項目二標(biāo)段工程
三角型鋼組合懸挑腳手架工程
專項施工方案
(格式最終版)
編制單位:中國建筑第八工程局有限公司
編制人:
審核人:
審批人:
日期:
目錄
1編制依據(jù).............................................................................................................................................................4
1.1施工圖........................................................................................................................................................4
1.2主要規(guī)范、規(guī)程、標(biāo)準(zhǔn).............................................................................................................................4
1.3國家、地方行政文件等.............................................................................................................................4
2工程概況.............................................................................................................................................................5
2.1工程總體概況............................................................................................................................................5
2.2工程設(shè)計概況............................................................................................................................................5
2.2.1建筑概況.........................................................................................................................................5
2.2.2結(jié)構(gòu)概況.........................................................................................................................................7
2.3專項工程概況............................................................................................................................................8
2.3.1腳手架性質(zhì)、用途及荷載限定.....................................................................................................8
2.3.2腳手架部位及相關(guān)參數(shù).................................................................................................................8
2.4施工平面布置............................................................................................................................................9
2.4.1結(jié)構(gòu)平面圖.....................................................................................................................................9
2.4.2結(jié)構(gòu)剖面圖...................................................................................................................................11
2.5專項工程重點、難點、特點...................................................................................................................15
3腳手架設(shè)計.......................................................................................................................................................15
3.1腳手架體系選擇......................................................................................................................................15
3.2腳手架設(shè)計方案......................................................................................................................................15
3.2.1腳手架基礎(chǔ)設(shè)計...........................................................................................................................16
3.2.2架體設(shè)計.......................................................................................................................................16
3.2.3連墻件設(shè)計...................................................................................................................................16
