學(xué)校新校區(qū)建設(shè)項目工程總承包
基坑支護、降水及土方開挖施工方案
(格式最終版)
編制:
審核:
審批:
2023年6月
目錄
第一章編制依據(jù).........................................................................................................................................1
1.1編制說明.......................................................................................................................................1
1.2編制依據(jù).......................................................................................................................................1
第二章工程概況.........................................................................................................................................2
2.1基本概況.......................................................................................................................................2
2.2設(shè)計概況.......................................................................................................................................2
2.3周圍環(huán)境.......................................................................................................................................3
2.4工程地質(zhì)及水文情況...................................................................................................................4
2.4.1工程地質(zhì)情況...................................................................................................................4
2.4.2工程水文情況...................................................................................................................5
2.4.3基坑設(shè)計參數(shù)...................................................................................................................5
2.5基坑支護、降水、土方開挖概況...............................................................................................6
2.5.1基坑支護概況...................................................................................................................6
2.5.2降水工程概況.................................................................................................................16
2.5.3土方開挖概況.................................................................................................................19
第三章施工安排.......................................................................................................................................20
3.1項目管理組織機構(gòu)及職責.........................................................................................................20
3.1.1項目管理組織機構(gòu).........................................................................................................20
3.1.2崗位及部門職責.............................................................................................................20
3.2項目管理目標.............................................................................................................................22
3.3施工流水段的劃分及施工工藝流程.........................................................................................22
3.3.1施工總體思路.................................................................................................................22
3.3.2施工工藝流程.................................................................................................................22
3.3.3鋼板樁施工區(qū)段劃分及施工組織.................................................................................30
3.3.4降水工程施工區(qū)段劃分及施工組織.............................................................................30
3.3.5土方開挖施工區(qū)段劃分及施工組織.............................................................................31
3.4施工總平面布置.........................................................................................................................32
3.4.1總平面布置.....................................................................................................................32
3.4.2平面管理.........................................................................................................................33
