![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標技術(shù)方案_第1頁](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg117.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標技術(shù)方案_第2頁](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1172.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標技術(shù)方案_第3頁](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1173.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標技術(shù)方案_第4頁](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1174.jpg)
![鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房 投標技術(shù)方案_第5頁](http://file4.renrendoc.com/view9/M03/1D/1D/wKhkGWdbnvaAIhrOAAIWagDxRIg1175.jpg)
版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進行舉報或認領(lǐng)
文檔簡介
鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房投標技術(shù)方案
目錄
L工程概況及特點................................................9
1.1建筑概況................................................9
1.2結(jié)構(gòu)概況................................................10
1.2.1基礎................................................10
1.2.2主體.................................................10
1.3安裝工程概況...........................................10
1.3.1概述.................................................10
1.3.2工程概況.............................................10
1.4工程特點...............................................11
1.4.1施T場地文明施T難度大...............................11
1.4.2工程特殊部位較多.....................................12
2.施工組織設計總體設想.........................................12
2.1工程建設目標...........................................12
2.1.1質(zhì)量管理目標.........................................12
2.1.2工期管理目標.........................................12
2.1.3安全生產(chǎn)管理目標.....................................12
2.1.4文明施工管理目標....................................12
2.2質(zhì)量控制重點..........................................12
3.施工部署....................................................13
3.1組織機構(gòu)...............................................13
3.1.1項目部的組織機構(gòu).....................................13
3.2強化項目管理..........................................14
3.2.1編制和實施項目管理實施計劃...........................14
3.2.2貫徹落實公司的規(guī)章制度...............................14
3.2.3逐層分解指標,明確責、權(quán)、利........................14
3.2.4嚴格執(zhí)行施工組織設計.................................15
3.2.5執(zhí)行質(zhì)量進度公開制...................................15
3.2.6業(yè)主滿意.............................................15
3.3項目管理部職責.........................................15
3.4項目管理部主要部門、崗位職責...........................16
3.4.1項目經(jīng)理.............................................16
3.4.2項目副經(jīng)理...........................................16
3.4.3項目總工程師.........................................17
3.4.4項目部的管理職責.....................................17
3.5項目經(jīng)理長駐現(xiàn)場措施...................................18
3.5.1建立請假制度.........................................18
3.5.2建立約束機制.........................................18
3.5.3實行項目經(jīng)理評分制....................................18
3.6勞務工資管理和發(fā)放措施................................19
3.7施工組織................................................19
3.7.1施工區(qū)、段劃分......................................19
3.7.2施工順序.............................................19
