1312-STR-1200梁、柱模板及支架施工方案(英文版)_第1頁
1312-STR-1200梁、柱模板及支架施工方案(英文版)_第2頁
1312-STR-1200梁、柱模板及支架施工方案(英文版)_第3頁
1312-STR-1200梁、柱模板及支架施工方案(英文版)_第4頁
免費預覽已結(jié)束,剩余3頁可下載查看

下載本文檔

版權(quán)說明:本文檔由用戶提供并上傳,收益歸屬內(nèi)容提供方,若內(nèi)容存在侵權(quán),請進行舉報或認領(lǐng)

文檔簡介

1、Construction Method StatementFor Beam, Column Formworks and supporting frames of 1312-STR-12001. Scope12. Material13. Construction methods and technical measures21. ScopeThe method statement herein is compiled by mainly focusing on installation of column and beam formworks of 1312-STR-1200 and their

2、 supporting frames.2. Materials1)Plywood ( =15mm) shall be adopted to precast formworks of beam and column. The wooden board(50100mm) and the steel tube( 48.3 shall4.0) be used to respectively support the inner kneel and outer kneel of formworks2)The steel tube ( 48.3 4.0) shall be used to make supp

3、ort of beam and column formworks and to erectscaffoldings.3) The upright monkey ladder shall be made of aluminum alloy and the planks will be made of steel.3. Construction methods and technical measures3.1.To ensure the stability of supporting frames, the concrete pouring of column and beam shall be

4、 done separately by three times .The first time of pouring for column shall reach the elevation of 109000mm and the second time of pouring for column shall reach the elevation of 116850.Pouring the for the part of the column above elevation of 116850mm shall be done together with concrete pouring fo

5、r the beam. The supporting frame of beam formwork shall be connected rigidly to the poured column prior to starting concrete pouring on the beam.3.2.Method of reinforcement for column formwork.C1/C1a( sectional dimension 850750mm)、C2( sectional dimension 750750mm)5 ways of keels inside eachside face

6、 of column formwork and double steel tubes with a spacing of 500mm for column hoop. Tie bolts 12 withspacing of 500mm installed inside side face. The upper, middle and lower column hoops of column formwork shall beconnected to support outside to avoid tilting or inclinedness.3.3.Methods of reinforce

7、ment and supporting for beam formwork. See table 3.1.2.Table-3.1.2Code1GX1/5/6/1GX21GX31GX4/11GY1/4/51GY21B11B27/8/9 、1B3GY3、1B4Sectional Dimensions4007007001700135001040060065010006009007509001005000Formwork ofInner keel offormwork35543444bottom of beam( line )Spacing between outer keels of0.450.60

8、.60.60.4formwork(m)Two sidesSpacinSupport on theof1.21.0g ofbottom of beamformwork(mposts)Span of beams (m)0.50.5Bay of posts(m)1.51.5Bearing post additionally fitted02210111on the bottom of beam (line )SideInner keel of formworkformwor

9、k( line )45754555of beamOuter keel of formwork(line)0.60.4Spacing ( m)TieDiameter12161612/121212BoltH ( m)0.5/Code1GX1/5/6/1GX21GX31GX4/11GY1/4/51GY21B11B27/8/9 、1B3GY3、1B4l(m )0.6/Note: “ H” indicates the distance from tie bolt to the bottom of

10、 beam.“ I ” indicates the spacing on the direction ofbeam spans. The upper parts and lower parts of beam formwork shall be connected to the support tightly by steel tubecouplers.3.4.Procedure and requirements for erection of supporting frame.1)Procedure of erection: Place base plate(board) with a th

11、ickness of 50mm Erect base lift Connect the post andbase lift by couplersInstall the first runner and bearer and connect them to the post tightly with couplersRepeated the last stepErect cross bracingsLay steel planks.2). Lay the base plate (base support) and place the base lift as per the prioritie

12、s of beam locations. The longitudinal base lift shall be fixed to the post with right angle couplers and the post shall be not more than 200mm to the bottom of steel tube. However, the transverse base lift shall be fixed to the post with right angle couplers and the post shall be close to the undern

13、eath of longitudinal base lift.3) The posts shall be erected as per the sequence of positioning. The posts shall be connected and fixed to the longitudinal and transverse base lifts. For erection of posts, the joints on each lift height shall be pair joint couplers (except for the top height lift) a

