文檔簡介

1編制依據(jù)..............................................................................4

1.1編制說明.......................................................................4

1.2編制依據(jù).......................................................................4

1.3編制原則......................................................................5

2工程概況..............................................................................5

2.1工程簡介......................................................................5

2.2水文地質(zhì)概況.................................................................14

2.2.1工程地質(zhì)概況...........................................................14

2.2.2水文地質(zhì)概況...........................................................16

2.3風(fēng)險(xiǎn)工程情況................................................................16

3施工部署.............................................................................18

3.1工程難特點(diǎn)及針對性措施.......................................................18

3.1.1區(qū)間穿越深厚雜填土區(qū)...................................................18

3.1.2區(qū)間結(jié)構(gòu)下穿或臨近管線或建構(gòu)筑物.......................................19

3.1.3區(qū)間隧道馬頭門破除.....................................................20

3.2施工總體目標(biāo).................................................................21

3.3施工部署及進(jìn)度計(jì)劃...........................................................22

3.4施工現(xiàn)場平面布置.............................................................24

3.5資源投入計(jì)劃.................................................................25

3.5.1機(jī)械設(shè)備投入計(jì)劃.......................................................25

3.5.2測量人員及儀器投入計(jì)劃................................................26

3.5.3勞動力投入計(jì)劃.........................................................27

4施工方法及工藝要求..................................................................28

4.1區(qū)間暗挖總體施工方案.........................................................28

4.2降、排水施工方案.............................................................30

4.3區(qū)間供電、供水、通風(fēng)、通訊方案..............................................30

4.3.1供電和照明...............................................................30

4.3.2通風(fēng).....................................................................30

4.3.3供水.....................................................................32

4.3.4施工通訊................................................................32

4.4測量方案......................................................................32

4.4.1控制測量依據(jù)及主要儀器..................................................32

4.4.2測量程序................................................................33

4.4.3隧道施工測量.............................................................35

4.4.4隧道貫通誤差測量........................................................35

4.4.5成果的檢查與檢測........................................................36

4.5馬頭門施工方案............................................................36

4.5.1自橫通道進(jìn)區(qū)間馬頭門施工方案...........................................36

4.5.2自明挖結(jié)構(gòu)進(jìn)區(qū)間馬頭門施工方案.........................................41

4.6區(qū)間隧道施工方案..............................................................43

4.6.1施工原則...............................................................43

4.6.2區(qū)間隧道施工工藝.......................................................43

4.6.2.1臺階法區(qū)間隧道施工工藝............................................43

4.6.2.2CD法區(qū)間隧道施工工藝.............................................45

4.6.3區(qū)間隧道初期支護(hù)施工方案................................................47

4.6.3.1超前小導(dǎo)管注漿加固地層...........................................47

4.63.2土方開挖施工......................................................49

463.3格柵鋼架加工、安裝及鎖腳錨桿的施工...............................51

4.63.4噴射混凝土施工....................................................55

4.63.5掌子面封閉........................................................57

4.63.6初襯背后注漿施工..................................................58

463.7區(qū)間隧道開挖出硝...................................................58

5施工監(jiān)測方案........................................................................61

5.1監(jiān)測目的及意義................................................................61

5.2監(jiān)測對象及項(xiàng)目................................................................61

5.3監(jiān)測點(diǎn)的布設(shè)方法與保護(hù)要求....................................................62

5.3.1測點(diǎn)布置要求、精度要求..................................................62

5.3.2監(jiān)測點(diǎn)的保護(hù)措施.........................................................62

5.4主要監(jiān)測項(xiàng)目實(shí)施方法..........................................................63

5.4.1地層、洞內(nèi)外及支護(hù)情況觀察..............................................63

5.4.2沉降監(jiān)測................................................................63

5.4.3拱頂沉降觀測.............................................................64

5.4.4水平收斂觀測.............................................................64

5.5監(jiān)測控制標(biāo)準(zhǔn)、監(jiān)測頻率與預(yù)警等級管理..........................................65

5.6監(jiān)測應(yīng)急預(yù)案...................................................................66

5.7監(jiān)測信息采集、分析和處理要求及反饋............................................67

5.7.1監(jiān)測流程................................................................67

5.7.2監(jiān)測數(shù)據(jù)的采集、整理....................................................67

5.7.3數(shù)據(jù)的處理與報(bào)送........................................................68

5.7.4成果反饋體系.............................................................70

5.8監(jiān)測儀器設(shè)備、元器件及人員的配備..............................................71

5.8.1組織機(jī)構(gòu)................................................................71

