中科新經(jīng)濟科創(chuàng)園基礎設施項目(D-6地塊)

工程總承包(EPC)

3號公寓樓(編號4)塔吊安拆

專項施工方案

編制單位:中科新經(jīng)濟科創(chuàng)園基礎設施項目(D-6地塊)

工程總承包(EPC)項目部

編制人:

日期:年月日

1

目錄

目錄..............................................................................................................................................................2

1方案編制依據(jù)..............................................................................................................................................4

2工程概況......................................................................................................................................................4

3塔吊選型及布置..........................................................................................................................................6

3.1塔吊選型...........................................................................................................................................6

3.2塔吊平面布置...................................................................................................................................6

3.3塔吊基本參數(shù)...................................................................................................................................7

4塔吊基礎設計及施工..................................................................................................................................8

4.1基礎布置..............................................................................................................................................8

4.2基礎的設置與制作..............................................................................................................................9

固定式基礎位置選擇......................................................................................................................13

固定式基礎載荷..............................................................................................................................14

基礎的制作......................................................................................................................................14

5施工安排....................................................................................................................................................15

5.1管理人員配置及職責.....................................................................................................................15

5.2項目管理目標.................................................................................................................................16

5.3勞務資源安排.................................................................................................................................16

5.4工程施工重點和難點分析及應對措施.........................................................................................16

6施工進度計劃............................................................................................................................................17

7安拆方法....................................................................................................................................................17

7.1塔吊安裝順序.................................................................................................................................17

7.2塔吊施工工程管理目標.................................................................................................................17

7.3質(zhì)量、安全、環(huán)保管理措施.........................................................................................................18

7.4塔吊部件重量表...............................................................................................................................18

7.5安裝機械選擇及汽車吊站位.........................................................................................................22

7.5.1汽車吊站位..........................................................................................................................22

7.5.2汽車吊參數(shù)表......................................................................................................................23

7.6電源設置.........................................................................................................................................24

7.7施工人員配置.................................................................................................................................24

7.7.1勞動力組織及崗位職責......................................................................................................24

7.8吊索具和專用工具的配備.............................................................................................................24

7.8.1施工機具準備......................................................................................................................25

7.8.2主要吊索的選用..................................................................................................................25

7.9塔機安裝前準備工作及塔吊安裝工藝程序.................................................................................27

7.9.1塔吊安裝前準備工作..........................................................................................................27

7.9.2塔吊安裝工藝......................................................................................................................28

7.10安全裝置的調(diào)試及附著頂升.......................................................................................................32

7.10.1塔機組裝好后,應依次進行下列檢驗............................................................................32

7.10.2頂升程序............................................................................................................................32

7.10.3塔吊安裝后的檢查............................................................................................................33

7.10.4塔吊安裝后的驗收............................................................................................................35

2

7.11重大危險源及安全技術措施.......................................................................................................35

7.11.1重大危險源清單及控制措施............................................................................................35

7.11.2塔吊安裝安全操作規(guī)程....................................................................................................36

7.11.3塔吊頂升安全操作規(guī)程....................................................................................................37

7.12塔吊拆除概況.................................................................................................................................38

7.12.1塔機拆除工況....................................................................................................................38

7.12.1塔機拆除說明....................................................................................................................38

8塔吊安拆作業(yè)應急預案............................................................................................................................39

8.1總則.................................................................................................................................................39

8.2危險源與風險分析.........................................................................................................................39

8.3.1成立應急救援的獨立領導小組..........................................................................................39

8.3.2應急組織的分工職責..........................................................................................................40

8.4預防與預警.....................................................................................................................................41

8.4.1危險源監(jiān)控..........................................................................................................................41

8.4.2預警行動..............................................................................................................................41

8.4.3信息報告與處置..................................................................................................................42

8.5應急響應.........................................................................................................................................42

8.5.1啟動本預案..........................................................................................................................42

8.5.2趕赴事故現(xiàn)場....................................................................................................................42

