綜合房建工程項目
端錨式懸挑架施工方案
(格式最終版)
編制:
審核:
批準:
綜合安置用房工程項目端錨式懸挑架施工方案
目錄
第1章編制依據.........................................................................................1
第2章工程概況.........................................................................................2
2.1工程建設概況一覽表........................................................................2
2.2設計概況............................................................................................3
2.2.1建筑結構概況.................................................................................................3
2.2.2懸挑架設計概況.............................................................................................4
2.2.3腳手架材料選擇.............................................................................................7
2.2.4腳手架計算模型選擇.....................................................................................8
2.3工程施工條件....................................................................................8
第3章施工安排.........................................................................................9
3.1項目管理組織....................................................................................9
3.2項目管理目標....................................................................................9
3.3各項資源供應方式..........................................................................10
3.3.1勞務資源安排一覽表...................................................................................10
3.3.2工程用大宗物資供應安排一覽表...............................................................10
3.3.3施工周轉工具采購供應安排一覽表...........................................................10
3.4施工流水段的劃分及施工工藝流程..............................................10
3.4.1施工流水段的劃分.......................................................................................10
3.4.2施工工藝流程...............................................................................................10
3.5工程施工重點和難點分析及應對措施..........................................11
3.6新技術應用要求..............................................................................12
第4章施工進度計劃...............................................................................13
第5章施工準備與資源配置計劃...........................................................14
5.1施工準備計劃..................................................................................14
5.1.1技術準備.......................................................................................................14
I
綜合安置用房工程項目端錨式懸挑架施工方案
5.1.2現(xiàn)場準備.......................................................................................................15
5.2資源配置計劃..................................................................................16
5.2.1勞動力配置計劃...........................................................................................16
5.2.2工程用成品、半成品需要量計劃...............................................................16
5.2.3生產工藝設備需要量計劃...........................................................................16
5.2.4工程施工主要周轉材料配置計劃...............................................................16
5.2.5施工機具配置計劃.......................................................................................17
5.2.6測量設備配置計劃.......................................................................................17
第6章施工方法及工藝要求...................................................................18
6.1方案及技術參數(shù)..............................................................................18
6.2施工工藝流程..................................................................................20
6.2.1腳手架搭設流程...........................................................................................20
6.2.2腳手架拆除流程...........................................................................................22
6.3懸挑細節(jié)部位..................................................................................23
6.3.1常規(guī)部位.......................................................................................................23
6.3.2飄窗部位.......................................................................................................25
6.3.3典型三排立桿部位.......................................................................................26
6.3.4典型四排立桿部位.......................................................................................27
6.3.5典型陽臺/線條處普通工字鋼設置..............................................................28
6.3.6夾縫處兩側端錨(無拉桿)設置...............................................................28
6.4施工要點..........................................................................................29
6.4.1搭設要求.......................................................................................................29
6.4.2立桿構造要求...............................................................................................29