5.8.2投入人員................................................................72

5.8.3投入監(jiān)測儀器.............................................................73

5.9質(zhì)量管理、安全管理及其他管理制度.............................................73

5.9.1技術(shù)準(zhǔn)備...............................................................73

5.9.2設(shè)備及物質(zhì)控制.........................................................73

5.9.3監(jiān)測質(zhì)量控制措施.......................................................74

6主要施工管理保證措施................................................................78

6.1工程質(zhì)量保證措施..............................................................78

6.1.1質(zhì)量目標(biāo)................................................................78

6.1.2質(zhì)量保證體系............................................................78

6.1.3質(zhì)量管理機(jī)構(gòu)及職責(zé)......................................................79

6.1.3.1質(zhì)量管理機(jī)構(gòu)......................................................79

6.1.3.2質(zhì)量職責(zé)..........................................................80

6.1.4施工過程質(zhì)量控制........................................................82

6.1.5質(zhì)量控制點(diǎn)保證措施......................................................84

6.1.5.1組織措施.........................................................84

6.1.5.2思想教育措施.....................................................84

6.1.5.3技術(shù)管理措施.....................................................84

6.1.5.4施工措施.........................................................85

6.1.5.5關(guān)鍵工序質(zhì)量保證措施.............................................86

6.1.6確保質(zhì)量的檢測、試驗(yàn)手段和措施...........................................89

6.1.6.1檢測、試驗(yàn)組織機(jī)構(gòu)................................................89

6.1.6.2檢測人員職責(zé)......................................................89

6.1.6.3試驗(yàn)和檢測設(shè)備控制................................................89

6.1.6.4檢驗(yàn)、試驗(yàn)........................................................90

6.2工程安全保證措施...............................................................91

6.2.1安全生產(chǎn)總目標(biāo)及保證體系................................................91

621.1安全生產(chǎn)總目標(biāo).....................................................91

6.2.1.2安全生產(chǎn)管理體系...................................................91

6.2.1.4安全組織機(jī)構(gòu).......................................................92

6.2.1.5建立健全安全生產(chǎn)責(zé)任制.............................................95

6.2.2風(fēng)險(xiǎn)評估................................................................95

6.2.3安全保證措施............................................................96

6.2.3.1施工現(xiàn)場安全技術(shù)措施..............................................96

6.232暗挖施工開挖、初支安全技術(shù)措施....................................96

6.23.3用電安全技術(shù)措施..................................................97

6.23.4施工機(jī)械的安全控制措施............................................98

6.23.5起吊作業(yè)安全措施..................................................99

6.23.6交通安全保證措施..................................................99

6.2.4事故應(yīng)急預(yù)案.............................................................99

6.2.4.1應(yīng)急預(yù)案流程圖....................................................99

6.2.4.2突發(fā)事件應(yīng)急準(zhǔn)備..................................................99

6.2.43搶險(xiǎn)物質(zhì)儲備.....................................................101

6.2.4,4主要應(yīng)急方案及處理措施...........................................101

6.2.4.5恢復(fù)生產(chǎn)及應(yīng)急搶險(xiǎn)總結(jié)...........................................105

6.3工程進(jìn)度保證措施............................................................106

6.3.1外部協(xié)作單位組織措施...................................................106

6.3.2配備充足的施工資源.....................................................107

6.3.3強(qiáng)化過程控制,實(shí)行工期動態(tài)管理........................................107

6.3.4制定相應(yīng)的成品保護(hù)措施,避免維修或返工浪費(fèi)時(shí)間........................108

6.3.5季節(jié)性及節(jié)假日施工保證措施.............................................108

6.3.5.1夏季施工保證措施.................................................108

6.352冬季施工保證措施.................................................109

63.5.3節(jié)假日施工保證措施...............................................118

63.5.4夜間施工措施.....................................................118

6.4文明施工、環(huán)境保護(hù)措施.......................................................119

6.4.1文明施工保證體系.......................................................119

6.4.L1文明施工保證體系................................................119

6.4.1.2施工管理人員的管理..............................................119

6.4.1.3場容場貌標(biāo)準(zhǔn)化..................................................120

6.4.1.4臨時(shí)道路的管理..................................................120

6.4.1.5材料堆放管理....................................................120

6.4.1.6設(shè)備管理........................................................121

6.4.2環(huán)境保護(hù)保證體系........................................................121

6.4.2.1環(huán)境保護(hù)保證體系.................................................121

6.4.2.2工地衛(wèi)生.........................................................121

6.423周圍環(huán)境協(xié)調(diào).....................................................122

642.4控制揚(yáng)塵、水污染、噪聲等污染措施..................................124

1編制依據(jù)

1.1編制說明

本方案適用于烏魯木齊市軌道交通1號線工程三工站一宣仁墩站區(qū)間正線隧道暗

挖初支施工,不包含二襯結(jié)構(gòu)施工。二襯施工前,將單獨(dú)編制二襯施工專項(xiàng)方案。

1.2編制依據(jù)

1、設(shè)計(jì)、勘查文件

(1)中鐵第一勘察設(shè)計(jì)院集團(tuán)有限公司提供的《烏魯木齊軌道交通一號線(三屯碑?

