項(xiàng)目專(zhuān)項(xiàng)施工方案
武漢光谷化合物半導(dǎo)體基地(一期)
大體積混凝土工程施工方案
編制單位:中建八局第一建設(shè)有限公司
編制人:
日期:2023年10月
項(xiàng)目專(zhuān)項(xiàng)施工方案
目錄
1編制依據(jù)....................................................................................................................-1-
2工程概況....................................................................................................................-2-
2.1工程建設(shè)概況一覽表.....................................................................................-2-
2.2設(shè)計(jì)概況.........................................................................................................-2-
2.3工程施工條件.................................................................................................-4-
3施工安排....................................................................................................................-5-
3.1項(xiàng)目管理組織.................................................................................................-5-
3.2項(xiàng)目管理目標(biāo).................................................................................................-7-
3.3各項(xiàng)資源供應(yīng)方式.........................................................................................-8-
3.4施工區(qū)域劃分.................................................................................................-8-
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施.......................................................-10-
3.6施工進(jìn)度安排...............................................................................................-10-
3.7關(guān)鍵及特殊過(guò)程控制...................................................................................-11-
4施工進(jìn)度計(jì)劃..........................................................................................................-11-
5施工準(zhǔn)備與資源配置計(jì)劃......................................................................................-11-
5.1施工準(zhǔn)備計(jì)劃...............................................................................................-11-
5.2資源配置計(jì)劃...............................................................................................-15-
5.3保溫材料準(zhǔn)備...............................................................................................-17-
6施工方法及工藝要求..............................................................................................-17-
6.1流水段劃分...................................................................................................-17-
6.2混凝土配合比及原材料的要求...................................................................-18-
6.3混凝土制備及運(yùn)輸計(jì)劃...............................................................................-19-
6.3.1混凝土供應(yīng)........................................................................................-19-
6.3.2場(chǎng)外運(yùn)輸............................................................................................-20-
6.4混凝土澆筑...................................................................................................-22-
6.4.1工藝流程............................................................................................-22-
6.4.2混凝土澆筑........................................................................................-22-
6.4.3振搗....................................................................................................-23-
項(xiàng)目專(zhuān)項(xiàng)施工方案
6.4.4泵送混凝土要求................................................................................-24-
6.4.5混凝土澆筑管理................................................................................-24-