3.2.4剪刀撐和橫向斜撐設(shè)計...............................................................................................................16
3.2.5卸荷設(shè)計.......................................................................................................................................17
3.2.6腳手架開口處構(gòu)造設(shè)計...............................................................................................................18
3.2.7安全防護(hù)設(shè)計...............................................................................................................................18
3.2.8避雷設(shè)計.......................................................................................................................................18
3.2.9組合式型鋼懸挑架施工區(qū)域.......................................................................................................18
3.2.10三角架細(xì)部節(jié)點及構(gòu)造要求........................................................................................................19
3.2.11懸挑鋼梁設(shè)計圖............................................................................................................................22
3.2.12懸挑鋼梁錨固................................................................................................................................23
3.2.13鋼梁上立桿固定點........................................................................................................................24
3.2.14架體連墻件做法............................................................................................................................24
3.2.15三角架錨固....................................................................................................................................24
3.2.16鋼絲繩卸荷措施............................................................................................................................26
2.5.9部分加強做法..................................................................................................................................26
4施工計劃...........................................................................................................................................................28
4.14.1架體使用周期.....................................................................................................................................28
4.2盤扣式支撐系統(tǒng)主要材料.........................................................................................................................29
4.3盤扣式支撐系統(tǒng)材料制作質(zhì)量標(biāo)準(zhǔn)..........................................................................................................29
1
4.4盤扣式支撐系統(tǒng)搭設(shè)前的檢查..................................................................................................................30
5施工工藝技術(shù)...................................................................................................................................................30
5.1組合型鋼懸挑架搭設(shè)構(gòu)造要求...............................................................................................................30
5.2立桿..........................................................................................................................................................31
5.3豎向斜桿..................................................................................................................................................31
5.4連墻件的設(shè)置應(yīng)符合下列規(guī)定:...........................................................................................................32