3.8資源酉已置...............................................21
3.8.1勞動力安排計劃.......................................21
3.8.2工程投入的主要施工機械設備安排計劃..................22
3.8.3周轉(zhuǎn)材料配備.........................................24
3.8.4成品、半成品加工與組織.............................25
4.施工準備...................................................26
4.1現(xiàn)場準備...............................................26
4.1.1周邊環(huán)境的了解.......................................26
4.1.2場地平整.............................................26
4.2技術(shù)準備...............................................26
4.2.1圖紙會審.............................................26
4.2.2施工組織設計和施工方案...............................27
4.3物資準備...............................................27
4.3.1編制材料計劃.........................................27
4.3.2材料供應商選擇.......................................27
4.3.3材料進場.............................................28
4.3.4材料檢測.............................................28
4.4設備準備...............................................29
4.4.1設備組織.............................................29
5.協(xié)調(diào)、配合及服務............................................29
5.1與設計院的協(xié)調(diào)配合.....................................29
5.2與監(jiān)理的協(xié)調(diào)配合.......................................29
5.3與業(yè)主協(xié)調(diào)配合.........................................30
5.4與質(zhì)檢站的協(xié)調(diào)配合.....................................30
5.5與公安部門的協(xié)調(diào)配合...................................30
5.6與業(yè)主指定分包單位的協(xié)調(diào)配合...........................30
5.7與社會各界的協(xié)調(diào).......................................30
5.7.1與地方安全部門的協(xié)調(diào)配合.............................30
5.7.2與地方環(huán)境監(jiān)測單位的協(xié)調(diào)配合.........................31
5.8內(nèi)部關(guān)系的協(xié)調(diào)配合.....................................31
5?9服務...................................................31
6.土建各分部分項工程主要施工方案...............................32
6.1施工測量...............................................32
6.1.1平面控制.............................................32
6.1.2垂直度控制...........................................33
6.1.3標高抄測.............................................33
6.1.4精度要求.............................................33
6.1.5沉降觀測.............................................34
6.2基礎工程...............................................34
6.2.1基礎土方.............................................34
6.2.2基礎施工.............................................36
6.2.3基礎模板.............................................36
6.2.4基礎鋼筋工程.........................................37
6.2.5基礎混凝土..........................................38
6.3主體工程...............................................39
6.3.1模板工程.............................................39
6.3.2鋼筋工程.............................................43
6.3.3混凝土工程...........................................44
6.3.4砌體結(jié)構(gòu).............................................46
6.4保溫隔熱屋面...........................................50
6.4.1工藝流程.............................................50
6.4.2找平層...............................................50
6.4.3防水卷材施工.........................................50
6.4.4保溫層施工...........................................51