6.4.6特殊部位澆筑....................................................................................-25-
6.4.7泌水處理............................................................................................-25-
6.4.8特殊氣候條件下的施工....................................................................-26-
6.4.9混凝土裂縫預(yù)防措施........................................................................-26-
6.5混凝土養(yǎng)護(hù)...................................................................................................-27-
6.6混凝土測(cè)溫...................................................................................................-28-
6.6.1測(cè)溫系統(tǒng)............................................................................................-28-
6.6.2測(cè)點(diǎn)布置............................................................................................-28-
6.6.3溫度監(jiān)測(cè)............................................................................................-31-
6.6.4混凝土測(cè)溫小組................................................................................-31-
6.7混凝土檢測(cè)...................................................................................................-32-
6.7.1試塊留置............................................................................................-32-
6.7.2混凝土坍落度測(cè)試............................................................................-32-
6.7.3混凝土卸料口溫度測(cè)試....................................................................-32-
6.7.4試模準(zhǔn)備............................................................................................-33-
6.8冬期混凝土施工措施...................................................................................-33-
6.8.1原材料及配比要求............................................................................-33-
6.8.2混凝土攪拌........................................................................................-33-
6.8.3混凝土運(yùn)輸........................................................................................-34-
6.8.4混凝土澆筑........................................................................................-34-
6.8.5混凝土養(yǎng)護(hù)保溫措施........................................................................-35-
6.8.6混凝土試塊留置................................................................................-36-
6.9驗(yàn)收標(biāo)準(zhǔn).......................................................................................................-37-
6.10驗(yàn)收程序.....................................................................................................-38-
6.11驗(yàn)收內(nèi)容.....................................................................................................-38-
6.12驗(yàn)收人員.....................................................................................................-39-
7各項(xiàng)管理計(jì)劃..........................................................................................................-39-
7.1綠色施工管理計(jì)劃.......................................................................................-39-
項(xiàng)目專(zhuān)項(xiàng)施工方案
7.1.1綠色施工管理目標(biāo)............................................................................-39-
7.1.2綠色施工管理機(jī)構(gòu)和職責(zé)分工........................................................-40-
7.1.3綠色保護(hù)體系及措施........................................................................-43-
7.2進(jìn)度管理計(jì)劃...............................................................................................-43-
7.2.1施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工................................................-43-