4.1.7安全網(wǎng)..............................................................................................................................................32
5.5落地式腳手架搭設(shè)構(gòu)造要求...................................................................................................................32
5.5.1腳手架基礎(chǔ)的要求..........................................................................................................................32
5.5.2連墻桿..............................................................................................................................................32
5.5.3腳手板..............................................................................................................................................33
5.6安全防護(hù)搭設(shè)..........................................................................................................................................33
5.7鋼梁懸挑安裝工藝..................................................................................................................................34
5.7.1工藝流程..........................................................................................................................................34
5.7.2組合型鋼懸挑架..............................................................................................................................36
6施工安全保證措施............................................................................................................................................37
6.1組織保證措施..........................................................................................................................................37
6.1.1施工組織架構(gòu)..................................................................................................................................37
6.1.2驗收組織架構(gòu)..................................................................................................................................38
6.2技術(shù)保證措施..........................................................................................................................................38
6.3安全保證措施..........................................................................................................................................39
6.4季節(jié)性施工保證措施..............................................................................................................................39
6.5防疫管理措施..........................................................................................................................................39
6.5.1施工人員日常測溫管理...............................................................................................................39
6.5.2施工現(xiàn)場封閉式集中管理...........................................................................................................40
6.5.3生活區(qū)封閉式集中管理...............................................................................................................40
6.6監(jiān)測監(jiān)控要求..........................................................................................................................................40
7施工管理及作業(yè)人員配備和分工....................................................................................................................41
8腳手架的驗收和管理........................................................................................................................................41