8.5.3現(xiàn)場救援處置......................................................................................................................42

8.6應急結束.........................................................................................................................................44

8.7后期處理.........................................................................................................................................44

8.8應急保障.........................................................................................................................................44

8.8.1通信與信息保障..................................................................................................................44

8.8.2物資保障..............................................................................................................................44

8.8.3經(jīng)費保障......................................................................................................................................45

8.9培訓與演練.....................................................................................................................................45

8.10獎懲...............................................................................................................................................45

8.11附則...............................................................................................................................................45

9附件及附圖................................................................................................................................................45

3

1方案編制依據(jù)

表1方案編制依據(jù)

序號類別文件名稱編號

國務院令第393

1建設工程安全生產(chǎn)管理條例

中華人民共和國

2建筑起重機安全監(jiān)督管理規(guī)定建設部令第166

國家行政文中華人民共和國

3件危險性較大的分部分項工程安全管理規(guī)定住房和城鄉(xiāng)建設

部令第37號

中華人民共和國

4氣象災害防御條例國務院令第570

5施工現(xiàn)場安全防護用具及機械設備使用監(jiān)督管理規(guī)定建[1998]164號

6建筑施工塔式起重機安裝、使用、拆卸安全技術規(guī)程JGJ196-2010

7塔式起重機設計規(guī)范GBT13752-2017

8塔式起重機混凝土基礎工程技術規(guī)程JGJ/T187-2023

8國家標準塔式起重機安全規(guī)程GB5144-2006

9塔式起重機GBT5031-2023

10建筑施工高處作業(yè)安全技術規(guī)范JGJ80-2016

11建筑機械使用安全技術規(guī)程JGJ33-2012

濟建發(fā)〔2017〕76

12塔式起重機安全管理十條

《TCt7520塔式起

13塔式起重機說明書

重機使用說明書》

70t汽車吊起重性

14其他輔助起重設備性能參數(shù)

能參數(shù)

結構圖紙;建筑圖

15建筑及結構圖紙

16地勘報告本項目地勘報告

2工程概況

中科新經(jīng)濟科創(chuàng)園基礎設施項

工程名稱工程性質(zhì)工程總承包

目(D-6地塊)

建設規(guī)模約4.9億元工程地址濟陽區(qū)崔寨街道

總占地面積37900平方米總建筑面積約105300平方米

中科新經(jīng)濟科創(chuàng)園基礎設施項目(D-6

項目承包地塊)工程總承包(EPC)相關設計、

建設單位

范圍采購、施工、調(diào)試、驗收、保修及相

關手續(xù)辦理、配合移交等工程總承包。

4

設計單位中建八局第一建設有限公司主要分包工程

全過程咨詢工期540

總承包單位中建八局第一建設有限公司安全無死亡及重傷

工程主要功能

公寓、學生宿舍、配套商業(yè)及其他配套用房。

或用途

3號樓樓座基本情況

樓座樓高剖面

地下1層,地上14層

建筑高度48.3米

3號樓1~2層層高4.2米

標準層層高3.3米

框架剪力墻結構

地質(zhì)參數(shù)層序土層名預應力管樁泥漿護壁鉆孔灌注樁后注漿增強系數(shù)

5

稱極限側阻極限端阻極限側阻側阻力端阻力

極限端阻

力力力增強系增強系

力標準值

標準值標準值標準值數(shù)數(shù)

q(kPa)