6.4.5細石砂面層施工.......................................52
6.5裝飾工程...............................................52
6.5.1室內(nèi)抹灰工程.........................................52
6.5.2外墻保溫層施工.......................................53
6.5.3乳膠漆墻面施工.......................................53
6.5.4油漆工程.............................................55
6.5.5門窗工程.............................................55
6.5.6欄桿安裝.............................................58
6.6樓地面工程.............................................58
6.6.1水泥細石碎樓地面.....................................58
6.7室外散水...............................................59
6.8腳手架工程.............................................59
6.8.1外腳手架.............................................59
6.8.2腳手架的防雷接地....................................62
6.8.3內(nèi)腳手架.............................................62
6.8.4安全防護架...........................................62
6.8.5腳手架拆除...........................................63
7,安裝各分部分項工程的施工方案.................................64
7.1給排水工程施工方案.....................................64
7.1.1預埋件的安裝.........................................64
7.1.2管道施工流程.........................................64
7.1.3PP—R管安裝...........................................65
7.1.4排水管安裝...........................................66
7.1.5UPVC管專用膠粘接.....................................67
7.1.6衛(wèi)生器具的安裝方法和要求.............................68
7.1.7消防系統(tǒng)的安裝方法和要求.............................69
7.1.8管道支架的安裝方法和要求.............................70
7.1.9管道試驗與管道沖洗...................................70
7.1.10管道防腐與保溫......................................72
7.2電氣工程施工方案.......................................72
7.2.1電氣施工流程.........................................72
7.2.2土建配合階段.........................................72
7.2.3相接階段.............................................73
7.2.4系統(tǒng)調(diào)試.............................................85
&建筑節(jié)能及建筑保溫專項施工方案和措施.........................88
8.1.1外墻保溫專項施工方案和質(zhì)量保證措施...................88
一、基層墻體處理...........................................88
二、材料的準備.............................................88
三、聚苯板的粘貼...........................................88
四、保溫板粘貼過程控制要點.................................88
五、質(zhì)量檢驗:.............................................89
8.1.2屋面保溫專項施工方案和質(zhì)量保證措施...................91
9.重點、難點施工措施...........................................92
9.1.1測量放線采取的措施...................................92
9.1.2土方開挖保證樁基質(zhì)量的施工措施......................92
9.1.3鋼筋保護層控制不嚴的防治措施.........................93
9.1.4為確保碎成型質(zhì)量,模板采取的施工措施...............93
10.確保工程質(zhì)量的技術(shù)組織措施..................................94
10.1質(zhì)量目標..............................................94
10.1.1質(zhì)量管理目標........................................94
10.1.2分部分項工程質(zhì)量管理目標............................94
10.1.3工程觀感質(zhì)量管理目標................................94
10.2質(zhì)量保證管理措施.....................................94
10.2.1質(zhì)量管理保證體系網(wǎng)絡................................94
10.2.2質(zhì)量管理制度......................................95
10.2.3編制質(zhì)量計劃、創(chuàng)優(yōu)措施..............................96
10.2.4施工過程質(zhì)量控制點................................96
10.3工程質(zhì)量技術(shù)措施......................................98