3.5施工重點和難點分析及應(yīng)對措施.............................................................................................34
3.6新技術(shù)應(yīng)用要求.........................................................................................................................35
第四章施工計劃.......................................................................................................................................37
4.1施工進度計劃.............................................................................................................................37
4.2施工準備計劃.............................................................................................................................38
4.2.1技術(shù)準備.........................................................................................................................38
4.3資源配置計劃.............................................................................................................................38
4.3.1機械設(shè)備配置計劃.........................................................................................................38
4.3.2檢測設(shè)備配置計劃.........................................................................................................39
4.4勞動力投入計劃.........................................................................................................................40
4.4.1項目管理人員.................................................................................................................40
4.4.2現(xiàn)場施工人員.................................................................................................................40
4.5材料投入計劃.............................................................................................................................41
第五章施工工藝技術(shù)...............................................................................................................................42
5.1主要施工方案選擇.....................................................................................................................42
5.2拉森鋼板樁施工方案.................................................................................................................42
5.2.1鋼板樁施工流程.............................................................................................................42
5.2.2鋼板樁施工要點.............................................................................................................42
5.3鋼支撐施工方案.........................................................................................................................43
5.3.1鋼支撐施工流程...............................................................................................................43
5.3.2鋼支撐施工要點.............................................................................................................43
5.4管井降水施工方案.....................................................................................................................45
5.4.1施工流程.........................................................................................................................46
5.4.2施工準備.........................................................................................................................46
5.4.3管井施工.........................................................................................................................47
5.4.4質(zhì)量標準.........................................................................................................................48
5.4.5施工注意事項.................................................................................................................48
5.4.6封井方案.........................................................................................................................48
5.5土方開挖方案.............................................................................................................................49
