項(xiàng)目專項(xiàng)施工方案
高速公路濟(jì)南至泰安段改擴(kuò)建工程
空心板預(yù)制施工方案
編制:
審核:
審批:
日期:
項(xiàng)目專項(xiàng)施工方案
目錄
第一章編制依據(jù).............................................................................................................1
1.1編制依據(jù)...................................................................................................................1
1.2編制范圍...................................................................................................................1
1.3編制原則...................................................................................................................1
1.3.1確保工期.........................................................................................................1
1.3.2質(zhì)量控制.........................................................................................................2
1.3.3安全第一、預(yù)防為主......................................................................................2
1.3.4文明施工.........................................................................................................2
第二章工程概況.............................................................................................................2
2.1工程概況...................................................................................................................2
2.2技術(shù)標(biāo)準(zhǔn)...................................................................................................................2
2.3特大、大中橋設(shè)置情況............................................................................................4
2.4預(yù)制場(chǎng)建設(shè)...............................................................................................................7
2.4.1區(qū)域劃分.........................................................................................................7
2.4.2臺(tái)座配置及生產(chǎn)能力......................................................................................7
第三章施工安排.............................................................................................................7
3.1施工組織機(jī)構(gòu)...........................................................................................................7
3.2施工管理人員...........................................................................................................8
3.3項(xiàng)目管理目標(biāo).........................................................................................................10
第四章施工進(jìn)度計(jì)劃...................................................................................................10
4.1施工工期安排.........................................................................................................10
4.2施工進(jìn)度計(jì)劃.........................................................................................................11
第五章施工準(zhǔn)備與資源配置計(jì)劃.................................................................................11
5.1施工準(zhǔn)備.................................................................................................................11
5.1.1技術(shù)準(zhǔn)備.......................................................................................................11
5.1.2現(xiàn)場(chǎng)準(zhǔn)備.......................................................................................................12