10.3.1施工組織設計審批制度................................98
10.3.2分部、分項工程技術(shù)交底、復核、隱蔽工程驗收制度......98
10.3.3施工機械設備、監(jiān)視和測量設備的控制..................98
10.3.4原材料質(zhì)量保證措施.................................98
10.4主要分部分項工程質(zhì)量保證技術(shù)措施.....................99
10.4.1分部分項工程過程質(zhì)量控制措施.......................99
10.4.2基礎工程............................................99
10.4.3主體工程...........................................100
10.4.4裝修工程...........................................102
10.4.5屋面防水施工.......................................103
10.5工程質(zhì)量通病的防治措施.............................103
10.5.1目的...............................................103
10.5.2適用范圍...........................................103
10.5.3具體措施...........................................103
10.6采用質(zhì)量預控制的科學方法.............................106
10.7開展QC小組活動......................................107
10.7.1小組概況及活動形式.................................107
10.7.2課題確定.........................................107
10.8計量管理...........................................108
11.確保安全生產(chǎn)的技術(shù)組織措施................................109
11.1安全管理目標.........................................109
11.2組織措施.............................................109
11.2.1施工現(xiàn)場安全組織.................................109
11.3安全保證計劃的編制..................................112
11.4施工過程控制........................................112
11.4.1人員培訓..........................................112
11.4.2安全檢查..........................................112
11.4.3隱患整改..........................................113
11.4.4安全事故的處理....................................113
11.4.5現(xiàn)場急救.........................................113
1L4.6施工現(xiàn)場的安全要求................................114
11.5施工過程安全控制措施...............................115
11.5.1搭設腳手架安全要求...............................115
11.5.2洞口、臨邊的防護...................................115
11.5.3內(nèi)外交通管理保障措施...............................115
11.6消防管理............................................116
11.6.1組織措施...........................................116
11.6.2防火要求...........................................116
11.6.3消防設施的布置.....................................116
12.確保文明施工的技術(shù)組織措施................................117
12.1目標.................................................117
12.2現(xiàn)場文明施工管理.....................................117
12.2.1文明施工組織網(wǎng)絡...................................117
12.2.2文明施工崗位職責..................................117
12.2.3內(nèi)部溝通...........................................119
12.2.4場容場貌...........................................120
12.2.5施工現(xiàn)場標化管理....................................120
12.3環(huán)保施工措施........................................122
12.3.1工作目標...........................................122
12.3.2組織管理...........................................123
12.3.3工作制度...........................................123
12.3.4管理規(guī)定...........................................123
12.4組織保證措施........................................124
12.5技術(shù)保證措施........................................125
13.確保工期的技術(shù)組織措施.....................................126
13.1施工工期.............................................126
13.2施工進度計劃.........................................126