8.1盤扣式支撐系統(tǒng)的檢查、驗收..................................................................................................................41
8.2組合型鋼懸挑架檢查驗收.......................................................................................................................43
8.3腳手架的安全管理..................................................................................................................................45
8.4腳手架搭設(shè)作業(yè)危險源、危險點預(yù)測與預(yù)控措施...............................................................................46
8.5腳手架的拆除作業(yè)危險源、危險點預(yù)測與預(yù)控措施...........................................................................47
8.6腳手架作業(yè)危險源識別與預(yù)控...............................................................................................................47
9應(yīng)急處理措施...................................................................................................................................................49
9.1應(yīng)急救援機構(gòu)及職責(zé)..............................................................................................................................49
9.2應(yīng)急物資保障..........................................................................................................................................50
9.3應(yīng)急救援工作程序..................................................................................................................................50
10架體計算書及相關(guān)圖紙....................................................................................................................................52
10.1多排懸挑架主梁驗算計算書(3100mm懸挑4排桿)........................................................................52
10.2多排懸挑架主梁驗算計算書(懸挑2200mm三立桿).......................................................................63
10.3型鋼懸挑腳手架(盤扣式)計算書(4m標(biāo)準(zhǔn)梁)..................................................................................73
2
10.4盤扣式腳手架計算書(落地式)...........................................................................................................92
10.5三角架計算書(1500mm)....................................................................................................................99
3
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
1編制依據(jù)
1.1施工圖
序號圖紙類別編號出圖日期
河西區(qū)解放南路48號地項目二標(biāo)段建
12020-H182020.12.14
筑圖紙
河西區(qū)解放南路48號地項目二標(biāo)段建
22020-H182020.12.14
筑圖紙
1.2主要規(guī)范、規(guī)程、標(biāo)準(zhǔn)
序號規(guī)范、規(guī)程名稱規(guī)范、規(guī)程編號
1《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
2《碳素結(jié)構(gòu)鋼》GB/T700—2006
3《可鍛鑄鐵件》GB/T9440-2010
4《鋼管腳手架扣件》GB15831-2006
5《普通螺紋》GB/T196—2003
6《鋼結(jié)構(gòu)設(shè)計規(guī)范》GB50017-2017
7《安全網(wǎng)》GB5725-2009
8《鋼管腳手架扣件》GB15831-2006
9《吊環(huán)》GB/T8395-2007
10《一般用途鋼絲繩》GB/T20118-2006
11《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》GB50204-2015
12《直縫電焊鋼管》GB/T13793-2008
13《建筑施工臨時支撐結(jié)構(gòu)技術(shù)規(guī)范》JGJ300-2013
14《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
15《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
16《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
17《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》JGJ46-2014
18《建筑施工承插型盤扣式鋼管支架安全技術(shù)規(guī)程》JGJ231-2010
19《承插型盤扣式鋼管支架構(gòu)件》JG/T503-2016
20《建筑鋼結(jié)構(gòu)焊接技術(shù)規(guī)程》JGJ81-2002
21《建筑施工承插型盤扣式鋼管支架安全技術(shù)規(guī)程》DBJ/T13-318-2019
1.3國家、地方行政文件等
序號文件名稱編號
住房和城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施《危險性較大分部
1建質(zhì)[2018]31號文
分項工程安全管理規(guī)定》有關(guān)問題的通知
2危險性較大的分部分項工程安全管理規(guī)定住建部37號令