6.4.3縱向水平桿(大橫桿)構造要求...............................................................30
6.4.4橫向水平桿(小橫桿)搭設.......................................................................30
6.4.5腳手板搭設...................................................................................................30
6.4.6掃地桿搭設...................................................................................................31
6.4.7連墻件搭設...................................................................................................31
6.4.8門洞搭設.......................................................................................................33
6.4.9剪刀撐與橫向斜撐.......................................................................................34
6.4.10斜(過)道設置.........................................................................................34
6.4.11防護設置.....................................................................................................34
II
綜合安置用房工程項目端錨式懸挑架施工方案
6.4.12層間軟硬隔離設置.....................................................................................36
6.4.13施工電梯部位設置.....................................................................................36
6.4.14塔吊附墻部位設置.....................................................................................37
6.5腳手架檢查驗收與交底..................................................................37
6.5.1驗收標準.......................................................................................................37
6.5.2驗收程序.......................................................................................................42
6.5.3驗收內容.......................................................................................................43
6.5.4驗收人員.......................................................................................................43
6.6腳手架安全保障措施......................................................................43
6.6.1腳手架搭設安全技術措施...........................................................................43
6.6.2注意事項.......................................................................................................47
6.6.3腳手架拆除...................................................................................................47
6.6.4日常監(jiān)測.......................................................................................................48
第7章陽臺設備平臺處及邊梁無抗扭筋處加強專項措施..................50
第8章各項管理計劃...............................................................................51
8.1綠色施工管理計劃..........................................................................51
8.2進度管理計劃..................................................................................51
8.3質量管理計劃..................................................................................51
8.3.1工程施工質量分解目標...............................................................................51
8.3.2項目質量管理的組織機構并明確職責.......................................................52
8.3.3確定質量控制點...........................................................................................52
8.3.4現(xiàn)場質量管理制度.......................................................................................53
8.3.5質量保證措施...............................................................................................54
8.4安全及職業(yè)健康管理計劃..............................................................55
8.4.1職業(yè)健康安全管理目標...............................................................................55
8.4.2現(xiàn)場職業(yè)健康安全管理組織機構和職責分工...........................................55
8.4.3職業(yè)健康安全重大危險源...........................................................................57
8.4.4職業(yè)健康安全資源配置計劃.......................................................................57
8.4.5專項施工安全方案編制計劃.......................................................................58
8.4.6施工現(xiàn)場安全生產管理制度.......................................................................58
III
綜合安置用房工程項目端錨式懸挑架施工方案
8.4.7職業(yè)健康安全保證措施...............................................................................58
8.5成品保護計劃..................................................................................59
8.5.1成品保護管理目標.......................................................................................59
8.5.2成品和設備保護的組織機構與職責...........................................................59
8.5.3成品和設備保護的管理制度.......................................................................60
8.5.4成品和設備保護措施...................................................................................60
第9章應急預案.......................................................................................61
9.1應急指揮機構及職責......................................................................61