國際機(jī)場)工程三工站?宣仁墩站區(qū)間巖土工程詳細(xì)勘察報(bào)告》(詳細(xì)勘察階段2014

年1月);

(2)新疆維吾爾自治區(qū)建筑設(shè)計(jì)研究院提供《烏魯木齊軌道交通1號線環(huán)境調(diào)查

02標(biāo)段調(diào)查結(jié)果》;

(3)北京城建設(shè)計(jì)發(fā)展集團(tuán)股份有限公司提供《烏魯木齊軌道交通1號線工程施工

圖設(shè)計(jì)三工站?宣仁墩站區(qū)間百園路車輛基地出入線(第十九冊第二分冊第一部分區(qū)間

隧道)》;

(4)相關(guān)的技術(shù)聯(lián)系單、會議紀(jì)要、設(shè)計(jì)交底及圖紙會審;

2、現(xiàn)行國家及行業(yè)相關(guān)規(guī)范規(guī)程,見表1-1所示。

表1-1主要標(biāo)準(zhǔn)、規(guī)范及規(guī)程

序號內(nèi)容備注

1《地下鐵道、輕軌交通巖土工程勘察規(guī)范》GB50307-1999

2《地下鐵道、輕軌交通工程測量規(guī)范》GB50308-1999

3《地下鐵道工程施工及驗(yàn)收規(guī)范》GB50299-2003

4《錨桿噴射混凝土支護(hù)技術(shù)規(guī)范》GB50086-2001

5《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2002

6《鋼筋焊接及驗(yàn)收規(guī)程》JGJ18-2012

7《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)程》DBJ01-82-2005

8《混凝土強(qiáng)度檢驗(yàn)評定標(biāo)準(zhǔn)》GB/T50107-2011

9《混凝土質(zhì)量控制標(biāo)準(zhǔn)》GB50164-2011

10《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2001

11《建筑工程質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)》GB50210-2001

12《建筑結(jié)構(gòu)檢測技術(shù)標(biāo)準(zhǔn)》GB/T50344-2004

13《軌道交通隧道工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》JQB-050-2005

14《軌道交通工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》JQB-068-2005

3、合同文件中指定的標(biāo)準(zhǔn)、規(guī)范、規(guī)程及現(xiàn)行國家及烏魯木齊市的相關(guān)法規(guī)、技

術(shù)規(guī)范。

4、結(jié)合我聯(lián)合體現(xiàn)有的技術(shù)水平、施工管理水平、機(jī)械設(shè)備配置能力及施工經(jīng)驗(yàn)。

5、我聯(lián)合體質(zhì)量、環(huán)境、職業(yè)健康安全管理體系標(biāo)準(zhǔn)中的有關(guān)規(guī)定。

6、相關(guān)的技術(shù)聯(lián)系單及會議紀(jì)要。

1.3編制原則

1、在充分理解合同文件、設(shè)計(jì)圖紙及認(rèn)真踏勘現(xiàn)場的基礎(chǔ)上,采用經(jīng)充分論證的

先進(jìn)、科學(xué)、合理、經(jīng)濟(jì)、可行的施工方案。

2、嚴(yán)格貫徹“安全第一、質(zhì)量為本”原則及淺埋暗挖十八字方針,確保施工安全、

確保工程質(zhì)量、確保施工工期,全面兌現(xiàn)合同承諾。

3、優(yōu)化施工技術(shù)方案,推廣應(yīng)用“四新”成果,加強(qiáng)科技創(chuàng)新和技術(shù)攻關(guān),確保

工程質(zhì)量全面創(chuàng)優(yōu)。

4、加強(qiáng)監(jiān)控量測和信息反饋,用科學(xué)數(shù)據(jù)指導(dǎo)施工,確保施工工藝與施工規(guī)范及

設(shè)計(jì)要求相符。

5、嚴(yán)格執(zhí)行烏魯木齊市建設(shè)行政主管部門下發(fā)的有關(guān)工程施工的安全、文明、環(huán)

保、衛(wèi)生健康等管理?xiàng)l例;施工全過程對環(huán)境破壞最小、占用場地最少,并有周密的環(huán)