市建委關(guān)于印發(fā)《天津市房屋建筑和市政基礎(chǔ)設(shè)施工
3津建發(fā)2018年9號
程危險性較大的分部分項工程安全管理辦法》的通知
4
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
2工程概況
2.1工程總體概況
建設(shè)單位:
監(jiān)理單位:
施工單位:
設(shè)計單位:
勘察單位:
計劃工期:1042日歷天
計劃開工時間:2020年7月18日
計劃竣工時間:2023年5月25日
河西區(qū)解放南路48號地項目二標(biāo)段位于天津市河西區(qū)洞庭路與太湖路交口,項目范圍東
至洞庭路,南至太湖路,西至規(guī)劃內(nèi)江路,北至規(guī)劃支路七。
本工程為高層商品房項目,為群體工程,總建筑面積約為100252.22㎡;包括16#、17#、
18#、20#、21#、22#、23#住宅樓,一個幼兒園、一個托老所、配建4(黑號站)、配建5(黑
號站)和一個地下車庫等。住宅建筑高度(女兒墻頂):99.4m(最高),建筑層數(shù)、層高:
23#樓33層、22#樓28層、21#樓24層、20#樓15層、18#樓17層、16#、17#樓16層,住宅
地下1層,車庫地下1層;住宅層高3.1/3.0m。室內(nèi)地坪設(shè)計標(biāo)高±0相當(dāng)于絕對標(biāo)高3.45m
(大沽高程),室內(nèi)外高差設(shè)為0.15m;抗震設(shè)防烈度:8度,防水等級:屋面防水為I級;
地下室防水為二級(變配電間等為一級)。
本工程地下室、幼兒園、托老所、配電室為框架結(jié)構(gòu),住宅為現(xiàn)澆剪力墻結(jié)構(gòu)。住宅樓、
幼兒園、地下車庫基礎(chǔ)為樁基礎(chǔ);托老所、配電室為天然地基+獨立基礎(chǔ)。
2.2工程設(shè)計概況
2.2.1建筑概況
表2.2-1建筑概況
序號項目內(nèi)容
16#樓10565.81㎡
建筑面積17#樓7888.22㎡建筑面積總建筑面積
1住宅
(㎡)18#樓4766.09㎡72870.41100252.22㎡
20#樓9912.55㎡
5
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
21#樓10670.92㎡
22#樓13355.39㎡
23#樓15711.43㎡
地下車庫23273.54㎡
配建4204㎡
配建5204㎡
幼兒園2800㎡
托老所900.27㎡
16#樓、17#樓地上16層,地下1層
18#樓地上17層,地下1層
20#樓地上15層,地下1層
21#樓地上24層,地下1層
2建筑層數(shù)22#樓地上28層,地下1層
23#樓地上33層,地下1層
幼兒園地上3層
托老所地上2層
地下車庫地下1層
16#樓、17#樓3.1m
18#樓3.1m
20#樓3.1m
3建筑層高(m)21#樓3m
22#樓3m
23#樓3m
地下車庫3.6m
4±0.000標(biāo)高3.45/3.75
16#樓、17#樓50.00m
18#樓53.10m
5建筑高度(m)20#樓46.90m
21#樓72.40m
22#樓84.40m
6
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
23#樓99.40m
幼兒園13.00m
托老所7.60m
住宅樓21#、22#、23#樓灌注樁基礎(chǔ)
住宅樓16、17、18、20#樓、幼兒園為PHC預(yù)應(yīng)
基礎(chǔ)結(jié)構(gòu)形式
力管樁基礎(chǔ),地下車庫、配建4、配建5、托老
6結(jié)構(gòu)形式
所為獨立基礎(chǔ)
主體結(jié)構(gòu)形式現(xiàn)澆剪力墻、框架
屋蓋結(jié)構(gòu)形式現(xiàn)澆鋼筋混凝土平屋面
設(shè)計使用年
7混凝土結(jié)構(gòu)50年抗震烈度8度
限
2.2.2結(jié)構(gòu)概況
本工程結(jié)構(gòu)概況見表2.2-2、2.2-3。
表2.2-2結(jié)構(gòu)概況
構(gòu)件描述
樓座結(jié)構(gòu)體系樓板等水
梁墻
平構(gòu)件
16#、17#、18#、20#、21#、22#、砼梁現(xiàn)澆
剪力墻現(xiàn)澆
23#樓
地下車庫、幼兒園、托老所、配建
框架結(jié)構(gòu)現(xiàn)澆砼梁現(xiàn)澆
4、配建5
表2.2-3結(jié)構(gòu)設(shè)計基本信息情況
結(jié)構(gòu)安全等級及抗震安全等級二級、抗震設(shè)防類別標(biāo)準(zhǔn)設(shè)防類(丙類),幼兒園、托老所
設(shè)防類別為重點設(shè)防類(乙類)
抗震構(gòu)造措施對應(yīng)烈8度0.20g區(qū),第二組,Ⅲ類場地
度
混凝土等級梁板主要采用C30混凝土
墻柱主要采用C60、C55、C50、C45、C40、C35、C30混凝土
梁300×600、300×900、250×900、400×700、400×650、400
主要構(gòu)件尺寸
×800、300×1800、250×400、350×650、300×500、250×
7
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
500
柱400×600、500×850、400×1200、500×600、400×1100、400
×1250、400×500
鋼筋工程HPB300、HRB400E
2.3專項工程概況
按照《住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施<危險性較大的分部分項工程安全管理規(guī)定>有關(guān)
問題的通知》建辦質(zhì)〔2018〕31號的要求,腳手架工程:分段架體搭設(shè)高度20m及以上的懸
挑式腳手架工程,屬超過一定規(guī)模的危險性較大的分部分項工程,施工單位應(yīng)編制安全專項
施工方案并組織專家對專項方案進(jìn)行論證。
結(jié)合本工程結(jié)構(gòu)形式及施工進(jìn)度整體安排,小高層16#、17#、18#、20#均采用雙排落地
式腳手架和懸挑腳手架相結(jié)合的外架方式。
2.3.1腳手架性質(zhì)、用途及荷載限定
本專項工程為主體結(jié)構(gòu)作業(yè)腳手架選擇落地式雙排盤扣式腳手架,施工荷載值為3kN/㎡,
同時考慮2層施工。
2.3.2腳手架部位及相關(guān)參數(shù)
序號項目內(nèi)容
1搭設(shè)部位16#、17#、18#、20#樓外檐
16#樓53.45m;17#樓53.45m;18#樓55.56m;20#樓
2建筑檐高
50.35m;
3混凝土梁板C30
4強度等級柱C40、C35、C30
17樓南側(cè)、20樓西側(cè)部分落地架坐落在地基土上,地耐
5架體基礎(chǔ)情況力105kpa;承載力不滿足要求,需要進(jìn)行硬化處理。其
余部分均坐落于車庫頂板上,車庫頂板砼強度C35。
8
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
2.4施工平面布置
2.4.1結(jié)構(gòu)平面圖
16#樓、20#樓結(jié)構(gòu)平面圖
17#樓結(jié)構(gòu)平面圖
9
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
18#樓結(jié)構(gòu)平面圖
10
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
2.4.2結(jié)構(gòu)剖面圖
17#樓剖面圖
11
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