5.5.1土方開挖施工總體部署.................................................................................................49
5.5.2土方開挖施工要點.........................................................................................................50
5.5.3出土口坡道加固措施.....................................................................................................51
5.6護坡噴錨方案.............................................................................................................................51
5.6.1施工流程.........................................................................................................................51
5.6.2施工方法.........................................................................................................................51
5.6.3技術(shù)措施.........................................................................................................................52
第六章安全保證措施...............................................................................................................................53
6.1組織保障措施.............................................................................................................................53
6.1.1安全保證體系.................................................................................................................53
6.1.2崗位及部門職責.............................................................................................................53
6.2安全技術(shù)措施.............................................................................................................................55
6.2.1安全教育及培訓(xùn).............................................................................................................55
6.2.2安全防護管理措施.........................................................................................................56
6.2.3機械設(shè)備的安全使用措施.............................................................................................58
6.2.4基坑土方開挖季節(jié)性施工措施.....................................................................................61
6.3監(jiān)測監(jiān)控措施.............................................................................................................................62
6.3.1基坑監(jiān)測.........................................................................................................................62
6.3.2基坑巡查內(nèi)容.................................................................................................................64
6.3.4對監(jiān)測結(jié)果的要求.........................................................................................................66
6.3.5注意事項.........................................................................................................................66
6.4職業(yè)健康安全重大危險源.........................................................................................................66
6.5深基坑驗收.................................................................................................................................67
6.5.1驗收依據(jù).........................................................................................................................67
6.5.2土方開挖條件的驗收(第一次驗收).........................................................................68
6.5.3土方開挖中間驗收(第二次驗收).............................................................................68
6.5.4竣工驗收(第三次驗收).............................................................................................69
第七章各項管理計劃...............................................................................................................................70
7.1進度管理計劃.............................................................................................................................70
7.1.1確定施工進度控制點.....................................................................................................70
7.1.2工期管理措施.................................................................................................................70