13.3進度保證措施.........................................126
13.3.1組織保證措施.......................................126
13.3.2勞動力保證措施....................................127
13.3.3機械設備保證措施....................................127
13.3.4技術(shù)保證措施.......................................127
13.3.5周轉(zhuǎn)工具保證措施....................................127
13.3.6基礎工程階段保證措施...............................127
13.3.7主體工程階段保證措施...............................127
13.3.8裝飾工程階段保證措施...............................128
13.3.9水電安裝階段保證措施..............................128
13.3.10進度計劃動態(tài)控制措施..............................128
13.4進度獎罰措施.........................................129
13.5法定假期間保證措施....................................129
13.6農(nóng)忙期間保證措施......................................130
14.施工總平面布置.............................................131
14.1布置原則.............................................131
14.2生活區(qū)臨時設施布置..................................131
14.3臨時生產(chǎn)設施布置....................................131
14.3.1施工臨時用地圍護設置...............................131
14.3.2施工道路...........................................132
14.3.3攪拌臺設置........................................132
14.3.4鋼筋車間...........................................132
14.3.5現(xiàn)場辦公室.........................................133
14.3.6其它生產(chǎn)設施.......................................133
14.3.7施工區(qū)周邊環(huán)境的保護措施.........................133
14.3.8施工現(xiàn)場臨時用電方案...............................133
14.3.9施工現(xiàn)場臨時用水方案...............................134
15.新工藝、新技術(shù)、新材料的應用...............................135
15.1新型模板.............................................135
15.2泵送碎...............................................135
15.3鋼筋直螺紋連接技術(shù)................................135
15.4激光測距儀、全站儀..................................135
15.5微機應用.............................................135
16.季節(jié)性及夜間施工保證措施..................................136
16.1雨期及臺風期施工措施...............................136
16.1.1管理措施...........................................136
16.1.2安全措施...........................................136
16.1.3技術(shù)措施.........................................136
16.2夜間施工措施.......................................137
16.3冬期施工技術(shù)措施.....................................137
16.3.1土方工程.........................................138
16.3.2鋼筋工程...........................................138
16.3.3碎工程.............................................138
16.4暑季施工措施.........................................138
17.降低工程成本技術(shù)措施......................................139
17.1主要技術(shù)節(jié)約措施.....................................139
17.2進行技術(shù)經(jīng)濟分析,優(yōu)選施工方案.......................139
17.3提高勞動生產(chǎn)率.......................................139
17.4節(jié)約材料消耗.........................................139
17.5提高機械設備利用率...................................139
編制依據(jù)
1.XX市XXXX有限公司二期建設工程招標文件;
2.XX市XXXX有限公司一期建設工程設計圖紙;
3.XX市XXXX有限公司二期建設工程招標答疑;
4.現(xiàn)行安全、文明施工的有關(guān)規(guī)定;
5,現(xiàn)場踏勘目測結(jié)果;
6.國家現(xiàn)行施工技術(shù)規(guī)范、規(guī)程、標準。
1.工程概況及特點
XX市XXXX有限公司二期建設工程,位于XX市XX區(qū)工業(yè)園區(qū)緯二路18
號。
本標段施工內(nèi)容包括4#、5#廠房以及綜合樓土建、水電安裝工程。
建設單位:XX市XXXX有限公司
設計單位:XX市現(xiàn)代建筑設計研究院有限公司
1.1建筑概況
本標段工程建筑面積約10854.38m;其中4#、5#廠房都為3595m",綜合