7.2.2進(jìn)度管理措施....................................................................................-43-
7.3質(zhì)量管理計(jì)劃...............................................................................................-44-
7.3.1質(zhì)量控制目標(biāo)分解............................................................................-44-
7.3.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工....................................................-45-
7.3.3確定質(zhì)量控制點(diǎn)................................................................................-45-
7.3.4混凝土八控........................................................................................-46-
7.3.5四個(gè)百分百落實(shí)................................................................................-46-
7.3.6大體積混凝土的質(zhì)量通病................................................................-46-
7.3.7質(zhì)量控制措施....................................................................................-46-
7.3.8質(zhì)量保證措施....................................................................................-49-
7.4安全管理計(jì)劃...............................................................................................-50-
7.4.1職業(yè)健康安全重大危險(xiǎn)源................................................................-50-
7.4.2安全生產(chǎn)管理制度............................................................................-50-
7.4.3安全生產(chǎn)保證措施............................................................................-51-
7.4.4安全應(yīng)急措施....................................................................................-52-
7.5成品保護(hù)管理計(jì)劃.......................................................................................-53-
7.5.1成品保護(hù)管理組織和職責(zé)分工........................................................-53-
7.5.2成品保護(hù)計(jì)劃及保證措施................................................................-54-
7.6新型冠狀病毒感染肺炎疫情防控管理計(jì)劃...............................................-55-
7.6.1成立疫情防控工作小組....................................................................-55-
7.6.2疫情防控工作小組組織機(jī)構(gòu)和職責(zé)分工........................................-55-
7.6.3防疫物資準(zhǔn)備....................................................................................-56-
7.6.4突發(fā)情況處置措施............................................................................-57-
7.6.5定點(diǎn)醫(yī)療機(jī)構(gòu)....................................................................................-58-
8應(yīng)急預(yù)案..................................................................................................................-58-
項(xiàng)目專(zhuān)項(xiàng)施工方案
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)...................................................................................-58-
8.2事故風(fēng)險(xiǎn)分析...............................................................................................-62-
8.3應(yīng)急救援程序...............................................................................................-63-
8.4應(yīng)急處置措施...............................................................................................-64-
8.4.1火災(zāi)、爆炸事故處置措施................................................................-64-
8.4.2人員傷亡應(yīng)急處置措施....................................................................-64-
8.4.3安保突發(fā)事件應(yīng)急處置措施............................................................-65-
8.4.4新冠肺炎疫情處置措施....................................................................-66-
8.4.5應(yīng)急救援路線....................................................................................-69-