5.2資源配置.................................................................................................................12
5.2.1勞動(dòng)力組織...................................................................................................12
5.2.2機(jī)具配置.......................................................................................................12
I
項(xiàng)目專項(xiàng)施工方案
第六章施工方法及工藝要求........................................................................................13
6.1施工工藝流程.........................................................................................................13
6.2施工方法及控制要點(diǎn).............................................................................................14
6.2.1施工準(zhǔn)備.......................................................................................................14
6.2.2鋼筋的制作與安裝.......................................................................................15
6.2.3預(yù)應(yīng)力鋼絞線安裝及張拉............................................................................17
6.2.4模板的制作與安裝.......................................................................................19
6.2.5混凝土澆筑...................................................................................................20
6.2.6模板拆除.......................................................................................................22
6.2.7梁板養(yǎng)生.......................................................................................................22
6.2.8預(yù)應(yīng)力放張...................................................................................................23
6.2.9梁體鑿毛.......................................................................................................23
6.2.10移梁.............................................................................................................24
6.3空心板驗(yàn)收.............................................................................................................24
6.3.1驗(yàn)收程序.......................................................................................................24
6.3.2驗(yàn)收標(biāo)準(zhǔn).......................................................................................................25
6.4質(zhì)量通病及防治措施.............................................................................................25
第七章綠色施工措施...................................................................................................26
7.1環(huán)境保護(hù)及文明施工管理措施..............................................................................26
7.1.1環(huán)境保護(hù)及文明施工管理原則....................................................................26
7.1.2環(huán)境保護(hù)主要控制措施................................................................................26
7.2資源利用管理.........................................................................................................27
7.2.1資源利用管理目標(biāo).......................................................................................27
7.2.2資源利用管理機(jī)構(gòu)和職責(zé)分工....................................................................27
7.3“五節(jié)”實(shí)施措施......................................................................................................29