樓為3664.38m2。
建筑樓層:4#、5#廠房溝為兩層,綜合樓三層局部四層。
本工程設計基準年限為50年,建筑主體結(jié)構(gòu)安全等級為二級。±0.000
為室內(nèi)地坪標高,相當于絕對標高詳見總圖,室內(nèi)外高差廠房為150mm,綜合
樓為300mmo
建筑類別及耐火等級:耐火等級為二級
抗震設防烈度:六度。
結(jié)構(gòu)類型:框架結(jié)構(gòu)體系。
地面做法:(廠房)地一:水泥砂漿地面;
地二:地磚地面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿地面
樓面做法:(廠房)樓一:水泥砂漿樓面;
樓二:地磚樓面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿樓面;
內(nèi)墻做法:(廠房)內(nèi)墻一:乳膠漆墻面
內(nèi)墻二:瓷磚墻面(用于衛(wèi)生間)
(綜合樓)乳膠漆墻面
外墻做法:(廠房)水泥砂漿抹灰,乳膠漆飾面;
(綜合樓)水泥砂漿抹灰,巖棉板保溫層,抗裂砂漿壓入一層
耐堿玻纖網(wǎng)格布,乳膠漆飾面;
頂棚做法:素水泥漿一道,混合砂漿抹灰,乳膠漆罩面;
門窗:塑鋼窗、防火鋼門安裝。
屋面做法:廠房為20厚1:3水泥砂漿找平層、40厚聚苯乙烯擠塑板、20厚1:3
水泥砂漿找平層、SBS改性瀝青防水卷材丁
綜合樓為最薄處30厚粉煤灰陶粒碎找坡層、40厚擠塑聚苯板、20
厚水泥砂漿找平層、刷一層基層處理劑、4厚高聚物改性瀝青防水卷材、50厚
C30細石碎,內(nèi)配中4@150雙向鋼筋。
1.2結(jié)構(gòu)概況
L2.1基礎
基礎碎墊層C10,獨立基礎、條形基礎廠房均采用C25泵送商品碎,綜合
樓均采用C30泵送商品稅。
L2.2主體
框架柱、梁、板:結(jié)構(gòu)強度等級為廠房C25、綜合樓C30泵送商品碎;
構(gòu)造柱:為C20非泵送商品碎;圈梁、過梁:為C20非泵送商品碎
砌體結(jié)構(gòu):-0.060以下采用MU20混凝土磚M10水泥砂漿砌筑;-0.060
以上外墻采用承重性砌塊,M7.5混合砂漿砌筑,內(nèi)墻采用碎空心砌塊,M5混
合砂漿砌筑,女兒墻采用碎空心砌塊,M7.5混合砂漿砌筑。
1.3安裝工程概況
1.3.1概述
本工程主要工作內(nèi)容為:給排水管道、電氣等工程的安裝。
1.3.2工程概況
A.給排水工程
包括給水系統(tǒng)、消火栓消防系統(tǒng)、排水系統(tǒng)、雨水系統(tǒng)等安裝;
給水系統(tǒng):本工程由市政管網(wǎng)供水
污水系統(tǒng):采用雨污分流制,糞便污水經(jīng)化糞池處理后與其它生活廢水
排入室外污水管網(wǎng);
雨水系統(tǒng):主樓采用重力流排水系統(tǒng)排至室外,與場地及道路雨水匯合
排入市政雨水管網(wǎng)。
室內(nèi)給水管采用PP-R管,熱熔連接;
消火栓消防管采用內(nèi)外熱浸熱鍍鋅鋼管,管徑大于等于DN100采用卡箍
連接,管徑小于DN100采用絲扣連接。
污水管采用UPVC排水管,粘接。
雨水管、冷凝水管采用UPVC塑料排水管,膠結(jié)。
B.電氣工程
包括配電設計、照明設計、防雷接地系統(tǒng);
電力配電系統(tǒng):
低壓配電電壓為380/300V三相四線制,采用放射式與樹干式相結(jié)合供電
方式;
照明系統(tǒng):
本工程電纜電線均采用阻燃電線電纜;
接地型式采用TN-C-S系統(tǒng),利用建筑物基礎主鋼筋作共同接地裝置。
防雷與接地:
防直擊雷:采用在屋頂明設避雷帶和其它地方暗設避雷帶組成混合接閃
器,引下線做法商品砂柱內(nèi)電焊成一體的四根不小于610的主筋作防雷引下
線。
所有接地均利用基礎及基礎梁中的鋼筋焊接溝通后連成一整體作為統(tǒng)一
接地體,形成共用接地系統(tǒng)。
1.4工程特點
1.4.1施工場地文明施工難度大
根據(jù)現(xiàn)場實地觀測,本工程施工現(xiàn)場內(nèi),施工中要特別注重文明施工,
以最小的影響來確保場內(nèi)的正常活動。另外,現(xiàn)場臨建設施、材料堆放場地、
大型機械設備布置必須進行合理的規(guī)劃和布局,施工順序也必須進行全局的
策劃和組織,來保證場地受施工干擾最小。
L4.2工程特殊部位較多
本T.程屋面及衛(wèi)生間的防水處理等,都必須制定相應的技術(shù)措施,確保
工程質(zhì)量符合設計與規(guī)范要求。
2.施工組織設計總體設想
2.1工程建設目標
2.1.1質(zhì)量管理目標
符合國家質(zhì)量驗收標準,一次性驗收合格
2.1.1.1各分部工程質(zhì)量管理目標
分部工程、分項工程一次性驗收合格
2.1.1.2工程觀感質(zhì)量管理目標
觀感評定:好
2.1.2工期管理目標
工期:370個日歷天
2.1.2.1工程竣工管理目標
工程竣工一次驗收合格率100%
2.1.3安全生產(chǎn)管理目標
2.1.3.1安全生產(chǎn)目標
杜絕死亡、重傷事故
輕傷事故控制在5%。以內(nèi)
2.1.3.2安全生產(chǎn)過程目標
事故隱患控制率在95%以上
整改率控制在100%
2.1.4文明施工管理目標
2.1.4.1文明工地目標
確?!笆屑壩拿鞴さ囟?/p>
2.2質(zhì)量控制重點
稅結(jié)構(gòu)施工
衛(wèi)生間防滲
屋面防水細部節(jié)點施工
平面及垂直度度控制
安裝與土建交叉施工的質(zhì)量控制
3.施工部署
3.1組織機構(gòu)
本工程采用公司、項目管理部二級管理模式。成立“XX市XXXX有限公司
二期建設工程項目經(jīng)理部”,代表公司進行工程施工組織和管理,全面負責
整個工程的進度、安全、質(zhì)量、成本控制四大指標,抓好優(yōu)質(zhì)服務及現(xiàn)場文
明施工等。
3.1.1項目部的組織機構(gòu)
在公司內(nèi)抽調(diào)一批具有較高專業(yè)知識和業(yè)務能力、經(jīng)驗豐富的施工骨干
力量組成項目管理部的項目班子和管理層。項目部設項目經(jīng)理一名、項目總
工程師一名、項目副經(jīng)理一名,下設質(zhì)保部、技術(shù)部、工程部、物項部、經(jīng)
營部、人勞部、財務部、安保部、資料室。
項目組織機構(gòu)網(wǎng)絡圖
項目經(jīng)理
項目總工程師項目副經(jīng)理
3.2強化項目管理
3.2.1編制和實施項目管理實施計劃
工程開工前,項目經(jīng)理組織項目部相關(guān)管理人員編制項目管理實施規(guī)劃。
編制前,必須對施工合同和施工條件進行分析,對項目管理目標責任書
進行分析。
在實施過程中,每隔一個月進行一次檢查,必要時增加檢查頻率,發(fā)現(xiàn)
偏差,及時調(diào)整。確保本工程順利進展。
3.2.2貫徹落實公司的規(guī)章制度
在項目施工過程中,必須貫徹執(zhí)行公司的各項規(guī)章制度,主要有:
《項目施工管理細則》
《項目施工質(zhì)量責任制》
《項目施工安全生產(chǎn)責任制》
《項目施工用戶滿意責任制》
《項目施工資金使用管理制度》
3.2.3逐層分解指標,明確責、權(quán)、利
項目開工前,公司與項目經(jīng)理簽訂本項目承包合同,明確項目經(jīng)理及項