9.2事故風險分析..................................................................................61
9.3應急救援程序..................................................................................63
9.4應急處置措施..................................................................................63
9.5應急物資準備..................................................................................65
9.6應急響應、響應結束、演練..........................................................65
第10章計算書和相關圖紙.....................................................................68
10.1計算書............................................................................................68
10.1.12250mm懸挑工字鋼(雙排立桿)計算書...............................................68
10.1.22500mm懸挑工字鋼(三排立桿)計算書...............................................68
10.1.33040mm懸挑工字鋼(三排立桿)計算書...............................................68
10.1.43040mm懸挑工字鋼(四排立桿)計算書...............................................68
10.1.53400mm(五立桿)擱置主梁計算書........................................................68
10.1.6大線條處陽臺普通工字鋼(總長4050mm)懸挑計算書......................68
10.1.78#/11#樓北側設備平臺普通工字鋼(總長7000mm,加10#槽鋼斜撐)
懸挑計算書.............................................................................................................68
10.1.8南側飄窗處陽角計算書.............................................................................68
10.2圖紙................................................................................................68
10.2.1FT-11#樓懸挑工字鋼平面布置圖.............................................................68
10.2.2FT-22#樓懸挑工字鋼平面布置圖.............................................................68
10.2.3FT-33#樓懸挑工字鋼平面布置圖.............................................................68
10.2.4FT-44/5/6#樓懸挑工字鋼平面布置圖.......................................................68
IV
綜合安置用房工程項目端錨式懸挑架施工方案
10.2.5FT-57/13#樓懸挑工字鋼平面布置圖........................................................68
10.2.6FT-68#樓懸挑工字鋼平面布置圖.............................................................68
10.2.7FT-711#樓懸挑工字鋼平面布置圖...........................................................68
10.2.8FT-8梁相對標高-1.4部位懸挑架搭設示意圖.........................................68
10.2.9FT-9剖面圖及節(jié)點詳圖(一)................................................................68
10.2.10FT-10剖面圖及節(jié)點詳圖(二)............................................................68
10.2.11FT-11構件詳圖(一)............................................................................68
10.2.12FT-12構件詳圖(二)............................................................................68
10.2.13FT-13端錨主梁及拉桿設置節(jié)點圖........................................................68
10.2.14FT-14螺栓套筒預埋圖............................................................................68
V
綜合安置用房工程項目端錨式懸挑架施工方案
第1章編制依據
表1.1-1編制依據
序號類別文件名稱編號
危險性較大的分部分項工程安全管
1國家行政文件住建部令第37號
理規(guī)定
關于實施《危險性較大的分部分項
建辦質〔2018〕31
2國家行政文件工程安全管理規(guī)定》有關問題的通
號
知
3國家行政文件建設工程安全生產管理條例國務院第393號令
4國家行政文件中華人民共和國安全生產法主席令9屆第70號
建筑施工扣件式鋼管腳手架安全技
5國家行業(yè)規(guī)范JGJ130-2011
術規(guī)范
6國家行業(yè)規(guī)范建筑施工高處作業(yè)安全技術規(guī)范JGJ80-2016
7國家行業(yè)規(guī)范施工現(xiàn)場臨時用電安全技術規(guī)范JGJ46-2005
8國家標準建筑施工腳手架安全技術統(tǒng)一標準GB51210-2016
9國家標準鋼結構設計標準GB50017-2017
10國家標準建筑結構可靠性設計統(tǒng)一標準GB50068-2018
11國家標準建筑結構荷載規(guī)范GB50009-2012
12國家標準建設工程施工現(xiàn)場供用電安全規(guī)范GB50194-2014
13國家標準鋼結構工程施工質量驗收標準GB50205-2020
14國家標準鋼結構工程施工規(guī)范GB50755-2012
15國家標準鋼結構焊接規(guī)范GB50661-2011
16國家行業(yè)規(guī)范建筑施工安全檢查標準JGJ59-2011
建筑施工懸挑式鋼管腳手架安全技
17地方標準DGJ32/J121-2011
術規(guī)程
18地方標準浙江省扣件式建筑腳手架用鋼管DB33/588-2005
19企業(yè)管理文件技術質量管理手冊CSCEC8SH-JS-2018
ZJQ08-SGJB003-
20企業(yè)技術標準腳手架安全技術標準
2017
項目施工合同、施工組織設計、工
21其他/
程施工圖紙、招投標文件
1
綜合安置用房工程項目端錨式懸挑架施工方案
第2章工程概況
2.1工程建設概況一覽表
表2.1-1工程建設概況
工程建設概況
工程名稱xx綜合安置用房工程工程業(yè)態(tài)
14棟16+1、17+1層住宅,2
寧波市奉化區(qū)方橋區(qū)域,
棟1層公變,1棟1層專變,1-
工程規(guī)模工程地址東環(huán)北路以東,恒興東路
2層商業(yè)用房,1棟1層門衛(wèi)以
以北,恒盛路以南
及1層地下室。
總占地面積53916㎡總建筑面積161555.84㎡
結構形式框架剪力墻結構基礎形式樁承臺基礎
屋面形式平屋面外墻形式真石漆外墻
建設單位項目承包范圍施工總承包
主體結構、砌筑、抹灰及
設計單位主要分包工程
其他零星工作
勘察單位質量一次性驗收合格
監(jiān)理單位合同工期714日歷天
總承包單位中國建筑第x工程局有限公司要求安全合格
分包單位科技無
工程主要功
地下一層為車庫及工具間,地上為住宅及底層商業(yè)
能或用途
項目場地位于寧波市奉化區(qū)方橋街道東環(huán)北路與恒興東路交叉口東北側,其
南側約55.50m為恒興東路;西側約42.4m處為機場路高架;北側約17.1m為恒盛
路??傆玫孛娣e為53916m2,總建筑面積1615525.84m2,地上建筑面積
115430.81m2,地下建筑面積46125.03m2
地上為18棟高層住宅,1棟1層專變,1-2層商業(yè)用房,1棟1層門衛(wèi),其中
1#~6#為16+1F,建筑高度為50.8m,7#~14#為17+1F,建筑高度為53.7m;地下室
僅1F,為車庫及工具間等。
2
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.1-1項目效果圖
2.2設計概況
2.2.1建筑結構概況
表2.2-1建筑結構概況
序
項目內容
號
地上鋼筋混凝土框架-剪力墻結構
1結構形式地下室鋼筋混凝土框架-剪力墻結構
基礎樁基礎+筏板基礎
2結構設計使用年限50年
3抗震設防類別重點設防類(乙類)
4結構安全等級二級
5地基基礎設計等級乙級
6建筑抗震設防類別丙類
7地下室防水等級二級
8人防設計等級甲類核6常6級
總建
筑面161555.84㎡
積
地下
室高5.4m(地下室僅1F)
度
包含高層
樓棟1#2#3#4#5#6#7#8#9#10#11#12#13#14#
正負4.94.94.94.94.94.94.94.94.94.94.94.94.94.9
零00000000000000
建筑
1717171717171818181818181818
層數(shù)
建筑
50.50.50.50.50.50.53.53.53.53.53.53.53.53.