8.5應(yīng)急物資準(zhǔn)備...............................................................................................-70-
8.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練.......................................................................-71-
8.6.1人員培訓(xùn)............................................................................................-71-
8.6.2應(yīng)急演練............................................................................................-73-
8.6.3事故后處理工作................................................................................-74-
9計(jì)算書(shū)......................................................................................................................-74-
9.1里表溫差計(jì)算...............................................................................................-74-
9.2溫度應(yīng)力計(jì)算...............................................................................................-76-
9.3溫度裂縫的計(jì)算...........................................................................................-78-
項(xiàng)目專(zhuān)項(xiàng)施工方案
1編制依據(jù)
序號(hào)類(lèi)別文件名稱(chēng)編號(hào)
1《混凝土外加劑應(yīng)用技術(shù)規(guī)范》GB50119-2013
2《混凝土質(zhì)量控制標(biāo)準(zhǔn)》GB50164-2011
3《混凝土強(qiáng)度檢驗(yàn)評(píng)定標(biāo)準(zhǔn)》GB50107-2010
4《普通混凝土配合比設(shè)計(jì)規(guī)程》JGJ55-2011
5技術(shù)標(biāo)《普通混凝土拌合物性能試驗(yàn)方法》GB/T50080-2016
6準(zhǔn)《混凝土泵送施工技術(shù)規(guī)程》JGJ/T10-2011
7《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》GB50010-2010
8《混凝土結(jié)構(gòu)工程施工規(guī)范》GB50666-2011
9《大體積混凝土施工標(biāo)準(zhǔn)》GB50496-2018
《大體積混凝土溫度測(cè)控技術(shù)規(guī)范》GB/T51028-2015
10質(zhì)量驗(yàn)《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
11收規(guī)范《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
12《建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50202-2018
13建施工程安全生產(chǎn)管理?xiàng)l例國(guó)務(wù)院令第393號(hào)
14安全技《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005
15術(shù)規(guī)程《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
16《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
17建筑施工手冊(cè)/
18其他武漢光谷化合物半導(dǎo)體基地施工圖紙/
19武漢光谷化合物半導(dǎo)體基地施工組織設(shè)計(jì)/
-1-
項(xiàng)目專(zhuān)項(xiàng)施工方案
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱(chēng)工程性質(zhì)廠房
建設(shè)規(guī)模109000㎡工程地址
占地面積約164畝總建筑面積109000㎡
項(xiàng)目承包范土方、樁基、基坑支護(hù)、主
建設(shè)單位
圍體結(jié)構(gòu)
主要分包工
設(shè)計(jì)單位/
程
勘察單位質(zhì)量合格
監(jiān)理單位合同工期587日歷天
總承包單要求
安全無(wú)人身傷亡事故
位
工程主要
功能或用生產(chǎn)、研發(fā)、服務(wù)等
途
2.2設(shè)計(jì)概況
大體積混凝土指混凝土結(jié)構(gòu)物實(shí)體最小尺寸不小于1m的大體量混凝土,或預(yù)計(jì)會(huì)因
混凝土中膠凝材料水化引起的溫度變化和收縮而導(dǎo)致有害裂縫產(chǎn)生的混凝土,本工程中
LAB生產(chǎn)廠房、CUB動(dòng)力站、WH丙類(lèi)庫(kù)基礎(chǔ)底板厚度大于1m為大體積混凝土,設(shè)計(jì)情況
見(jiàn)表2.2-1所示。
本工程主要結(jié)構(gòu)尺寸和結(jié)構(gòu)形式詳見(jiàn)表2.2-1。
表2.2-1基礎(chǔ)底板設(shè)計(jì)概況
基礎(chǔ)情況混凝
面積厚度最大厚(防水保護(hù)土設(shè)抗?jié)B
施工部位長(zhǎng)度*寬度(m)
(㎡)(m)度(m)層上、樓層計(jì)強(qiáng)等級(jí)
板)度
LAB-生產(chǎn)廠房防水保護(hù)層
4306環(huán)形1.85.1C40P8
1-11交A-P軸上
LAB-生產(chǎn)廠房763598.2*801.21.2防水保護(hù)層C40P8
-2-
項(xiàng)目專(zhuān)項(xiàng)施工方案
2-16交B-N軸上
LAB-生產(chǎn)廠房防水保護(hù)層
2239100.8*19.21.21.4C40P8
17-19交A-P軸上
CUB-動(dòng)力站1-6防水保護(hù)層
190631.7*5.5*111.74.7C40P8
交A-N軸上
CUB-動(dòng)力站1
防水保護(hù)層
交A-N、6交A-N942285*3.31.21.2C40P8
上
軸
2.0*2.01.2
WH-丙類(lèi)庫(kù)22305.5*2.01.7承臺(tái)基礎(chǔ)C35/
1.7
5.81*5.06
圖2.2-2LAB生產(chǎn)廠房基礎(chǔ)平面圖
-3-
項(xiàng)目專(zhuān)項(xiàng)施工方案
圖2.2-3CUB-動(dòng)力站基礎(chǔ)平面圖圖2.2-4WH-丙類(lèi)庫(kù)基礎(chǔ)平面圖
2.3工程施工條件
該項(xiàng)目位于東湖高新區(qū)九龍湖街以北、蘇湖路以東,廠區(qū)面積較大,廠區(qū)內(nèi)布置多
條臨時(shí)路,方便后續(xù)通車(chē)和混凝土澆筑,現(xiàn)場(chǎng)南側(cè)、西側(cè)、分別布置2個(gè)出入口與市政