目部的責、權(quán)、利,項目部與項目管理人員及生產(chǎn)班組簽訂施工協(xié)議,分解
項目各項指標,明確參與施工人員的職責、權(quán)利及獎勵和處罰,把績效與經(jīng)
濟收入掛鉤,進一步強化職工的責任心、事業(yè)心,從而保證項目正常實施。
3.2.4嚴格執(zhí)行施工組織設計
施工組織設計經(jīng)公司總工和業(yè)主、監(jiān)理批準后,必須嚴格執(zhí)行,任何人
不得隨意修改施工組織設計或不按施工組織設計施工,如需要修改施工組織
設計,必須至少提前一周報請原審批部門審批,經(jīng)批準后方可按修改后的施
工組織設計執(zhí)行。
3.2.5執(zhí)行質(zhì)量進度公開制
工程開工前,將工程質(zhì)量目標、進度計劃張貼上墻,施工過程中,根據(jù)
每一分部完成情況,填寫對照表,找出原因,以便及時整改。
3.2.6業(yè)主滿意
通過強化項目管理,來達到工期短、質(zhì)量好、成本低及安全的目標,從
而最終生產(chǎn)出令業(yè)主滿意的產(chǎn)品。
3.3項目管理部職責
對公司總部負責,向公司總部報告工程實施過程中的一切重大事宜;
負責工程項目的施工管理和各項工作的具體實施;
編制項目各項計劃,包括資金計劃和執(zhí)行機構(gòu)開支預算;
編制項目質(zhì)量保證計劃和技術(shù)方案,并報公司審批后負責落實和實施;
編制項目安全文明施工組織管理方案,報公司審批后落實;
做好現(xiàn)場生產(chǎn)組織管理工作,保證質(zhì)量、工期和安全目標的實現(xiàn);
具體負責項目的各分部交驗工作,以及竣工驗收負責工程創(chuàng)優(yōu)的各項工
作;
3.4項目管理部主要部門、崗位職責
3.4.1項目經(jīng)理
3.4.1.1項目經(jīng)理的崗位職責
是項目管理部的法定代表人,與公司一道討論并決定承包項目部的一切
重大事宜,審核并批準項目執(zhí)行機構(gòu)的各類計劃、方案、報告和制度;
與公司經(jīng)理一道,牽頭負責項目管理部與業(yè)主和政府機構(gòu)的聯(lián)絡工作;
全面主持項目執(zhí)行機構(gòu)的日常工作,是項目實施過程的全職組織者和指
揮者;
決定項目的各種獎勵分配方案并報公司備案;
擬訂項目執(zhí)行機構(gòu)組織和人員配制,提請公司聘任或解聘項目主要崗位
人員;
處理項目實施中的重大緊急事件,并及時向公司報告:
負責與業(yè)主、監(jiān)理、設計等的協(xié)調(diào)和溝通的組織領(lǐng)導工作;組織和領(lǐng)導
創(chuàng)優(yōu)工作。
3.4.1.2項目經(jīng)理的主要業(yè)績
項目經(jīng)理近幾年的主要業(yè)績:見商務標
3.4.2項目副經(jīng)理
3.4.2.1項目副經(jīng)理的崗位職責
落實項目質(zhì)量保證計劃、各類施工技術(shù)方案、安全文明、施工組織管理
方案;
配合項目經(jīng)理,組織編制項目執(zhí)行機構(gòu)的勞資分配制度和其它管理制度;
配合項目經(jīng)理,組織編制項目實施的各類進度計劃、預算、報表;
協(xié)助項目經(jīng)理工作,具體負責項目基礎、土建、鋼結(jié)構(gòu)、裝修、機電等
施工生產(chǎn)的技術(shù)、質(zhì)量、安全、進度的組織、控制和管理工作,以及協(xié)助項
目經(jīng)理分管計劃協(xié)調(diào)、安全文明、質(zhì)量保證、行政、保安等部門的工作;
具體負責項目質(zhì)量、工期,安全目標的管理監(jiān)督工作;
配合項目經(jīng)理,管理經(jīng)營部、財務部和物資采購部的工作
負責工程的竣工交驗工作;
在項目經(jīng)理的配合下,負責組織協(xié)調(diào)后方生產(chǎn)資源和技術(shù)服務的支持工
作;
協(xié)助總工程師進行新材料、新技術(shù)、新工藝在本工程的推廣應用和技術(shù)
總結(jié)工作
3.43項目總丁程師
3.4.3.1項目總工的崗位職責
協(xié)助項目經(jīng)理管理和領(lǐng)導技術(shù)部工作;
具體負責項目質(zhì)量保證計劃、各類施工技術(shù)方案和安全文明施工組織管
理方案的編制及其檢查和落實工作;
負責總體和階段進度計劃的編制、分解、協(xié)調(diào)和落實工作
負責項目質(zhì)量目標、進度、目標、安全文明施工目標和質(zhì)量獎目標的策
劃、組織、管理和落實工作;
組織相關(guān)部門和人員代表項目經(jīng)理部參與與業(yè)主、監(jiān)理或設計方等就施
工方案、技術(shù)、設計、質(zhì)量等方面的問題的會議、討論或磋商;
主持施T組織設計和重大技術(shù)方案和測量方案的編制與修訂并負責把
關(guān);
組織進度計劃的編制并監(jiān)督落實,負責土建與水電安裝工作之間在進度
安排方面的配合和協(xié)調(diào);
參與項目質(zhì)量策劃并督促技術(shù)方案和施工組織設計主要內(nèi)容的落實工
作;
對新技術(shù)、新工藝和新材料在本工程的推廣和使用進行指導;
協(xié)助項目經(jīng)理并組織創(chuàng)優(yōu)工作;
竣工圖、竣工資料、技術(shù)總結(jié)等工作的指導和審核;
負責組織對工人的崗前培訓工作,并審查培訓效果;
負責工程的技術(shù)資料整理工作
3.4.4項目部的管理職責
主要部門的崗位職責
3.4.4.1技術(shù)部
協(xié)助項目總工程師工作,負責項目施工的技術(shù)準備工作;
編制項目質(zhì)量保證計劃、安全文明、施工方案。及時向總工返饋信息,
參與施工方案修訂工作。
具體負責現(xiàn)場總平面的布置方案及其調(diào)整方案;
協(xié)助安全文明施工、質(zhì)量體系運行和爭創(chuàng)質(zhì)量獎工作;
負責編制工程的物資需求計劃;
負責技術(shù)資料收集整理工作,項目階段交驗和竣工交驗;
負責新技術(shù)、新材料、新工藝在本項目的推廣應用和科技成果的總結(jié)工
作;
3.4.4.2質(zhì)保部
協(xié)助項目副經(jīng)理工作,負責項目的全面質(zhì)量管理;
參與編制項目質(zhì)量保證計劃,負責編制安全文明施工組織管理方案和管
理制度并監(jiān)督實施;
負責安全生產(chǎn)和文明施工的日常檢查、監(jiān)督、消除隱患等管理;
負責管理落實質(zhì)量記錄的整理存檔工作,協(xié)助項目總工程師進行竣工資
料的編制工作;
負責項目質(zhì)量保證計劃并負責監(jiān)督實施、過程控制、日常管理;
負責項目全員質(zhì)量保證體系和質(zhì)量方針的培訓教育工作;
負責分部分項工程工序質(zhì)量檢查和質(zhì)量評定工作;
負責質(zhì)量目標的分解落實,編制質(zhì)量獎懲責任制度并負責日常管理;
負責工程創(chuàng)優(yōu)和評獎的策劃、組織、資料準備和日常管理工作;
3.5項目經(jīng)理長駐現(xiàn)場措施
3.5.1建立請假制度
項目經(jīng)理若離開現(xiàn)場,在一天以內(nèi),應以書面形式請假,經(jīng)現(xiàn)場總監(jiān)及