pkbb

qsik(kPa)qpk(kPa)qsik(kPa)sip

②黏土38361.4

②-1粉土35331.4

③黏土40381.4

③-1粉土37351.4

④粉質(zhì)黏44421.4

④-1粉土43411.4

⑤粉細砂451600435001.62.4

⑤-1粉質(zhì)黏451250434001.42.2

⑥粉質(zhì)黏491400474501.42.2

⑥-1粉土501400485001.42.2

⑦細砂513000499001.62.4

⑦-1粉質(zhì)黏521800505501.42.2

⑧粉質(zhì)黏541900526001.42.2

⑧-1粉土602200586501.42.2

⑨粉質(zhì)黏702300687501.42.2

⑨-1粉土662400647001.42.2

⑩粉質(zhì)黏722500708001.42.2

?粉質(zhì)黏7836007612001.42.2

3塔吊選型及布置土

3.1塔吊選型

塔吊選型考慮滿足鋼筋、模板、預制構件等吊重需求,于3#公寓樓北側布置1臺

TCT7520塔吊,現(xiàn)場標號為4#,為保證覆蓋無盲區(qū),群塔作業(yè)無影響,塔吊初始安裝高

度為19.5m(1節(jié)基礎節(jié)+4節(jié)加強節(jié)),初始使用高度為39米,最終安裝高度69m(基

礎節(jié)+20節(jié)標準節(jié))。塔吊臂長為60m。

起重臂方向朝西,塔機總功率:117kw(不含頂升電機)。

3.2塔吊平面布置

6

3#STT153R=60MH=60M

54#TCT7520R=60MH=69M

0

.

4

66.54

1

8

.

7

1

2#T7020R=55MH=54M

5#S315K16R=55MH=75M

3

0

.

5

6#S315K16R=50H=54M

辦公2F辦公2F

1#T7020R=55MH=48M

3.3塔吊基本參數(shù)

1.初始安裝基礎節(jié)和4節(jié)加強節(jié)后,安裝塔機回轉等主機部分,頂升至作業(yè)高度39m

(最終安裝高度69米,一道附著)。

2.安裝工作幅度:60米

3.公稱起重力矩:200噸·米

4.最大起重量16噸

5.總功率:107.0KW

6.工作溫度:-20℃~40℃,風速小于6級

7

以下是安裝60米起重臂時的起重性能:

4塔吊基礎設計及施工

4.1基礎布置

1)塔機現(xiàn)場布置由工程施工項目部根據(jù)施工需要和現(xiàn)場具體情況總體安排。

2)注意確保塔機回轉時尾部與周圍建筑物及外圍設施間安全距離不小于2m,以及與

架空線、塔機保持安全距離。

3)塔機布置必須考慮防碰撞需要,滿足規(guī)范要求:

4)在有建筑物的場所,塔機的尾部與周圍建筑物及其外圍施工設施之間的安全距離

不小于2m。

5)多塔在同一區(qū)域安裝時,兩臺起重機之間的最小架設距離,應保證低位塔機臂架

端部與高位塔機塔身之間至少有2m的距離,高位塔機的最低位置的部件(吊鉤升至最高

點或平衡重的最低部位)與低位塔機最高位置部件之間的垂直距離不得小于2m。

6)塔機布置的最小空間距離應參照以下公式核算,必須保證安全距離不小于2m。

8

7)最小定位尺寸≥起重臂端部與基礎(塔身)中心距離或平衡臂+安全距離2m+外架

寬度(若有外架或外架后拆除時)。

8)塔身、起重臂、平衡臂平行于建筑物下降時,均應有一定安全距離,定位時,參

照下式計算:

9)最小定位尺寸≥塔機各部結構寬度(從中線起計算)+安全距離+外架寬度(若

有外架或外架后拆除時)。

10)安裝現(xiàn)場場地應滿足以下要求:

放置起重臂全長的窄長范圍內(nèi)的場地應平整,無雜物和障礙物,以便于平衡臂、起

重臂等部件在地面組裝及吊裝。

12)汽車吊行走所經(jīng)過路線寬度不得小于5米,輪距3米,轉彎處圓弧半徑不得小

于12米。汽車吊行走或站位區(qū)任意一段坡度不得大于1:5。

4.2基礎的設置與制作

本工程4#塔機基礎位于6#公寓樓南側,基礎形式為樁基基礎,承臺頂標高和筏板柱

墩墊層底標高為統(tǒng)一標高,為避免造成積水,承臺結構頂標高高于筏板30mm。根據(jù)說明

書要求,基礎大小為6000×6000×1600mm,具體基礎配筋如附圖所示。預埋固定支腿的

埋深740mm,底部用我公司制作的專用馬凳支撐并固定牢固。

9

4.2.1計算說明:

一、樁型:

二、計算書

1、自重(包括配重)取最大值Fgk=1173KN。

2、水平剪力取最大值Fhk=168KN。

3、塔吊傾覆力距取最大值Mk=5226KN?m,塔身寬度B=2m。

4、承臺混凝土強度C35,寬度Bc=6.0m,承臺厚度Hc=1.7m。樁距如下圖所示。

5、鉆孔灌注樁直徑,混凝土強度等級為C35。

6、計算簡圖

10

圖中x軸的方向是隨機變化的,設計計算時應按照傾覆力矩M最不利方向進行驗算(即

承臺對角線方向)。

1.3樁頂豎向力特征值的計算(4根樁基)

2

Qkmax=(F+G)/n+(M+Fvh)yi/∑yi

2

Qmin=(F+G)/n-(M+Fvh)yi/∑yi

其中n──樁基數(shù)量;

Qkmax、Qkmin──角樁樁頂最大、最小豎向力特征值;

7、塔機受力計算

Gk──承臺的自重標準值,Gk=25×6.0×6.0×1.6=1440kN;

h──承臺高度(m),h=1.6m;

經(jīng)計算得到單樁樁頂豎向最大壓力特征值:

2

Qkmax=(F+G)/n+(M+Fvh)yi/∑yi

=(1173+1440)/4+(5226+168×1.7)/5.66

=675.75+973.78=1650kN

經(jīng)計算得到單樁樁頂豎向壓力最小特征值(正值標示塔機對樁基沒有拉力,負值表示樁

基受拉力)

2

Qkmin=(F+G)/n-(M+Fvh)yi/∑yi

=(1173+1530)/4+(5226+168×1.7)/5.66

=675.75-973.78=-298kN

因最小壓力為負值,所以此時單樁有抗拔的力,數(shù)值為298kN。

對比以上塔機受力計算,綜合考慮,取拉力最大值和壓力最大值。

要求單根樁基抗壓特征值為1650N。抗拔為-298kN。

經(jīng)計算,滿足要求。

11

×

×

0

4

7

0

0

1

×

×

×

L:6000cmI:6000cm山東中誠機械租賃有限公司

(材料標記)

H:1600cmV:57.6m3標記處數(shù)更該文件號簽字日期

樁基基礎設計標準化塔機預埋腳柱式固定樁基

校對審定圖樣標記重量比例基礎配筋圖

審核

工藝日期

TCT7520塔機基礎配筋圖

12

4.2.1基礎設計說明:

4.2.1固定式基礎位置選擇

基礎位置必須保證塔機回轉時與其它物體的安全距離,同時方便汽車吊吊裝作業(yè)、

塔機部件堆放以及拆卸等

13

樁基礎的承載力應滿足塔吊基礎載荷要求。

基礎在任何情況下不能積水。

塔機基礎位于3#公寓樓北側,塔機基礎與車庫筏板重疊一部分,做塔機基礎的時候

可以把干涉的柱墩和塔機基礎一起澆筑,預留出車庫筏板搭接的鋼筋,防水從塔機基礎

底部穿過,后澆帶部分用止水鋼板處理好。

4.2.2固定式基礎載荷

固定式基礎載荷表

表1固定式基礎載荷表

基礎的制作

根據(jù)獨立安裝高度要求基礎立面圖和基礎平面圖選用、制作基礎。制作的基礎應能

承受塔機在各種情況下的最大載荷,滿足塔機抗傾翻穩(wěn)定性要求。如使用環(huán)境局限不能

滿足要求時,改制的基礎必須進行穩(wěn)定性和地耐力驗算?;A由工程施工項目部制作完

成。

1澆注混凝土基礎所需條件

1)預埋節(jié)、預埋馬凳;

2)接地鐵芯及接地導線;

3)1個基礎工裝;

