),及時(shí)進(jìn)行成本分析,為施工提供決策依據(jù);收回費(fèi)用。
5)負(fù)責(zé)審定物資采購(gòu)供應(yīng)計(jì)劃、物資需用計(jì)劃及資金使用計(jì)劃。
做好征地拆遷及外部協(xié)調(diào)工作,為項(xiàng)目開(kāi)展工作順利施工打好基礎(chǔ)。外
5協(xié)調(diào)經(jīng)理
部關(guān)系:指揮部征拆辦,當(dāng)?shù)卣?/p>
1)負(fù)責(zé)按照項(xiàng)目經(jīng)理部制
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025農(nóng)村信用合作社聘用合同樣本
- 二零二五年度國(guó)際貨物出口合同范文:非洲新興市場(chǎng)合作項(xiàng)目
- 2025年度公廁工程承包合同書(shū)(含社區(qū)共建)3篇
- 二零二五年度公司施工隊(duì)鋼結(jié)構(gòu)工程施工合作協(xié)議3篇
- 二零二五年度全新高空橋梁施工意外事故免責(zé)責(zé)任書(shū)3篇
- 二零二五年度智能倉(cāng)儲(chǔ)物流系統(tǒng)采購(gòu)合同模板2篇
- 二零二五年度消防隊(duì)伍后勤保障服務(wù)合同3篇
- 2025年度農(nóng)村出租房租賃與農(nóng)村電子商務(wù)運(yùn)營(yíng)服務(wù)合同
- 2025年度智慧城市建設(shè)項(xiàng)目合同2篇
- 二零二五年度農(nóng)村集體土地房屋產(chǎn)權(quán)轉(zhuǎn)讓合同下載
- 二零二四年風(fēng)力發(fā)電項(xiàng)目EPC總承包合同
- 文化傳媒企業(yè)資質(zhì)掛靠合作協(xié)議書(shū)
- 2024年凈化車(chē)間工程的合同
- 2024年山東省公務(wù)員錄用考試《行測(cè)》真題及答案解析
- 122首初中文言古詩(shī)文艾賓浩斯背誦表
- 2024年時(shí)政考點(diǎn)大全(135條)
- 咳嗽的診斷與治療指南(2021版)解讀
- 機(jī)動(dòng)車(chē)駕駛員考試《科目一》試題與參考答案(2024年)
- 2024年四年級(jí)英語(yǔ)上冊(cè) Module 8 Unit 2 Sam is going to ride horse說(shuō)課稿 外研版(三起)
- 高中地理人教版(2019)必修第一冊(cè) 全冊(cè)教案
- 2024年新人教版七年級(jí)上冊(cè)地理課件 第二章 地圖 第二節(jié) 地形圖的判讀
評(píng)論
0/150
提交評(píng)論