甲方代表批準,離開前,必須將其工作交給現(xiàn)場副經(jīng)理代管,方可離開。
3.5.2建立約束機制
資格預審文件和投標文件中明確的項目經(jīng)理和技術(shù)員或施工員、質(zhì)量員、
安全員等不得擅自變更,如未經(jīng)發(fā)包人同意,開工時或施工過程中變更,發(fā)
包人有權(quán)解除合同,并追究由此帶來的發(fā)包人一切損失。項目經(jīng)理本人每天
至少8小時,每周不少于3天在本工程施工現(xiàn)場工作。且必須參加每周召開
會例會(有事須請假)。
3.5.3實行項目經(jīng)理評分制
公司已建立項目經(jīng)理評分制,總共10分,根據(jù)評分進行年度考核,作為
評選公司優(yōu)秀項目經(jīng)理及年終獎的根本依據(jù),其中業(yè)主意見占5分,若業(yè)主
反映項目經(jīng)理無故或不請假就離開現(xiàn)場,每次扣0.5分。
3.6勞務工資管理和發(fā)放措施
我單位將嚴格遵守《中華人民共和國勞動法》,認真貫徹《關(guān)干切實解決
建筑業(yè)企業(yè)拖欠農(nóng)民工工資問題的通知》文件精神,以及江蘇省和XX市《市
政府關(guān)于進一步做好解決建設工程中拖欠工程款和拖欠民工工資工作的若干
意見》等一系列文件精神,切實做好此項工作。
無論工程款支付怎樣,我公司將按照下列措施執(zhí)行:
A.如果在工程款按合同支付情況下,將在每月30日全額支付勞務人員當
月工資;
B.如果工程款未按合同支付時,將在每月30日支付勞務人員生活費850
元;
C.在節(jié)假日和學生開學前,將支付勞務人員所完工程量的100%。
3.7施工組織
3.7.1施工區(qū)、段劃分
3.7.1.1施工區(qū)、段的劃分原則
整個標段由二棟廠房和一棟綜合樓組成,施工時,以各棟主體結(jié)構(gòu)施工
為主導工序。精心組織施工區(qū)域內(nèi),空間立體交叉有節(jié)奏流水作業(yè),做到工
序銜接緊密;安裝工程穿插于土建施工過程中,與土建工程施工交叉進行。
3.7.1.2施工區(qū)、段劃分
按照設計圖中建筑物的布局,結(jié)合結(jié)構(gòu)的設計劃分施工區(qū)段,為保證工
期將整個標段劃分成二大施工區(qū)域(4#及5#廠房、綜合樓),組織二班人馬,
進行平行作業(yè)。以便各施工區(qū)內(nèi)部產(chǎn)生流水,縮短工期。
3.7.2施工順序
第一施工區(qū)(4#及5#廠房)一第二施工區(qū)(綜合樓)
3.7.2.2施工段的施工順序
按分部分項工程組織流水施工,其順序為:定位放線一土方開挖一基礎
模板、鋼筋、商品碎一主體結(jié)構(gòu)模板、鋼筋、商品稅~砌體結(jié)構(gòu)一屋面防水
一門窗f內(nèi)裝飾一外裝飾f樓地面f安裝工程f室外一竣工
施工順序的穿插
主體結(jié)構(gòu)一層模板拆除后,即可穿插內(nèi)部結(jié)構(gòu)及安裝工程的施工,以減
少空間和時間上的損失,確保項目建設工期。每一個施工段均本著“先地下
后地上”、“先土建后安裝”“先主體后裝修”的原貝!組織施工。
每一階段都必須完成規(guī)定的工作內(nèi)容,為下一階段創(chuàng)造條件。
安裝工程的插入應遵循的原則為:先土建后安裝,先主管后支管,在土建施
工主體時,預留、預埋好預埋洞、預埋件。下部可穿插施工一些給水的施工,
土建室內(nèi)裝修的同時,安裝全面進入安裝階段。
3.8資源配置
3.8.1勞動力安排計劃
根據(jù)本工程施工需要,由人勞部對作業(yè)人員從技能、責任心、工作經(jīng)驗、
身體素質(zhì)、持證情況等方面選擇合格勞動力,及時組織進行施工,人勞部必須
在工程開工前落實作業(yè)人員。特殊作業(yè)人員必須持有效證件方能上崗,持證率
100%,必要時進行考試,做到好中選優(yōu)。
3.8.1.1勞動力投入計劃
根據(jù)工程的結(jié)構(gòu)形式、建筑構(gòu)造和工作量及工期要求,編制勞動力投入計
劃。
3.8.1.2勞動力進場計劃
根據(jù)施工進度網(wǎng)絡計劃要求編制勞動力投入計劃,按勞動力投入計劃及時
組織作業(yè)人員進入施工現(xiàn)場。
主要勞動力投入計劃表
按工程施工階段投入勞動力情況
工種基礎主體裝修、安裝
施工階段施工階段施工階段收尾階段
木工3050105
碎工3045205
瓦工15301510
抹灰工254010
鋼筋工303052
架子工420105
動力司機4664
電工620206
油漆工004015
焊工4442
起重工3330
水工210106
調(diào)試工0004
普工15303015
合/p>
3.8.1.3人員培訓教育
對參加施工的作業(yè)人員及時進行進場三級教育。
培訓后進行書面測試,合格后方可上崗作業(yè)。
3.8.2工程投入的主要施工機械設備安排計劃
根據(jù)本工程施工的結(jié)構(gòu)類型特點,配置合適的大、中、小型施工機械設備,
以滿足工程進度的需要。
3.8.2.1垂直運輸設備
現(xiàn)場設置2臺QTZ40固定式塔吊負責工程施工的垂直運輸。同時負責鋼筋
原材和模板半成品的吊運。
廠房主體碎施工到封頂、綜合樓主體碎施工到二層后在4#廠房和綜合樓附
近各安裝井架各一臺,以滿足填充材料等小型材料上下。
為滿足施工及進度要求,碎澆筑采用碎固定泵泵送。
3.8.2.2水平運輸設備
?配備FC-1型機動翻斗車1臺,負責砂漿,碎及零星建材的運輸。
?配備12t自卸車2輛,負責砂、石等建材的運輸。
?樓層內(nèi)水平運輸采用手推架子車。
3.8.2.3土方機械設備
配備履帶式反鏟挖土機0.5m3二臺進行土方開挖;在清槽施
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 新人教版七年級數(shù)學上冊 3.3 《解一元一次方程》聽評課記錄1
- 人教版歷史七年級上冊第14課《溝通中外文明的“絲綢之路”》聽課評課記錄
- 現(xiàn)場電力服務合同(2篇)
- 生活設施租賃協(xié)議書(2篇)
- 新版湘教版秋八年級數(shù)學上冊第二章三角形課題已知邊角作三角形聽評課記錄
- 新版華東師大版八年級數(shù)學下冊《18.2平行四邊形的判定》聽評課記錄
- 湘教版數(shù)學八年級下冊4.3《一次函數(shù)的圖象》聽評課記錄1
- 魯人版道德與法治七年級下冊13.3《正視壓力 輕松前行》聽課評課記錄
- 2022年新課標八年級上冊歷史第3課太平天國運動聽課評課記錄
- 人教版九年級數(shù)學上冊22.2.1《二次函數(shù)與一元二次方程》聽評課記錄
- 裝修工程延期協(xié)議
- 《梅大高速茶陽路段“5·1”塌方災害調(diào)查評估報告》專題警示學習
- 2024年09月北京中信銀行北京分行社會招考(917)筆試歷年參考題庫附帶答案詳解
- 《大健康解讀》課件
- 2025年度交通運輸規(guī)劃外聘專家咨詢協(xié)議3篇
- 2024年04月北京中信銀行北京分行社會招考(429)筆試歷年參考題庫附帶答案詳解
- 專項債券培訓課件
- 《會務的組織和管理》課件
- 2024年公司領(lǐng)導在新年動員會上的講話樣本(3篇)
- 《倒虹吸管安全評價導則》
- 2025年中國濕度傳感器行業(yè)深度分析、投資前景、趨勢預測報告(智研咨詢)
評論
0/150
提交評論