7.2質(zhì)量管理計劃.............................................................................................................................72
7.2.1質(zhì)量目標.........................................................................................................................72
7.2.2質(zhì)量保證體系.................................................................................................................73
7.2.3質(zhì)量保證措施.................................................................................................................73
7.3環(huán)境管理計劃.............................................................................................................................73
7.3.1環(huán)境管理目標.................................................................................................................73
7.3.2辨識重大環(huán)境因素.........................................................................................................74
7.3.3環(huán)境保護資源配置計劃.................................................................................................74
7.3.4施工環(huán)境保證措施.........................................................................................................74
第八章應(yīng)急救援預(yù)案...............................................................................................................................77
8.1應(yīng)急救援組織機構(gòu).....................................................................................................................77
8.1.1應(yīng)急預(yù)案的組織體系.....................................................................................................77
8.1.2應(yīng)急領(lǐng)導(dǎo)小組成員及聯(lián)系方式.....................................................................................77
8.1.3崗位及部門職責.............................................................................................................78
8.2應(yīng)急救援物資.............................................................................................................................79
8.3應(yīng)急救援路線.............................................................................................................................80
8.4土方支護工程應(yīng)急救援預(yù)案.....................................................................................................81
8.5破壞管線應(yīng)急響應(yīng)預(yù)案.............................................................................................................82
8.6生產(chǎn)安全事故應(yīng)急救援預(yù)案.....................................................................................................83
8.7雨季排水應(yīng)急預(yù)案.....................................................................................................................86
第九章計算書及附表...............................................................................................................................88
9.1土方開挖生產(chǎn)能力分析.............................................................................................................88
9.1.1機械生產(chǎn)能力.................................................................................................................88
9.1.2正常工作日有效工作時間.............................................................................................89
9.1.3設(shè)備投入量計算...............................................................................................................89
9.2管井降水計算書...........................................................................................................................91
一、水文地質(zhì)資料.......................................................................................................................91
二、計算過程...............................................................................................................................91
9.3深基坑工程安全檢查表.............................................................................................................93