高度
88888877777777
(m)
3
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.2-1高層住宅結構示意
2.2.2懸挑架設計概況
本工程施工階段外腳手架采用落地式雙排腳手架+懸挑腳手架的搭設形式,本
方案僅為1-6#、7#、8#、11#、13#樓型鋼懸挑腳手架設計及施工方案。本工程外
腳手架主要是作為主體結構施工階段的操作架兼安全維護和裝修階段施工及其維
護,不得用作支模架或其他超載使用。
1、設計思路
結合本工程結構特點,以及經濟適用,安全可靠應充分考慮以下幾點:
(1)架體的結構設計,力求做到結構要安全可靠,造價經濟合理。
(2)選用材料時,力求做到常見通用、可周轉利用,便于保養(yǎng)維修。
(3)結構選型時,力求做到受力明確,構造措施到位,安拆方便,便于檢查
驗收,鋼管材料進場宜選擇φ48×3.5mm鋼管。
綜合以上幾點,腳手架的搭設,還必須符合JGJ59-2011檢查標準要求,要符
合相關文明標化工地的有關標準。
懸挑架由專業(yè)單位制作,進場的挑架有檢測試驗報告、合格證,詳附件。對
進場材料進行驗收。材料驗收內容包括:工字鋼梁、鋼板厚度、耳板尺寸、焊縫
質量、拉桿、螺桿(螺桿為10.9級高強度等級)。驗收應按節(jié)驗收表進行驗收。
2、設計概況
(1)本工程1#、2#、3#、4#、5#、6#樓為16+1層高層住宅,14層以下搭設
落地式雙排鋼管扣件腳手架,從14層樓板(標高37.9)開始采用懸挑腳手架,搭
設至炮樓頂面(標高55.2),高度17.3m。
4
綜合安置用房工程項目端錨式懸挑架施工方案
(2)本工程7#、8#、11#、13#樓為17+1層高層住宅,15層以下搭設落地式
雙排鋼管扣件腳手架,從15層樓板(標高40.8)開始采用懸挑腳手架,搭設至炮
樓頂面(標高58.1),高度17.3m。
圖2.2-2端錨上拉式懸挑架示意圖
5
綜合安置用房工程項目端錨式懸挑架施工方案
圖2.2-3懸挑架分段立面圖
表2.2-2腳手架分段表
樓棟架體類型結構樓層及標高搭設高度備注
落地20m雙鋼管立
樓(標準落地式鋼管腳手架1~13層頂39.6m
1-6#桿
層高2.9m)
第一次懸挑14~炮樓頂17.4m(局端錨式懸挑架
6
綜合安置用房工程項目端錨式懸挑架施工方案
部18.8m)
落地20m雙鋼管立
7#、8#、落地式鋼管腳手架1~14層頂42.5m
11#、13#樓桿
(標準層高17.4m(局
2.9m)第一次懸挑15~炮樓頂端錨式懸挑架
部18.8m)
2.2.3腳手架材料選擇
l、進場搭設架主材料由專業(yè)廠家加工制作,所有進場搭設材料均應有合格證
和檢驗報告;所有材料必須進場驗收、復驗。
2、腳手架選用架設鋼管外徑48mm,壁厚3.5mm,鋼材強度等級Q235-A,鋼
管表面應平直光滑,不應有裂紋、分層、壓痕、劃道和硬彎,新用的鋼管要有出
廠合格證。腳手架施工前必須將入場鋼管取樣,送有相關國家資質的試驗單位,
進行鋼管抗彎、抗拉等力學試驗,試驗結果滿足設計要求后,方可在施工中使用。
3、本工程鋼管腳手架的搭設使用可鍛鑄造扣件,應符合建設部《鋼管腳手扣
件標準》JGJ130-2011的要求,由有扣件生產許可證的生產廠家提供,不得有裂紋、
氣孔、縮松、砂眼等鍛造缺陷,扣件的規(guī)格應與鋼管相匹配,貼和面應平整,活
動部位靈活,夾緊鋼管時開口處最小距離不小于5mm。鋼管螺栓擰緊力矩達
65N.m時不得破壞。如使用舊扣件時,扣件必須取樣送有相關國家資質的試驗單
位,進行扣件抗滑力等試驗,試驗結果滿足設計要求后方可在施工中使用。
4、腳手板、腳手片采用符合有關要求。
5、安全網采用密目式安全網,網目應滿足2000目/100cm2,做耐貫穿試驗
不穿透,1.6×1.8m的單張網重量在3kg以上,顏色應滿足環(huán)境效果要求,選用綠
色。要求阻燃,使用的安全網必須有產品生產許可證和質量合格證,以及由建筑
安全監(jiān)督管理部門發(fā)放的準用證。
6、連墻件做法:本工程連墻件采用預埋鋼管與外架連接的方法。