路相連接交通條件完全滿(mǎn)足需求。周邊建筑物較少,夜間施工噪音影響較小。
-4-
項(xiàng)目專(zhuān)項(xiàng)施工方案
80158,94
2F
廚宿宿宿宿宿宿宿宿宿宿宿宿女女
商務(wù)部經(jīng)理室門(mén)廳技術(shù)部物資部小食堂活動(dòng)室上男廁所男浴室洗漱室宿舍宿舍宿舍
倉(cāng)宿舍舍舍舍舍舍舍舍舍舍舍舍舍浴廁
宿舍宿舍宿舍
電動(dòng)感應(yīng)門(mén)宿舍
宿舍宿舍宿舍
施工部宿舍宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿
籃球場(chǎng)舍舍舍舍舍舍舍舍舍舍舍舍洗漱室宿舍宿舍宿舍
2F舍舍舍舍舍舍舍舍舍舍
會(huì)議室宿舍
2F宿舍宿舍宿舍
宿舍宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿宿2F
0倉(cāng)庫(kù)
舍舍舍舍舍舍舍舍舍舍舍舍宿舍宿舍宿舍
5宿舍舍舍舍舍舍舍舍舍舍舍舍舍
男衛(wèi)生間宿舍宿舍宿舍
羽毛球場(chǎng)宿舍
封樣室女衛(wèi)生間
宿宿宿宿宿宿宿宿宿宿宿宿宿舍宿舍宿舍
男浴室宿宿宿宿宿宿宿宿宿宿宿宿
上上舍舍舍舍舍舍舍舍舍舍舍舍
2F舍舍舍舍舍舍舍舍舍舍舍舍宿舍宿舍宿舍
男廁2F
女廁
餐廳廚房
女浴室廚房餐廳廚房
上
晾衣架
洗碗池洗碗池非機(jī)動(dòng)車(chē)棚
消防通道土方堆場(chǎng)
(13000㎡)
I區(qū)堆場(chǎng)(10000㎡)II區(qū)料場(chǎng)(11000㎡)
氣站區(qū)料場(chǎng)(2000㎡)
60
1#出入口洗車(chē)池地磅
路
湖
蘇
2#出入口
III區(qū)料場(chǎng)(10800㎡)
3#出入口九龍湖街
場(chǎng)區(qū)規(guī)劃圖
3施工安排
3.1項(xiàng)目管理組織
序
管理職務(wù)姓名職責(zé)和權(quán)限
號(hào)
1)負(fù)責(zé)落實(shí)單位總部對(duì)項(xiàng)目部人員配備,落實(shí)和解決單位總
部對(duì)項(xiàng)目人員、物資、設(shè)備、資金等主要生產(chǎn)要素的供給,
保證大體積混凝土施工過(guò)程中有充足的資源組織施工。
2)大體積混凝土施工過(guò)程中與業(yè)主、監(jiān)理保持溝通和協(xié)調(diào),
落實(shí)業(yè)主和監(jiān)理安排的事項(xiàng)。
1項(xiàng)目經(jīng)理3)對(duì)項(xiàng)目進(jìn)行有效的監(jiān)管,保證大體積混凝土的方案有效實(shí)
施,處理大體積混凝土施工過(guò)程中各專(zhuān)業(yè)之間的管理和協(xié)調(diào)
問(wèn)題。
4)負(fù)責(zé)大體積混凝土施工過(guò)程中各專(zhuān)業(yè)施工之間和項(xiàng)目管
理人員的總協(xié)調(diào)及調(diào)度,制定項(xiàng)目工期、質(zhì)量、成本、安全
文明施工等各項(xiàng)管理目標(biāo),并組織實(shí)施等。
-5-
項(xiàng)目專(zhuān)項(xiàng)施工方案
序
管理職務(wù)姓名職責(zé)和權(quán)限
號(hào)
1)全面負(fù)責(zé)大體積混凝土施工過(guò)程中的深化設(shè)計(jì)、技術(shù)和質(zhì)
量工作的展開(kāi)。
2)編制大體積混凝土施工方案,協(xié)調(diào)各分包之間的技術(shù)問(wèn)題。
3)與設(shè)計(jì)、監(jiān)理保持溝通,保證設(shè)計(jì)、監(jiān)理的要求與指令在
各專(zhuān)業(yè)中貫徹實(shí)施。
4)及時(shí)組織技術(shù)人員解決大體積混凝土施工過(guò)程中出現(xiàn)的
2項(xiàng)目總工
技術(shù)問(wèn)題。
5)直接領(lǐng)導(dǎo)技術(shù)人員,施工人員和有關(guān)職能部門(mén)人員的技術(shù)
工作,承擔(dān)項(xiàng)目的技術(shù)領(lǐng)導(dǎo)責(zé)任,貫徹執(zhí)行技術(shù)規(guī)范、標(biāo)準(zhǔn),
制訂施工項(xiàng)目的技術(shù)管理制度,組織工程的施工驗(yàn)收工作,
領(lǐng)導(dǎo)工程安全事故的預(yù)防和處理工作,組織工程的施工安全
驗(yàn)收工作等。
1)全面負(fù)責(zé)工程管理部。
2)對(duì)大體積混凝土工程的施工生產(chǎn)、進(jìn)度計(jì)劃、現(xiàn)場(chǎng)總協(xié)調(diào)
等管理全面負(fù)責(zé)。
3)對(duì)大體積混凝土工程施工與其他各專(zhuān)業(yè)之間的施工生產(chǎn)
協(xié)調(diào)。
4)負(fù)責(zé)大體積混凝土施工中各工種之間的協(xié)調(diào)及配合,組織
各專(zhuān)業(yè)管理人員、施工日常工作的落實(shí),組織工程的施工、
驗(yàn)收工作等,及時(shí)解決施工中出現(xiàn)的各種問(wèn)題。
3生產(chǎn)經(jīng)理
5)認(rèn)真貫徹執(zhí)行國(guó)家的方針、政策以及項(xiàng)目部施工安全生產(chǎn)
管理制度。
6)合理安排主持大體積混凝土施工過(guò)程中現(xiàn)場(chǎng)各項(xiàng)管理工
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶(hù)所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶(hù)上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶(hù)上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶(hù)因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 無(wú)線信號(hào)掃描課程設(shè)計(jì)
- 山東農(nóng)業(yè)工程學(xué)院《寧夏文旅專(zhuān)題》2023-2024學(xué)年第一學(xué)期期末試卷
- 山東鋁業(yè)職業(yè)學(xué)院《管理學(xué)基礎(chǔ)》2023-2024學(xué)年第一學(xué)期期末試卷
- 托班廚房創(chuàng)意課程設(shè)計(jì)
- 小班鄉(xiāng)土文化課程設(shè)計(jì)
- 中班動(dòng)物大世界課程設(shè)計(jì)
- 鳳陽(yáng)花鼓微課程設(shè)計(jì)方案
- 土木課程設(shè)計(jì)寫(xiě)進(jìn)簡(jiǎn)歷
- 山東科技大學(xué)《移動(dòng)電商基礎(chǔ)與實(shí)務(wù)》2023-2024學(xué)年第一學(xué)期期末試卷
- 美國(guó)制造業(yè)經(jīng)濟(jì)2024年度報(bào)告-2024-12-宏觀大勢(shì)
- 設(shè)備維修年終總結(jié)總結(jié)
- 危險(xiǎn)化學(xué)品培訓(xùn)計(jì)劃
- 鐵路檢車(chē)員個(gè)人工作總結(jié)2篇
- 京東財(cái)務(wù)部門(mén)組織架構(gòu)
- 導(dǎo)管堵塞的預(yù)防與處理
- 土壤污染治理與修復(fù)
- 書(shū)香企業(yè)閱讀活動(dòng)系列方案
- 保健品“番茄紅素軟膠囊”的研發(fā)-醫(yī)學(xué)資料
- 社區(qū)食堂建設(shè)可行性方案
- 23秋國(guó)家開(kāi)放大學(xué)《漢語(yǔ)基礎(chǔ)》期末大作業(yè)(課程論文)參考答案
- 軍事體育基礎(chǔ)知識(shí)
評(píng)論
0/150
提交評(píng)論