7.3.1節(jié)能措施.......................................................................................................29
7.3.2節(jié)材措施.......................................................................................................29
7.3.3節(jié)水措施.......................................................................................................29
7.3.4節(jié)地措施.......................................................................................................30
7.3.5人力節(jié)約措施...............................................................................................30
II
項(xiàng)目專項(xiàng)施工方案
第八章工期保證措施...................................................................................................30
8.1工期保證體系.........................................................................................................30
8.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工......................................................................31
8.3工期保證措施.........................................................................................................32
第九章質(zhì)量保證措施...................................................................................................33
9.1質(zhì)量目標(biāo).................................................................................................................33
9.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工..........................................................................33
9.3質(zhì)量保證體系.........................................................................................................34
9.4質(zhì)量保證措施.........................................................................................................36
9.4.1組織措施.......................................................................................................36
9.4.2管理措施.......................................................................................................36
第十章安全文明施工措施............................................................................................36
10.1職業(yè)健康安全管理目標(biāo)........................................................................................36
10.2建立安全組織機(jī)構(gòu),明確安全職責(zé)和權(quán)限........................................................36
10.3施工現(xiàn)場(chǎng)安全生產(chǎn)管理制度................................................................................37
10.3.1班前活動(dòng)記錄.............................................................................................38
10.3.2機(jī)械設(shè)備管理制度.....................................................................................39
10.3.3特種作業(yè)持證上崗制度..............................................................................40
10.3.4安全設(shè)施、設(shè)備驗(yàn)收制度..........................................................................40
10.4安全保證措施.......................................................................................................41
10.4.1施工人員安全保證措施..............................................................................41
10.4.2施工機(jī)械安全保證措施..............................................................................41