7、所有挑梁尾端采用螺栓錨固焊接,挑梁均采用Φ24的拉桿斜拉(計算時按Φ
22計算),斜拉上錨固點為框架梁、剪力墻板。長度大于2.25米處斜拉桿采用雙
拉桿。
用件連接的螺栓應符合現(xiàn)行國家標準《六角頭螺栓》(GB/T5782)的規(guī)定,
其機械性能應符合現(xiàn)行國家標準《緊固件機械性能螺栓、螺釘和螺絲》(GB/T3089)
的規(guī)定。
制作懸挑承力鋼梁等的焊接材料應與主體金屬材料的技術性能相適應。手工
焊接采用的焊條,應符合現(xiàn)行國家標準《碳鋼焊條》(GB/T5117)和《低合金鋼
焊條》(GB/T5118)的規(guī)定,自動焊和半自動焊所采用的焊絲和焊劑,應符合現(xiàn)
行國家標準《埋弧焊用碳鋼焊絲和焊劑》(GB/T5293)和《低合金鋼埋弧焊用焊
劑》(GB/T12470)的規(guī)定。
8、懸挑梁與拉桿采用Φ24銷栓連接(驗算時按Φ22計算)。拉桿與建筑物、
7
綜合安置用房工程項目端錨式懸挑架施工方案
型鋼連接鋼板與建筑物,采用Φ24螺栓連接。
2.2.4腳手架計算模型選擇
結合本工程結構形式、實際施工特點,構筑物四周搭設落地式結合懸挑式、
全封閉的扣件式雙排鋼管腳手架。此架為一架二用,既用于裝修施工,同時兼作
安全防護。
各棟樓號懸挑腳手架平面布置圖均在附圖中詳細畫出,詳見附圖。圖中對不
同樓棟、不同規(guī)則尺寸的工字鋼做了分類,具體詳見附圖工字鋼材料統(tǒng)計表。根
據表中各材料對比,結合預埋位置,選取以下部位及長度工字鋼作為計算代表:
(1)大面積采用1.2m、1.3m、1.5m、1.6m、1.7m、1.8m、1.9m、2.0m、
2.1m、2.25m等長度的工字鋼作為懸挑主梁,其上作用2根立桿,選取最不利情況
2.25m進行計算;
(2)部分區(qū)域采用2m、2.1m、2.2m、2.25m、2.5m、2.7m、3.04m等長度的
工字鋼作為懸挑主梁,其上作用3根立桿,選取最不利情況3.04m進行1次計算,
同時為確定雙拉桿設置界限,選取2.5m進行1次計算;
(注:經計算,2.5m主梁單根拉桿計算可通過,但考慮到保險性,特要求>
2.25m主梁需設置雙拉桿)
(3)部分區(qū)域采用2.9m、3.04m等長度的工字鋼作為懸挑主梁,其上作用4
根立桿,選取最不利情況3.04m進行1次計算;
(4)陽角情況選取1#樓西南側飄窗部位進行1次計算;
(5)部分大線條處設置普通懸挑工字鋼作為主梁、單根工字鋼長度4.05m,
進行1次計算;
(6)8#、11#樓北側設備平臺處梁過于小,高度僅為350,且未設計梁底筋,
不便作為端錨懸挑工字鋼錨固端,因此此處設置普通懸挑工字鋼作為主梁、單根
工字鋼長度7m,進行1次計算;
(7)夾縫處最不利條件為1#樓15-19/J-K軸處,此處兩側端錨(無拉桿)工
字鋼長度為3.4m,其上設置5根立桿,此處進行1次計算。
2.3工程施工條件
1、現(xiàn)場施工道路通暢,材料堆場硬化;
2、懸挑架主梁生產單位按圖紙加固成套架體材料;
3、鋼管、扣件及小型安裝設備齊全;
4、架體搭設人員三級教育并持證上崗;
5、13層頂(1-6#樓)或14層頂(7#、8#、11#、13#樓)邊梁及柱中預埋φ26
金屬套管,套管中心距樓板面或梁面200mm。以便拆模板后,安裝懸挑承力鋼梁;
8
綜合安置用房工程項目端錨式懸挑架施工方案
第3章施工安排
3.1項目管理組織
序號管理職務姓名職稱(資質)職責和權限
項目質量、安全、成本、進度的第一責
1項目經理胡建衛(wèi)工程師
任人
負責型鋼懸挑架施工方案編制,并上報
2項目總工陳琪工程師公司相關部門履行審批手續(xù),審批完成
后對施工人員進行方案交底。
1、全面負責懸挑架質量的過程監(jiān)督工作。
2、組織對項目管理人員的質量教育,提
3質量總監(jiān)楊光才工程師高全員質量意識。
3、參與懸挑架的質量檢查,發(fā)現(xiàn)問題下
達整改通知單,并對整改情況進行驗證。
1、對接地方安全監(jiān)管部門,傳達并督促