14

4)水準儀1套。

2基礎技術要求

1)混凝土標號:≥C35;

2)鋼筋:Ⅱ級螺紋鋼;

3)塔機安裝時混凝土強度應達到80%,使用時砼強度應為100%;

4)鋼筋混凝土密度:2400kg/m3;

5)混凝土保護層厚度:50mm;

6)預埋支腿檐口水平度偏差不得超出1‰;

7)接地電阻(阻值≤4歐姆)。

8)基礎找平要求:基礎平整度控制在2.5‰以內(nèi)。

基礎驗收

塔吊基礎鋼筋綁扎完成后,由項目部進行驗收,驗收通過后進行下一步施工,主要

驗收內(nèi)容為:

1)檢查鋼筋綁扎、錨固情況;

2)檢查塔吊基礎四周止水鋼板焊接情況;

3)檢查塔吊基礎鋼筋預留尺寸。

塔吊安裝前,塔吊公司負責人和項目部負責人共同參與對塔吊基礎進行驗收,塔吊

基礎驗收合格后,方可安裝塔吊。塔吊基礎驗收時,項目部需提供以下資料:

1)項目地勘報告;

2)塔吊基礎鋼筋材質(zhì)單;

3)塔吊基礎強度報告;

4)吊基礎預埋件水平度測量報告。

5)基礎驗收合格后,塔吊安裝單位提供基礎驗收表。驗收表由安裝單位、使用單位、

監(jiān)理單位三方驗收并蓋章。

5施工安排

5.1管理人員配置及職責

序號姓名崗位名稱職責

1吳鵬項目經(jīng)理負責塔吊安拆過程對外關系,負責塔吊安裝過程安全監(jiān)督

15

序號姓名崗位名稱職責

1、負責塔吊安拆方案的審核

2、負責塔吊安拆過程方案的落實和檢查,確?,F(xiàn)場按照方案執(zhí)

2亓志剛項目總工行

3、負責聯(lián)系塔吊進場事宜

4、負責塔吊安拆過程各家單位配合協(xié)調(diào)

3胡金成商務經(jīng)理塔吊安拆過程資金總協(xié)調(diào)

1、全面負責塔吊安拆過程的安全監(jiān)督

2、對接當?shù)匕脖O(jiān)站關于塔吊安拆過程的要求

4江勇安全部

3、負責塔吊進場安全管理、塔吊司機管理、安裝工執(zhí)證上崗情

1、負責現(xiàn)場的統(tǒng)一安排和現(xiàn)場指揮

5余家樂專業(yè)工程師

2、負責現(xiàn)場施工監(jiān)督協(xié)調(diào)

1、塔吊安裝前地腳螺栓地位復核

2、塔吊安拆過程垂直度校核

6張士坤測量工程師

3、塔吊安裝完后垂直度檢查

4、塔吊使用過程定期檢查塔身垂直度

7楊笑天質(zhì)量部對塔吊構件進場質(zhì)量進行驗收檢查

租賃單位技術

8李學丁全面負責塔吊安拆施工過程中相關事宜

負責人

5.2項目管理目標

項目管理目標名稱目標值

工期3天

質(zhì)量符合規(guī)范及說明書要求

特種作業(yè)人員持證上崗率100%;安全防護用品正確配備率100%;無高空墜

安全

落事故、觸電事故、起重設備坍塌事故及重傷事故的發(fā)生

綠色施工噪音污染可控

5.3勞務資源安排

施工開始施工分包商選

專業(yè)隊伍資質(zhì)要求工期分包方式責任人

項目時間定方式

塔吊山東中誠機械租賃2023.10.