9.4深基坑驗收記錄表.....................................................................................................................95
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
第一章編制依據(jù)
1.1編制說明
本施工方案根據(jù)本工程特點、地質(zhì)情況及周邊環(huán)境,參照國家規(guī)范、規(guī)程、技術(shù)標
準,結(jié)合我單位在鹽城施工同類的基坑土方、支護工程的實踐經(jīng)驗,采取近年較為成熟
的支護、降水等施工工藝編制而成。
1.2編制依據(jù)
本施工方案編制依據(jù)見表1.2-1。
表1.2-1編制依據(jù)
序號文件名稱編號類別
1《工程測量規(guī)范》GB50026-2007
2《建筑變形測量規(guī)范》JGJ8-2016
3《建筑地基基礎(chǔ)設(shè)計規(guī)范》GB50007-2011
4《建筑基坑支護技術(shù)規(guī)程》JGJ120-2012
5《建筑基坑工程監(jiān)測技術(shù)標準》GB50497-2019
6《建筑地基處理技術(shù)規(guī)范》JGJ79-2012
7《建筑地基工程施工質(zhì)量驗收規(guī)范》GB50202-2018
8《建筑施工安全檢查標準》JGJ59-2011
國家規(guī)范
9《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
10《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》JGJ46-2005
11《鋼結(jié)構(gòu)工程施工質(zhì)量驗收標準》GB50205-2020
12《建筑工程施工質(zhì)量驗收統(tǒng)一標準》GB50300-2013
13《混凝土結(jié)構(gòu)工程施工質(zhì)量驗收規(guī)范》GB50204-2015
14《鋼筋機械連接技術(shù)規(guī)程》JGJ107-2016
《江蘇省建筑安裝工程施工技術(shù)操作規(guī)程(地基
15DGJ32/J28-2006
與基礎(chǔ)工程)》
16《建筑基坑支護結(jié)構(gòu)構(gòu)造》11SG814圖集
17本工程基坑支護設(shè)計圖紙/
圖紙和設(shè)
18本工程巖土工程勘察報告/
計文件
19本工程設(shè)計圖紙/
20危險性較大的分部分項工程安全管理規(guī)定建設(shè)部37號令
其他
21危險性較大的分部分項工程安全管理規(guī)定建辦質(zhì)【2018】31號
1
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
第二章工程概況
2.1基本概況
xx學(xué)校新校區(qū)建設(shè)項目工程總承包位于鹽城經(jīng)濟技術(shù)開發(fā)區(qū),擬建圖書綜合樓、教
學(xué)實訓(xùn)樓、學(xué)生宿舍、學(xué)生食堂、活動中心、體育館、體育場附屬設(shè)施、地下室及其周
邊外場工程。總用地面積約35.53萬㎡,一期總建筑面積約19.50萬㎡,其中,一期地
上建筑面積約17.50萬㎡,地下建筑面積約2.00萬㎡。
本工程基坑安全等級二級,環(huán)境保護等級三級。
本工程場地平均標高為絕對標高+2.20m。
本工程維護周邊地面超載(含施工荷載)不超過15kPa。
本工程各參建單位見表2.1-1。
表2.1-1本工程參建單位信息一覽表
序號項目單位名稱
1建設(shè)單位xx學(xué)校
2監(jiān)理單位
3設(shè)計單位
4勘察單位
5施工單位中建x局第三建設(shè)有限公司
2.2設(shè)計概況
本工程建筑設(shè)計概況見表2.2-1。
表2.2-1建筑設(shè)計概況
序
內(nèi)容
號
建筑面積建筑高度建筑層數(shù)
1單體名稱備注
(㎡)(m)(F)
2圖書綜合樓35019.162.112
3教學(xué)實訓(xùn)樓70269.6最高22.12-5含4棟教學(xué)樓單體
4學(xué)生宿舍47298.621.96含4棟宿舍樓
5學(xué)生食堂12140.415.63
6活動中心4004.99.92
7體育館5105.515.71
8門衛(wèi)、看臺、后勤1160.831
2
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
9地下室19998.83.8-1含人防
2.3周圍環(huán)境
本工程基坑均在場內(nèi),無外部建筑物及市政道路的影響?;拥拈_挖僅需考慮場內(nèi)
新建建筑物及場內(nèi)道路的影響。各基坑周圍環(huán)境情況見下表所示。
表2.3-1基坑周圍環(huán)境情況一覽表
宿舍樓地下室
序號方位內(nèi)容
基坑?xùn)|側(cè)為擬建永臨結(jié)合道路,基坑自然放坡開挖邊線與道路距離約11m,
1基坑?xùn)|側(cè)
能滿足自然放坡開挖條件。
基坑南側(cè)為擬建臨時道路,基坑自然放坡開挖邊線與臨時道路距離約19m,
2基坑南側(cè)
能滿足自然放坡開挖條件。
基坑西側(cè)為1#宿舍樓西側(cè)區(qū)域工程樁,需要考慮基坑開挖對無地下室區(qū)域工
3基坑西側(cè)
程樁的影響。
基坑南側(cè)為擬建臨時道路及2#宿舍樓,基坑自然放坡開挖邊線與臨時道路距
4基坑北側(cè)
離約7m,開挖降水需考慮對正在主體施工階段2#宿舍樓的影響。
圖書綜合樓地下室
序號方位內(nèi)容
基坑?xùn)|側(cè)為擬建臨時道路,基坑自然放坡開挖邊線與道路距離約5.5m,能滿
1基坑?xùn)|側(cè)
足自然放坡開挖條件。
基坑南側(cè)為擬建臨時道路,基坑自然放坡開挖邊線與臨時道路距離約11m,
2基坑南側(cè)
能滿足自然放坡開挖條件。
3基坑西側(cè)基坑西側(cè)為空曠場地,無影響。
基坑南側(cè)為擬建永臨結(jié)合道,基坑自然放坡開挖邊線與臨時道路距離約8m,
4基坑北側(cè)
開挖降水需考慮對道路影響。
教學(xué)組團地下室
序號方位內(nèi)容
基坑?xùn)|側(cè)為擬建教學(xué)樓,基坑在教學(xué)樓范圍內(nèi),基坑開挖降水需考慮對教學(xué)
1基坑?xùn)|側(cè)
樓工程樁的影響。
基坑南側(cè)為擬建永臨結(jié)合道路,基坑距離路邊約3m,開挖降水需考慮對道路
2基坑南側(cè)
的影響。
基坑西側(cè)為擬建教學(xué)樓,基坑在教學(xué)樓范圍內(nèi),基坑開挖降水需考慮對教學(xué)
3基坑西側(cè)
樓工程樁的影響。
4基坑北側(cè)基坑北側(cè)為擬建教學(xué)樓,基坑在教學(xué)樓范圍內(nèi),基坑開挖降水需考慮對教學(xué)
3
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
教學(xué)組團地下室
序號方位內(nèi)容
樓工程樁的影響。
2.4工程地質(zhì)及水文情況
2.4.1工程地質(zhì)情況
基坑開挖范圍內(nèi)主要涉及的土層有①-1層素填土、②-2層黏質(zhì)黏土、③-3層淤泥
質(zhì)粉質(zhì)黏土、④-4層砂質(zhì)粉土、⑤-砂質(zhì)粉土、⑥-黏質(zhì)粉土,基底基本落在②-2層黏
質(zhì)粉土,其中①素填土和②-2層淤泥質(zhì)粉質(zhì)黏土較厚,第2層黏質(zhì)粉土強度中等,壓
縮性中等,埋深適中,層位穩(wěn)定;第3層淤泥質(zhì)粉質(zhì)黏土含水率高,高壓縮性,重度
小,抗剪強度及承載力低,該層土分布較均勻,場地普遍分布,為擬建場地不良地質(zhì)層。
根據(jù)《巖土工程勘察規(guī)范》(DGJ32/TJ208-2016),按地基土的成因、時代類型及
物理力學(xué)性質(zhì)差異性,將勘探深度范圍內(nèi)土層劃分為13個工程地質(zhì)層,各層工程地質(zhì)
特征分述見表。
表2.4.1-1工程巖土情況一覽表
序號土層名稱工程特性
主要成份為黏質(zhì)粉土,夾大量植物根莖,松散,土質(zhì)不均勻。場區(qū)普遍分布,
厚度:0.20~1.00m,平均0.65m;層底標高:1.38~1.88m,平均1.63m;層底埋
1素填土
深:0.20~1.00m,平均0.65m。
夾少量軟塑狀黏性土薄層單層厚0.3~1.0cm),見少量鐵錳氧化物斑
點,土質(zhì)欠均勻。場區(qū)普遍分布,厚度:0.80~1.00m,平均1.00m;層底標
2黏質(zhì)粉土
高:0.39~0.88m,平均0.63m;層底埋深:1.00~2.00m,平均1.65m。