第十一章成品保護(hù)措施................................................................................................43
11.1成立成品保護(hù)管理機(jī)構(gòu)........................................................................................43
11.2一般規(guī)定...............................................................................................................43
11.3具體保護(hù)措施.......................................................................................................43
第十二章應(yīng)急預(yù)案.......................................................................................................44
12.1危險(xiǎn)源與風(fēng)險(xiǎn)分析...............................................................................................44
12.2應(yīng)急組織機(jī)構(gòu)及職責(zé)...........................................................................................44
12.3預(yù)防與預(yù)警措施...................................................................................................47
III
項(xiàng)目專項(xiàng)施工方案
12.4應(yīng)急響應(yīng)...............................................................................................................48
12.5信息發(fā)布...............................................................................................................50
12.6后期處置...............................................................................................................50
12.7保障措施...............................................................................................................51
12.8應(yīng)急救援路線.......................................................................................................53
第十三章新型冠狀病毒肺炎疫情防控預(yù)案..................................................................53
13.1風(fēng)險(xiǎn)分析...............................................................................................................53
13.2防護(hù)及救援組織機(jī)構(gòu)及職責(zé)................................................................................54
13.3預(yù)防疫情防控措施...............................................................................................55
13.4監(jiān)測(cè)與預(yù)警...........................................................................................................57
13.5救援響應(yīng)...............................................................................................................58
13.6后期處置...............................................................................................................59
13.7救援保障...............................................................................................................59
第十四章計(jì)算書(shū)...........................................................................................................61
IV
項(xiàng)目專項(xiàng)施工方案
第一章編制依據(jù)
1.1編制依據(jù)
表1.1編制依據(jù)
序
類(lèi)別文件名稱編號(hào)
號(hào)
中華人民共和國(guó)主席
1中華人民共和國(guó)安全生產(chǎn)法
令第十三號(hào)
法律法規(guī)、中華人民共和國(guó)主席
2中華人民共和國(guó)環(huán)境保護(hù)法
行政文件令第九號(hào)
中華人民共和國(guó)國(guó)務(wù)
3建設(shè)工程質(zhì)量管理?xiàng)l例
院令(第714號(hào))
4公路工程技術(shù)標(biāo)準(zhǔn)(平裝版)JTGB01-2014
5公路橋涵施工技術(shù)規(guī)范JTG/T3650-2023
6公路工程質(zhì)量檢驗(yàn)評(píng)定標(biāo)準(zhǔn)第一冊(cè)土建工程JTGF80/1-2017
7公路工程施工安全技術(shù)規(guī)范JTGF90-2015
8鋼筋焊接及驗(yàn)收規(guī)程JGJ18-2012
9鋼筋機(jī)械連接技術(shù)規(guī)程JGJ107-2016