14、nd ensure that the pair joints on the same section shall keep some space (50% of the sectional size)4).The bearer shall be set on the inner side of the post and the length of single post shall be not less than 3 bays. The bearer shall be connected by pair joint couplers and conform to the following

15、rules: the ends for connection of two adjacent bearers shall not be set in the same bay or same lift height. Any two adjacent connection joints not in the same bay or lift height shall keep a distance of not less than 500mm on the horizontal direction. The distance fromeach joint centre to the neare

16、st main joint shall be not more than 1/3 of the longitudinal spacing.5).The connection between runner and bearer on the bottom of beam formwork shall be connected to the post bydouble couplers.6).Add one bearer in the middle of two bearers on the top lift of supporting frame. The top of the bearer s

17、hall be tightlyto the surrounding framed supports.7) The erection of cross bracing: the cross bracings shall be erected along with the scaffolding structure. The bracingson the bottom liftshall be all supported by the base plate.The method of lapjoint shallbe adopted forbracings,connection. The leng

18、th of lap joint shall not be less than 1m and fixed by 3 rotating couplers. The distance from theedge coupler?s cover on the top to the top of the post shall be not less than 100mm.The bracings shall be fixed to theextended part of runner or the post by rotating couplers. The central line of rotary

19、coupler shall keep a distance of notmore than 150mm to the main joint.8). Rigid connection shall be done in every 3 meters vertically between the formwork support, scaffolding and thecolumn of the frame around which the construction work has been completed.9). Cross bracings shall be erected respect

20、ively on the ends of outer sides , corners and the central vertical face with adistance of less than 15m of the scaffoldings .The sequence of cross bracing erection shall be from the bottom to thetop. The width of cross bracing is 6m, which makes an angle of 4560with the ground.10) .The wall fastene

21、rs of the scaffoldings shall be laid out horizontally close to the main jointas per the rule of“ two liftheights and threebays ” . The distance between fasteners and main joints shall be not more than 300mmm.11) .Planks shall be fully laid on the working platform with sound firmness and tied with st

22、eel wire #14 on three runners.Both ends of the scaffolding planks shall be reliable and fixed so as to prevent capsizing.12) .Guardrails: Erect two-line guardrails above the working platform and the upper line of guardrails (top rail) shall be 1.2m tall while the mid rail shall be set in the middle

23、line of the lift height. Toe boards shall be erected with a height of 180mm to the platform.1) Access for going up and down :Place 1 set of upright monkey ladder respectively on the southwest corner and northeast corner of scaffoldings. A rest platform shall be erected at the height of 4.5m of the u

24、pright monkey ladder.3.5.Dismantling of supporting frame.1).The technician shall conduct a technical disclosure for all the working crew members who are going to perform dismantling work prior to commencement of dismantling work and all the attendees are required to sign on the written form of this

25、said technical disclosure.2). Arrange the power cables properly before dismantling the supporting frame. For the cables that cannot be dismantled or put aside, they shall be buried by soil.3). Barricade the area with rope or warning tape prior to starting dismantling work. The work can be started on

26、ly in the presence of watchman, HSE personnel and foreman.4) During dismantling the scaffoldings, the workers must wear harness and be equipped with tool bag. The workersshall not hold the steel tube and wrenches simultaneously .The tools shall be kept in the tool bag after use.5).The procedure for

27、dismantling scaffoldings: From the top to the bottom, opposite to the sequence of erection. Thegeneral sequence for dismantling: guardrails scaffolding planks cross bracings runner bearer postpassed onto the ground couplers removing dismantled parts stacking and storing as per the specifications.6)

28、Someoneshall be appointedfor monitoringthe dismantlingwork for structuralform of scaffoldings .Thecrewmembersshallacknowledgedwiththeirrespectivegivendutiesand work underunitedinstruction .Theworkingpostsplatform shall be with enough space7) It is not allowed to dismantle a vertical platform from 2

29、different points or from 2 different lift heights at the same time .Do not move to the next one until the last one has been completely dismantled. If the dismantling is being done at 2 different positions of the scaffolding system, the height different shall be within 2 lift heights so that the stability ofthe structural form will not be destroyed.8) The wall fasteners shall be dismantled along with the scaffoldings lift by lift. It is not allowed to di

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
  • 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

評論

0/150

提交評論