不均勻地夾少量粉土團塊或薄層(單層厚約0.3~10.0cm),具微層理,切面稍
有光澤,無搖震反應(yīng),干強度及韌性中等,土質(zhì)欠均勻。場區(qū)普遍分布,厚
淤泥質(zhì)粉
3度:1.30~10.60m,平均4.38m;層底標高:-9.96~-0.71m,平均-3.75m;層底
質(zhì)黏土
埋深:3.00~12.20m,平均6.02m。
見少量云母碎屑,及大量淤泥質(zhì)粘性土薄層(單層厚5~10mm),搖震反應(yīng)
迅速,無光澤反應(yīng),干強度及韌性低,土質(zhì)欠均勻。局部區(qū)域該層土缺失,厚
4砂質(zhì)粉土度:0.00~9.00m,平均5.96m;層底標高:-11.26~-6.91m,平均-7.92m;層底
埋深:9.10~13.40m,平均10.20m。
見少量云母碎屑,夾少量粉砂團塊及少量淤泥質(zhì)粘性土薄層(單層厚3~
8mm),搖震反應(yīng)迅速,無光澤反應(yīng),干強度及韌性低,土質(zhì)欠均勻。場區(qū)普
5砂質(zhì)粉土遍分布,厚度:2.90~15.20m,平均7.86m;層底標高:-23.02~-13.14m,平
均-15.69m;層底埋深:15.40~25.50m,平均17.96m。
4
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
序號土層名稱工程特性
見大量黏性土薄層,單層厚約2~10mm,層理清晰,搖震反應(yīng)中等,無光澤反
應(yīng),干強度及韌性低,土質(zhì)不均勻。局部區(qū)域該層土缺失,厚度:0.00~
6黏質(zhì)粘土5.00m,平均2.98m;層底標高:-24.57~-15.38m,平均-18.45m;層底埋
深:17.70~27.00m,平均20.72m。
見較多云母碎屑及少量淤泥質(zhì)粘性土薄層(單層厚4~10mm),平均黏粒含
量為6.2,土質(zhì)欠均勻。局部區(qū)域該層土缺失,厚度:0.00~9.10m,平均
7粉砂6.48m;層底標高:-24.67~-23.88m,平均-24.35m;層底埋深:26.00~27.10m,
平均26.63m。
偶見少量鐵錳質(zhì)氧化物斑點及鈣質(zhì)結(jié)核,無搖震反應(yīng),切面光滑,干強度及韌
性高,土質(zhì)較均勻。場區(qū)普遍分布,厚度:10.00~11.60m,平均10.44m;層底
8黏土標高:-35.94~-34.42m,平均-34.80m;層底埋深:36.50~38.30m,平均
37.07m。
偶見少量鐵錳質(zhì)氧化物斑點,無搖震反應(yīng),切面稍有光滑,干強度及韌性中等,
土質(zhì)較均勻。場區(qū)普遍分布,厚度:3.10~4.70m,平均4.17m;層底標高:-
9粉質(zhì)黏土
39.74~-38.12m,平均-39.01m;層底埋深:40.40~42.10m,平均41.26m。
2.4.2工程水文情況
本工程場地地下水類型主要為孔隙潛水、微承壓水。地下水位隨季節(jié)、氣候變化而
上下浮動。本工程水文情況見表。
表2.4.2-1本工程水文條件
序號類型分布情況
孔隙潛水初見水位標高為0.73~0.81m,穩(wěn)定水位標高為0.84m~
0.90m。擬建場地近3~5年內(nèi)孔隙潛水最高地下水位標高為1.88m,歷史最
1孔隙潛水
高地下水位標高為1.90m,歷史最低地下水位標高為0.55m,年變化幅度為
1.30m,季節(jié)性變化幅度為1.00m。
擬建場區(qū)內(nèi)1#、2#、3#承壓水水位觀測孔測得的第10~12層土,平
2承壓水
均標高0.42m。
2.4.3基坑設(shè)計參數(shù)
根據(jù)本工程地勘報告,基坑支護設(shè)計所需巖土參數(shù)可參考見下表:
5
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
注:①、表中參數(shù)系根據(jù)室內(nèi)試驗結(jié)果并結(jié)合地區(qū)經(jīng)驗綜合取值,()中數(shù)據(jù)為工程
經(jīng)驗值,第3層土為正常固結(jié)土,第7層為有效強度指標;滲透系數(shù)取大值。
②、采用表中數(shù)值時應(yīng)考慮基坑開挖后邊界條件和地下水條件改變的影響,并結(jié)合
支護結(jié)構(gòu)型式計算模型、地下水控制方式等因素作合理調(diào)整。
2.5基坑支護、降水、土方開挖概況
2.5.1基坑支護概況
本工程基坑支護結(jié)構(gòu)安全等級為二級?;又ёo形式為:1#宿舍樓基坑西側(cè)采用鋼
板樁+自然放坡,其余采用二級放坡;圖書綜合樓北側(cè)采用鋼板樁+自然放坡,其余采用
二級放坡;教學(xué)樓組團基坑南側(cè)局部采用鋼板樁+鋼支撐,其余采用二級放坡。
2.5.1.1基坑支護各設(shè)計概況
各~3。
6
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-11#宿舍樓基坑支護布置圖
7
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-2圖書綜合樓基坑支護布置圖
8
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-3教學(xué)樓組團基坑支護布置圖
2.5.1.2基坑支護結(jié)構(gòu)剖面圖
1)基坑支護剖面結(jié)構(gòu)圖見圖2.5.1-4~15所示。
9
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-4地質(zhì)剖面圖
10
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-51-1剖面段支護結(jié)構(gòu)圖
圖2.5.1-61a-1a剖面段支護結(jié)構(gòu)圖
11
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-71b-1b剖面段支護結(jié)構(gòu)圖
圖2.5.1-82-2剖面段支護結(jié)構(gòu)圖
12
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-92a-2a剖面段支護結(jié)構(gòu)圖
圖2.5.1-103-3剖面段支護結(jié)構(gòu)圖
13
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-113a-3a剖面段支護結(jié)構(gòu)圖
圖2.5.1-124-4剖面段支護結(jié)構(gòu)圖
14
xx學(xué)校新校區(qū)建設(shè)項目工程總承包基坑支護、降水及土方開挖施工方案
圖2.5.1-134a-4a剖面段支護結(jié)構(gòu)圖
圖2.5.1-145-5剖面段支護結(jié)構(gòu)圖
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責。
- 6. 下載文件中如有侵權(quán)或不適當內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025土地承包合同終止范例
- 2025知識產(chǎn)權(quán)委托代理合同
- 2025地下車庫買賣合同書
- 2025貨樣買賣合同范本
- 二零二五年度文化產(chǎn)業(yè)公司股權(quán)受讓協(xié)議書范例3篇
- 二零二五年度特色農(nóng)產(chǎn)品種植基地土地永久轉(zhuǎn)讓協(xié)議
- 2025年度農(nóng)機購置與農(nóng)業(yè)人才培訓(xùn)合同3篇
- 二零二五年度物聯(lián)網(wǎng)技術(shù)合伙協(xié)議3篇
- 2025年度綜合交通樞紐停車場租賃與交通換乘服務(wù)合同3篇
- 2025年度高端裝備制造企業(yè)整體轉(zhuǎn)讓協(xié)議版3篇
- ODM合作方案教學(xué)課件
- 醫(yī)藥公司知識產(chǎn)權(quán)
- GB/T 1196-2023重熔用鋁錠
- Revit軟件學(xué)習(xí)實習(xí)報告
- 2024版國開電大本科《行政領(lǐng)導(dǎo)學(xué)》在線形考(形考任務(wù)一至四)試題及答案
- 風(fēng)電教育培訓(xùn)體系建設(shè)
- 《機械基礎(chǔ)(第七版)》期末考試復(fù)習(xí)題庫(含答案)
- 長龍山抽水蓄能電站500kv開關(guān)站工程環(huán)境影響報告書
- 2023年中考語文一輪復(fù)習(xí):童話示例與訓(xùn)練
- 自助畫室創(chuàng)業(yè)計劃書
- 生產(chǎn)車間薪酬管理制度
評論
0/150
提交評論