10行業(yè)規(guī)范鋼筋焊接接頭試驗(yàn)方法標(biāo)準(zhǔn)JGJ/T27-2014
11混凝土強(qiáng)度檢驗(yàn)評(píng)定標(biāo)準(zhǔn)GB50107-2010
12混凝土結(jié)構(gòu)工程施工規(guī)范GB50666-2011
13混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范GB50204-2015
14預(yù)應(yīng)力混凝土用鋼絞線GB/T5224-2014
15預(yù)應(yīng)力筋用錨具、夾具和連接器GB/T14370-2015
16施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(附條文說(shuō)明)JGJ46-2005
17設(shè)計(jì)文件xx高速公路濟(jì)南至泰安段改擴(kuò)建工程施工圖紙
1.2編制范圍
本方案適用于xx高速濟(jì)南至泰安段改擴(kuò)建工程(K415+160~K448+482.870)空心
板預(yù)制施工。
1.3編制原則
施工方案應(yīng)滿足設(shè)計(jì)要求、技術(shù)標(biāo)準(zhǔn)、規(guī)范、規(guī)程并滿足施工現(xiàn)場(chǎng)實(shí)際施工需要。
以確保工程安全、優(yōu)質(zhì)、按期完成。
1.3.1確保工期
1
項(xiàng)目專項(xiàng)施工方案
根據(jù)本工程的特點(diǎn)和要求,在保證質(zhì)量、安全可靠的前提下合理安排施工工序,優(yōu)
化施工組織,各工序緊密銜接,避免不必要的重復(fù)工作,以保證施工連續(xù)均衡有序地進(jìn)
行,確保施工工期按計(jì)劃節(jié)點(diǎn)完成,力爭(zhēng)提前完成。
1.3.2質(zhì)量控制
確立質(zhì)量目標(biāo)、制定創(chuàng)優(yōu)規(guī)劃、嚴(yán)格按照質(zhì)量體系運(yùn)作,以工作質(zhì)量確保每道工序
和每項(xiàng)工程的工程質(zhì)量。
1.3.3安全第一、預(yù)防為主
確立安全工作目標(biāo)、完善規(guī)章制度、層層簽訂安全生產(chǎn)責(zé)任狀,強(qiáng)化安全教育和安
全管理,狠抓現(xiàn)場(chǎng)各項(xiàng)規(guī)章制度、措施的落實(shí),確保安全生產(chǎn)目標(biāo)的實(shí)現(xiàn)。
1.3.4文明施工
堅(jiān)持自始至終對(duì)施工現(xiàn)場(chǎng)的全過(guò)程進(jìn)行嚴(yán)密監(jiān)控,以科學(xué)的方法實(shí)行動(dòng)態(tài)管理,并
按動(dòng)、靜結(jié)合的方法精心布置和規(guī)劃施工現(xiàn)場(chǎng),保護(hù)周?chē)h(huán)境。嚴(yán)格施工管理,開(kāi)展文
明施工活動(dòng),做到文明施工,爭(zhēng)創(chuàng)標(biāo)準(zhǔn)化施工現(xiàn)場(chǎng)。
第二章工程概況
2.1工程概況
xx高速公路濟(jì)南至泰安段改擴(kuò)建項(xiàng)目起于濟(jì)南市中區(qū)殷家林樞紐互通,向南與濟(jì)南
市長(zhǎng)清區(qū)大學(xué)路交叉并設(shè)置崮山互通立交,經(jīng)長(zhǎng)清區(qū)崮云湖街道后轉(zhuǎn)向東南,經(jīng)鳳凰莊
村、小西莊村、下龍華村、小河西村后路線轉(zhuǎn)向南延伸,經(jīng)饅頭山西側(cè)、吳家莊,在長(zhǎng)
清區(qū)萬(wàn)德街道北側(cè)設(shè)置萬(wàn)德互通立交連接G104,路線轉(zhuǎn)向東南,止于孫家峪中橋橋尾。
起止里程K415+160-K448+482.87,主線全長(zhǎng)33.32km,包括特大橋1059m/1座,大
橋996m/5座、中橋517m/9座、涵洞31道、互通立交3處、服務(wù)區(qū)1處、分離立交2
座、通道22座、天橋2座。
現(xiàn)狀既有高速公路為雙向六車(chē)道,改擴(kuò)建后主線主要采用雙向八車(chē)道、局部十車(chē)道
的高速公路技術(shù)標(biāo)準(zhǔn),設(shè)計(jì)速度120km/h,本標(biāo)段采用“高速公路兩側(cè)拼寬為主、局部
路段中分帶偏移”方式進(jìn)行施工,擴(kuò)建后路基寬度42.0m。
2.2技術(shù)標(biāo)準(zhǔn)
1設(shè)計(jì)時(shí)速:120km/h
2汽車(chē)荷載等級(jí):
2
項(xiàng)目專項(xiàng)施工方案
(1)新建橋涵(含拼接新建部分)滿足公路―Ⅰ級(jí)荷載標(biāo)準(zhǔn);
(2)直接利用的原有橋涵,應(yīng)進(jìn)行檢測(cè)評(píng)估并滿足原設(shè)計(jì)荷載標(biāo)準(zhǔn)要求;
(3)拼接加寬利用的原有橋涵,應(yīng)進(jìn)行檢測(cè)評(píng)估并滿足原設(shè)計(jì)荷載標(biāo)準(zhǔn)要求,且其
極限承載能力應(yīng)滿足或采取加固措施后滿足現(xiàn)行標(biāo)準(zhǔn);正常使用極限狀態(tài)應(yīng)滿足原設(shè)計(jì)
標(biāo)準(zhǔn)的要求。
3設(shè)計(jì)洪水頻率:特大橋:1/300;大、中、小橋、涵洞:1/100。
4橋梁橫斷面:
兩側(cè)拼寬路段的大中橋橋梁橫斷面布置為:0.5m護(hù)欄+19.25m行車(chē)道+0.5m護(hù)欄
+1.0m間距+0.5m護(hù)欄+19.25m行車(chē)道+0.5m護(hù)欄=41.5m,橋梁與路基采用護(hù)欄內(nèi)對(duì)齊
的方式。
圖2.2空心板橫斷面示意
5地震烈度:
根據(jù)相關(guān)標(biāo)準(zhǔn)的規(guī)定,本工程所經(jīng)地區(qū)地震動(dòng)峰值為0.10g,相應(yīng)地震烈度為7°。
6通航凈空:本項(xiàng)目所在區(qū)域河流無(wú)通航要求。
3
項(xiàng)目專項(xiàng)施工方案
2.3特大、大中橋設(shè)置情況
表2.3特大、大中小橋設(shè)置情況
梁板總換板總
梁板長(zhǎng)
序跨徑角度量量
樁號(hào)結(jié)構(gòu)物名稱結(jié)構(gòu)物樁號(hào)度原橋結(jié)構(gòu)形式拼寬/新建結(jié)構(gòu)形式拼寬方式
號(hào)(m)(°)(片)(片)
(m)
1.240.99
1黨齊路中橋K415+399.153*137013預(yù)應(yīng)力空心板預(yù)應(yīng)力砼空心板兩側(cè)拼寬126
明發(fā)路分離預(yù)應(yīng)力砼空心
2K417+650.713*167516預(yù)應(yīng)力砼空心板兩側(cè)拼寬306
立交板
預(yù)應(yīng)力砼空心
3小橋K418+0791*1013510預(yù)應(yīng)力砼空心板拆除新建32
板
C匝道2號(hào)通預(yù)應(yīng)力砼空心
4K415+160-1*1310513預(yù)應(yīng)力砼空心板右側(cè)拼寬2
道K1+244.749板