工程部落實地方安全監(jiān)管部門對懸挑架
工程的要求。
2、組織懸挑架工程的相關分包隊伍進行
4安全總監(jiān)麻永吉工程師安全交底。
3、對懸挑架搭設的過程安全管控。
4、參與對懸挑架工程的驗收。
5、組織懸挑架安裝與拆除的相關安全工
作。
1、負責對總包方的工程結算管理和現(xiàn)場
簽證管理。
5商務經理楊麗君工程師2、負責對分包方的結算和簽證管理。
3、按合同約定及時收取工程款。
4、組織項目成本分析,提出改進意見。
負責懸挑架工程相關進出場物資的管理。
6物資部經理毛凱永工程師組織對型鋼、鋼管、高強螺栓等材料的
進場檢驗驗收。
3.2項目管理目標
項目管理目標名稱目標值
工期滿足合同
質量目標一次性驗收合格
安全文明目標合格
綠色施工目標合格
科技目標無
9
綜合安置用房工程項目端錨式懸挑架施工方案
3.3各項資源供應方式
3.3.1勞務資源安排一覽表
施工項目資質開始施建設分包分包商選責任
專業(yè)施工隊名稱
名稱要求工時間工期方式擇方式人
奉化安置上海德占建筑工程有限主勞毛凱
/2019.5714d招標
房項目公司務永
奉化安置上海綠驍企業(yè)發(fā)展有限主勞毛凱
/2019.5714d招標
房項目公司務永
3.3.2工程用大宗物資供應安排一覽表
要求進場時
物資名稱采購單位擬選供應商采購地點責任人
間
18#工字鋼承
力梁及配套項目自購/奉化2021.4毛凱永
材料
3.3.3施工周轉工具采購供應安排一覽表
周轉工具名要求進場時計劃出場時
估計數(shù)量提供方式責任人
稱間間
鋼管66500m租賃2021.42021.9毛凱永
直角扣件72072個租賃2021.42021.9毛凱永
對接扣件9145個租賃2021.42021.9毛凱永
旋轉扣件2744個租賃2021.42021.9毛凱永
鋼笆片9750個租賃2021.42021.9毛凱永
3.4施工流水段的劃分及施工工藝流程
3.4.1施工流水段的劃分
表3.4-1腳手架分段表
樓棟架體類型結構樓層及標高搭設高度備注
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網頁內容里面會有圖紙預覽,若沒有圖紙預覽就沒有圖紙。
- 4. 未經權益所有人同意不得將文件中的內容挪作商業(yè)或盈利用途。
- 5. 人人文庫網僅提供信息存儲空間,僅對用戶上傳內容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內容本身不做任何修改或編輯,并不能對任何下載內容負責。
- 6. 下載文件中如有侵權或不適當內容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 專業(yè)人才2024年薪金聘用協(xié)議書版
- 二零二五版冷鏈物流車輛貨物運輸安全協(xié)議2篇
- 二零二五年藝術品搬運運輸服務合同3篇
- 二零二五版數(shù)字經濟產業(yè)發(fā)展合同范本2篇
- 2024施工合同匯集
- 二零二五年度鋼板租賃與節(jié)能減排服務協(xié)議3篇
- 個性化旅游顧問服務協(xié)議2024版版A版
- 2024版產品銷售協(xié)議6篇
- 二零二五年度高科技產業(yè)合伙人分家協(xié)議書3篇
- 二零二五年度智能工廠安全生產服務外包合同2篇
- 《用銳角三角函數(shù)解決問題(3)》參考課件
- 房地產營銷策劃 -佛山龍灣壹號學區(qū)房項目推廣策略提案方案
- 產品共同研發(fā)合作協(xié)議范本5篇
- 風水學的基礎知識培訓
- 2024年6月高考地理真題完全解讀(安徽?。?/a>
- 吸入療法在呼吸康復應用中的中國專家共識2022版
- 1-35kV電纜技術參數(shù)表
- 信息科技課程標準測(2022版)考試題庫及答案
- 施工組織設計方案針對性、完整性
- 2002版干部履歷表(貴州省)
- DL∕T 1909-2018 -48V電力通信直流電源系統(tǒng)技術規(guī)范
評論
0/150
提交評論