18#樓剖面圖
12
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
16#樓剖面圖
13
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
20#樓剖面圖
14
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
2.5專項工程重點、難點、特點
2.5.1本工程外墻懸挑構(gòu)件較多,樓梯外探尺寸較大,局部鋼梁懸挑長度達(dá)到3100mm;
2.5.2建設(shè)單位第三方飛檢對防滲漏要求較高,鋼梁布設(shè)要求躲開廚衛(wèi)反坎,局部陽角承放
射性布置,存在斜鋼梁情況;
2.5.3采用盤扣式雙排腳手架,模數(shù)化設(shè)計,懸挑結(jié)構(gòu)采用聯(lián)梁形式,聯(lián)梁間的固定和次梁
增加的荷載需專項考慮;
2.5.4采用三角型鋼和工字鋼兩種主梁形式,需分別計算兩種模型。
3腳手架設(shè)計
3.1腳手架體系選擇
序號項目內(nèi)容
1架體性質(zhì)結(jié)構(gòu)腳手架
2搭設(shè)部位16#、17#、18#、20#外檐
落地式腳手架最高搭設(shè)高度38m(17#樓南側(cè)肥槽位置)、懸挑式
2搭設(shè)高度
腳手架高度為24m。
3搭設(shè)底標(biāo)高-1.65m、-5.85m
4立桿盤扣式腳手架Q345鍍鋅鋼管
5里排立桿距墻0.2m、0.3m
步距1500mm
架體間
6縱距1500mm
距
橫距900mm
7腳手板木腳手板
8鋼絲繩卸荷6×19(?16)
9連墻桿件落地式兩步三跨設(shè)置,懸挑式兩步兩跨設(shè)置,鋼管雙扣件連接,
10剪刀撐盤扣體系專用豎向斜撐、橫向斜撐3跨1設(shè)
11使用荷載3kn/㎡,2層作業(yè)面
3.2腳手架設(shè)計方案
16#、17#、18#、20#樓均采用落地式及懸挑式組合形式腳手架,所有樓棟均在距屋頂結(jié)
構(gòu)6層位置懸挑,具體懸挑位置為16#樓11層樓地面,17#樓11層樓地面,18#樓12層樓地
面,16#樓10層樓地面,20#樓西側(cè)山墻及北側(cè)1-19軸需配合建設(shè)單位樣板展示區(qū)施工,需在
15
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
6層樓地面進(jìn)行懸挑,懸挑3層后同樣在10層樓地面整體懸挑至屋面。各樓棟最后一段懸挑
腳手架高度均為24m,落地式腳手架高度為16#樓33.85m,17樓為33.85m(南側(cè)部分立桿置
于肥槽,高度為38m),18#樓37m,20#樓30.75m。17#樓南側(cè)、20#樓西側(cè)置于肥槽內(nèi),地
基承載力不滿足安全使用要求,需對該部位施工砼墊層,200mm厚C20砼澆筑。
3.2.1腳手架基礎(chǔ)設(shè)計
(1)17#樓南側(cè)、20#樓西側(cè)腳手架搭設(shè)置于肥槽內(nèi),地基承載力經(jīng)驗算不滿足要求,故
對原回填土進(jìn)行夯實后澆筑200mm厚混凝土(強度等級C20)墊層,寬與肥槽同寬。待混凝
土墊層具備強度后方可搭設(shè)腳手架。其他部位均置于車庫頂板上,車庫頂板砼強度為C35。頂
板厚度250mm。
(2)搭設(shè)時在立桿底部鋪設(shè)4m×0.25m×0.05m防腐木墊板,作為腳手架底座。墊板與
混凝土墊層表面接觸密實。
(3)立桿底座置于墊板之上且底面標(biāo)高宜高于自然地坪50mm,在架體基礎(chǔ)外500mm
處設(shè)排水溝,保證腳手架基礎(chǔ)不被浸泡。
3.2.2架體設(shè)計
(1)本工程腳手架搭設(shè)形式為雙排盤扣式鋼管腳手架,懸挑層為16#樓11層樓地面,17#
樓11層樓地面,18#樓12層樓地面,16#樓10層樓地面,懸挑高度最大24m,上述懸挑層以
下均為落地式雙排盤扣腳手架。
(2)腳手架搭設(shè)排距為0.9m;立桿的縱距1.5m;步距1.5m;內(nèi)排架距離墻體長度為
0.3m,懸挑式腳手架南側(cè)飄窗位置局部為0.2m,詳見懸挑腳手架平面布置圖。
3.2.3連墻件設(shè)計
(1)本工程連墻件采用剛性連墻桿連接,落地式雙排腳手架連墻件按兩步三跨設(shè)置,
懸挑部分按兩步兩跨設(shè)置,采用扣件式鋼管腳手架形式連接,連墻件水平桿采用48.3×3.0mm
鋼管,雙扣件連接。
(2)連墻件采用連墻桿與腳手架內(nèi)外立桿相連接。拉結(jié)部位優(yōu)先選擇窗洞口或框架柱拉
結(jié)。局部不滿足拉結(jié)要求處采用在結(jié)構(gòu)墻體上打膨脹螺栓固定鋼板和鋼短管,再與連墻桿采
用雙扣件進(jìn)行拉結(jié)。連墻件必須與架體立桿相連,設(shè)置在有水平桿的盤扣節(jié)點旁,連接點至
盤扣節(jié)點距離不應(yīng)大于300mm。
3.2.4剪刀撐和橫向斜撐設(shè)計
(1)在腳手架的轉(zhuǎn)角處、開口型腳手架端部應(yīng)由架體底部至頂部連續(xù)設(shè)置斜桿。
(2)應(yīng)每隔不大于3跨設(shè)置一道豎向或斜向連續(xù)斜桿;
16
河西區(qū)解放南路48號地項目二標(biāo)段三角型鋼組合懸挑腳手架工程專項施工方案
中國建筑第八工程局有限公司
(3)豎向斜桿應(yīng)在雙排腳手架外側(cè)相鄰立桿間由底至頂按步連續(xù)設(shè)置。
豎向斜桿搭設(shè)示意圖
1—立桿;2—水平桿;3—豎向斜桿
3.2.5卸荷設(shè)計
1懸挑鋼梁的錨固方式應(yīng)滿足6.3.11條的基本要求,在懸挑鋼梁與鋼絲繩的吊拉位置應(yīng)
焊接U形鋼筋吊環(huán),吊環(huán)直徑應(yīng)按計算確定并應(yīng)不小于16mm,吊環(huán)應(yīng)使用HPB300級鋼筋,
吊環(huán)預(yù)埋錨固長度應(yīng)符合現(xiàn)行國家標(biāo)準(zhǔn)《混凝土結(jié)構(gòu)設(shè)計規(guī)范》GB50010中鋼筋錨固的規(guī)定。
2鋼絲繩與
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025的職工持股資金信托合同范本
- 新建數(shù)碼交直流兩用監(jiān)測儀項目立項申請報告
- 聲控開關(guān)生產(chǎn)加工項目可行性研究報告
- 合成橡膠項目立項申請報告
- 電磁流量計項目立項申請報告
- 無人駕駛汽車技術(shù)的發(fā)展-洞察分析
- 2025汔車運輸合同
- 2025技術(shù)服務(wù)合同書(含技術(shù)培訓(xùn)、技術(shù)中介)
- 2025土地種植苗木轉(zhuǎn)讓合同范本
- 2024年大型商場商場裝修工程質(zhì)保合同規(guī)范文本6篇
- 2024年-江蘇省安全員-A證考試題庫及答案
- 2024年青干班培訓(xùn)個人總結(jié)
- 2021~2022學(xué)年廣東廣州越秀區(qū)八年級上學(xué)期期末語文試卷(含答案)
- 固態(tài)電池生產(chǎn)(1GWH)項目可行性研究報告模板-立項拿地
- 中建一期工程履帶吊安拆方案
- 廣東省深圳市坪山區(qū)2024學(xué)年七年級上學(xué)期期末數(shù)學(xué)試題【含答案】
- 2024游樂新“室”界室內(nèi)樂園洞察與趨勢研究報告
- 2024-2025學(xué)年一年級數(shù)學(xué)上冊期末樂考非紙筆測試題(二 )(蘇教版2024秋)
- 辦公樓電氣改造施工方案
- 浙江省衢州市2023-2024學(xué)年高一上學(xué)期期末英語試題(含答案)3
- 校園餐整治存在的問題及建議
評論
0/150
提交評論