K420+227
E匝道1號(hào)通預(yù)應(yīng)力砼空心
5殷家林互通1*139013預(yù)應(yīng)力砼空心板新建9
道K0+448.95板
南繞城高速通預(yù)應(yīng)力砼空心
61*108010預(yù)應(yīng)力砼空心板兩側(cè)拼寬3
道K2+630.72板
主線1號(hào)橋預(yù)應(yīng)力砼空心
7崮山互通4*205020預(yù)應(yīng)力砼空心板兩側(cè)拼寬16
K419+065.2板
預(yù)應(yīng)力砼空心
8汽通K422+995.861*1013510預(yù)應(yīng)力砼空心板兩側(cè)拼寬4
板
K420+227-預(yù)應(yīng)力砼空心
9范莊大橋K423+29618*169016預(yù)應(yīng)力砼空心板兩側(cè)拼寬7272
K430+015板
預(yù)應(yīng)力砼空心
10汽通K423+744.421*1010010預(yù)應(yīng)力砼空心板拆除新建32
板
4
項(xiàng)目專項(xiàng)施工方案
梁板總換板總
梁板長(zhǎng)
序跨徑角度量量
樁號(hào)結(jié)構(gòu)物名稱結(jié)構(gòu)物樁號(hào)度原橋結(jié)構(gòu)形式拼寬/新建結(jié)構(gòu)形式拼寬方式
號(hào)(m)(°)(片)(片)
(m)
1.240.99
預(yù)應(yīng)力砼空心
11汽通K425+029.921*1012010預(yù)應(yīng)力砼空心板拆除新建32
板
預(yù)應(yīng)力砼空心
12汽通K426+1701*1012010預(yù)應(yīng)力砼空心板新建32
板
13坡莊大橋K427+230.47015*169016預(yù)應(yīng)力空心板預(yù)應(yīng)力砼空心板兩側(cè)拼寬6064
預(yù)應(yīng)力砼空心
14鳳凰中橋K427+872.4603*134513預(yù)應(yīng)力砼空心板兩側(cè)拼寬1212
板
預(yù)應(yīng)力砼空心
15金家大橋K429+940.4908*165016預(yù)應(yīng)力砼空心板兩側(cè)拼寬32
板
預(yù)應(yīng)力砼空心
16下龍中橋K431+000.5204*1613516預(yù)應(yīng)力砼空心板兩側(cè)拼寬16
板
預(yù)應(yīng)力砼空心
17汽通K432+2501*136513預(yù)應(yīng)力砼空心板拆除新建32
板
預(yù)應(yīng)力砼空心
18韓莊中橋K432+799.2003*169016預(yù)應(yīng)力砼空心板拆除新建96
K430+015-板
K436+000預(yù)應(yīng)力砼空心
19徐毛中橋K433+367.4404*205020預(yù)應(yīng)力砼空心板拆除新建128
板
預(yù)應(yīng)力砼空心
20汽通K433+873.521*135013預(yù)應(yīng)力砼空心板拆除新建32
板
預(yù)應(yīng)力砼空心
21吳莊中橋K437+054.5903*1310513預(yù)應(yīng)力砼空心板兩側(cè)拼寬1212
板
22K436+000-薛莊中橋K437+525.2406*169016預(yù)應(yīng)力砼空心預(yù)應(yīng)力砼空心板兩側(cè)拼寬245
5
項(xiàng)目專項(xiàng)施工方案
梁板總換板總
梁板長(zhǎng)
序跨徑角度量量
樁號(hào)結(jié)構(gòu)物名稱結(jié)構(gòu)物樁號(hào)度原橋結(jié)構(gòu)形式拼寬/新建結(jié)構(gòu)形式拼寬方式
號(hào)(m)(°)(片)(片)
(m)
1.240.99
K451+000板
預(yù)應(yīng)力砼空心
23汽通K438+663.731*137513預(yù)應(yīng)力砼空心板兩側(cè)拼寬4
板
預(yù)應(yīng)力砼空心
24石都中橋K441+651.2404*169016預(yù)應(yīng)力砼空心板兩側(cè)拼寬16
板
A匝道2號(hào)橋預(yù)應(yīng)力砼空心
2511*169016預(yù)應(yīng)力砼空心板兩側(cè)拼寬88
K1+029.83板
C匝道橋101-預(yù)應(yīng)力砼空心
26萬(wàn)德互通2*1616預(yù)應(yīng)力砼空心板新建16
K0+416107板
D匝道橋預(yù)應(yīng)力砼空心
272*1682-7816預(yù)應(yīng)力砼空心板新建16
K0+135.4板
預(yù)應(yīng)力砼空心
28大侯集大橋K444+817.7607*209020預(yù)應(yīng)力砼空心板兩側(cè)拼寬28
板
預(yù)應(yīng)力砼空心
29汽通K444+206.281*139013預(yù)應(yīng)力砼空心板兩側(cè)拼寬4
板
預(yù)應(yīng)力砼空心
30孫家峪中橋K448+482.8703*169516預(yù)應(yīng)力砼空心板兩側(cè)拼寬12
板
6
項(xiàng)目專項(xiàng)施工方案
2.4預(yù)制場(chǎng)建設(shè)
2.4.1區(qū)域劃分
預(yù)制場(chǎng)占地面積12540㎡,主要負(fù)責(zé)預(yù)制10m、13m、16m、20m空心板。
預(yù)制存放區(qū)中間設(shè)置一條寬6米的預(yù)制場(chǎng)內(nèi)道路,采用20cm風(fēng)化料+20cmC20混
凝土
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度BIM在歷史文化遺址保護(hù)合同范本3篇
- 專項(xiàng)2024民用爆破器材供應(yīng)及服務(wù)協(xié)議版
- 個(gè)人工程承包合同(2024版)版B版
- 2024年節(jié)能減排服務(wù)協(xié)議
- 2025年度劇本改編權(quán)授權(quán)合同3篇
- 2024音樂(lè)噴泉景區(qū)旅游紀(jì)念品開(kāi)發(fā)與銷(xiāo)售合同3篇
- 二零二五年度線上線下整合營(yíng)銷(xiāo)方案合作協(xié)議2篇
- 2025年度廠房裝修工程臨時(shí)用電及安全管理合同4篇
- 2025年現(xiàn)代化廠房購(gòu)置及安裝服務(wù)合同范本二3篇
- 2025年度新能源設(shè)備買(mǎi)賣(mài)合同規(guī)范范本4篇
- 2023年遼寧省交通高等??茖W(xué)校高職單招(英語(yǔ))試題庫(kù)含答案解析
- GB/T 33688-2017選煤磁選設(shè)備工藝效果評(píng)定方法
- GB/T 304.3-2002關(guān)節(jié)軸承配合
- 漆畫(huà)漆藝 第三章
- CB/T 615-1995船底吸入格柵
- 光伏逆變器一課件
- 貨物供應(yīng)、運(yùn)輸、包裝說(shuō)明方案
- (完整版)英語(yǔ)高頻詞匯800詞
- 《基礎(chǔ)馬來(lái)語(yǔ)》課程標(biāo)準(zhǔn)(高職)
- IEC61850研討交流之四-服務(wù)影射
- 《兒科學(xué)》新生兒窒息課件
評(píng)論
0/150
提交評(píng)論