二級3天租賃公司選定李學丁

安拆有限公司10

5.4工程施工重點和難點分析及應對措施

序號重難點具體分析應對措施責任人

塔吊安拆前與作業(yè)面范圍內(nèi)其他

塔吊安裝與土方開挖、基礎開挖工

分包提前溝通協(xié)調(diào),避免同時作

1交叉作業(yè)作面同時進行,場內(nèi)大型機械較江勇

業(yè),安拆期間在作業(yè)面周圍設置

多,易造成人員傷害

警戒區(qū),避免造成人員傷害

16

6施工進度計劃

4#塔吊計劃于2023年10月5日進場,10月7日進行安裝,安裝工期3天,計劃拆

除時間2023年4月15日,拆除工期5天。

7安拆方法

7.1塔吊安裝順序

1、安裝1節(jié)基節(jié)、4個加強節(jié);

2、安裝爬升架;

3、安裝回轉總成;

4、安裝塔頭總成;

5、安裝平衡臂前臂節(jié);

6、安裝平衡臂后臂節(jié);

7、安裝最內(nèi)側一塊3.5t平衡重;

8、依次分節(jié)吊裝60米起重臂總成;

9、吊裝平衡重(余留的);

10、安裝警示燈和風速儀;

11、穿繞變幅及起升鋼絲繩。

7.2塔吊施工工程管理目標

1、安全管理及職業(yè)健康管理目標:

1)特種作業(yè)人員持證上崗率100%;

2)安全防護用品正確配備率100%;

3)安全防護措施執(zhí)行率100%;

4)無高空墜落事故,觸電事故,起重設備坍塌事故及重傷事故發(fā)生。

2、工期目標:

在確保安全、質(zhì)量和環(huán)保的前提下,塔吊應在3天時間內(nèi)安裝完畢。塔吊部件進場

組裝1天,汽車吊安裝整機1天,頂升調(diào)試1天。

3、質(zhì)量目標:

1)工藝執(zhí)行率100%;

2)工程竣工一次驗收合格率100%;

17

3)成品保護完好率100%;

4)確保設備安全無故障運行,現(xiàn)場服務滿意率100%;

4、環(huán)境管理目標:

1)施工現(xiàn)場噪聲達標排放;

2)施工現(xiàn)場固體廢棄物分類收集安全處置;相關方無環(huán)境問題投訴;

7.3質(zhì)量、安全、環(huán)保管理措施

管理內(nèi)容控制措施中誠責任人

技術人員編制出的安裝施工方案,必須履行審批手續(xù),經(jīng)主管

技術人員

工程師審核、總工程師批準后實施。

安裝工長負責執(zhí)行每道作業(yè)程序,確保施工工藝執(zhí)行率100%;施工工長

安排專人進行自檢,實事求是地作好自檢記錄。施工工長

施工單位負責塔機基礎的施工質(zhì)量,配合塔吊安裝過程中垂直

基礎施工單位

度進行測量和記錄。

質(zhì)量控制

實施對施工設備、工具、索具每日安全檢查、維護保養(yǎng),確保

塔吊司機

設備安全無故障運行;

設備安裝完畢,必須經(jīng)安全檢查部門檢驗合格,所有缺陷均整

施工工長

改合格,取得安全使用合格證后,才能移交使用;

施工服務及維修人員嚴格執(zhí)行勞動紀律,保持良好的服務態(tài)度,

安裝班組

虛心聽取建設單位意見,確保服務質(zhì)量滿足客戶要求。

含油棉紗、手套、廢機油應集中收集,按規(guī)定

危險廢棄物統(tǒng)一處置;嚴格控制設備漏油,防止對土壤污施工工長

染。

重要環(huán)境因防止電氣線路老化引起火災,加強安全檢查;施工工長

素控制對氧氣和乙炔氣體的使用,應確保安全可靠,

火災隱患安全員

符合安全間距,按安全規(guī)程操作,配備消防器

施工單位

材;

施工噪聲嚴格按施工作息時間要求施工,防止噪聲擾民;施工工長

塔吊安裝操作和指揮人員必須經(jīng)過技術和安全

重要危險源

違章作業(yè)培訓,每一個作業(yè)人員必須熟悉說明書,熟知

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
  • 4. 未經(jīng)權益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
  • 6. 下載文件中如有侵權或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

評論

0/150

提交評論