境保護(hù)措施,樹立良好的工程形象和企業(yè)社會形象。

6、充分考慮本標(biāo)段工程特點(diǎn)和周邊施工環(huán)境,最大限度地降低工程施工對城市秩

序、環(huán)境衛(wèi)生、市容市貌、地面交通、既有設(shè)施安全及市民正常生活帶來的不利影響。

7、堅(jiān)持試驗(yàn)先行,樣板引路,選擇更適用于本合同段工程項(xiàng)目的管理方法、施工

機(jī)械設(shè)備、施工工藝和方法。突出工程重點(diǎn)、難點(diǎn),堅(jiān)持規(guī)范化管理、標(biāo)準(zhǔn)化作業(yè),不

斷優(yōu)化施工組織設(shè)計(jì),以質(zhì)量保安全,以質(zhì)量創(chuàng)效率。

2工程概況

2.1工程簡介

烏魯木齊軌道交通機(jī)場支線三工站至宣仁墩站區(qū)間從三工站出發(fā)后沿南北向北京

路北行,然后向西折向東西向的城北主干道,最后到達(dá)終點(diǎn)宣仁墩站。

區(qū)間右線設(shè)計(jì)起點(diǎn)里程為YJDK0+481.843,右線設(shè)計(jì)終點(diǎn)里程為YJDK1+545.575,

右線全長1101.602m(含長鏈37.87m)。區(qū)間左線設(shè)計(jì)起點(diǎn)里程為ZJDK0+353.315,終點(diǎn)

里程ZJDK1+545.575,全長1164.068m(含短鏈28.192m)。

本區(qū)間約有207.25m采用明挖施工,其余均為暗挖單洞單線區(qū)間,馬蹄形斷面,隧

道拱頂埋深8?17m,穿越地層主要為無水卵石層,圍巖級別為V級,采用礦山法施工。

暗挖區(qū)間在YJDK0+965.578設(shè)有一處豎井及橫通道。工程概況圖如圖2-1所示。

明挖區(qū)間

宜仁墩站

1、6號線立交明挖段

說明:

1、1、6號線立交明挖段由14標(biāo)負(fù)責(zé)實(shí)施;

2、豎井一三工站左線隧道長度約578m,豎井-1、6號線立交明挖段隧道長度約70m,

立交明挖段一三工站隧道長度約360m,豎井一明挖區(qū)間左線隧道長度約405m,

豎井一明挖區(qū)間右線長度約328m,明挖區(qū)間一宣仁墩站左右線隧道長度均約為80m:

三工站

圖2-1三工站一宣仁墩站區(qū)間工程概況圖

本工程暗挖區(qū)間隧道按設(shè)計(jì)及運(yùn)行類型共分五種斷面形式,分別為DDT、DD-2、

1-1、2-2、3-3斷面,其中:DD-1為標(biāo)準(zhǔn)斷面,DD-2為穿越上覆雜填土區(qū)標(biāo)準(zhǔn)斷面,

3-3斷面為左線射流風(fēng)機(jī)安裝區(qū)段,1T及2-2斷面為渡線加寬段。左右線各斷面里程

位置見表2-1及圖2-2、2-3所示。

表2-1區(qū)間隧道左、右線各里程段設(shè)計(jì)斷面情況匯總表

設(shè)計(jì)

區(qū)間隧道右線里程樁號長度(m)區(qū)間隧道左線里程樁號設(shè)計(jì)斷面長度(m)

斷面

YK0+48L843?ZK0+353.315?

DD-1361.973DD-110.1

YK0+843.816ZK0+363.415

YK0+843.816?ZK0+363.415?

明挖47.8523-319.8

YK0+891.668ZK0+383.215

YK0+891.668?ZK0+383,215-

DD-171.66DD-1548.595

YK0+963.328ZK0+931.810

YK0+963.328?ZK0+93L810?

橫通道4.5橫通道4.5

YK0+967.828ZK0+936,310

ZK0+936.310?

YK0+967.828?YK1+000DD-132.172DD-123.69

ZK0+960.000

ZK0+960.000?

YK1+000?YK1+070DD-270DD-295

ZK1+055.000

225.905286.235

ZK1+055.000?

YK1+070?YK1+258.035DD-1(含長鏈DD-1(含短鏈

ZK1+369.427

37.87)28.1918)

YK1+258.035?ZK1+369.427?

明挖207.669明挖96.283

YK1+465.704ZK1+465.710

YK1+465.704?ZK1+465.710-

2-223.3642-220.986

YK1+489.068ZK1+486.696

YK1+489.068?ZK1+486.696?

1-117.3421-117.338

YK1+506.410ZK1+504.034

YK1+506.410?ZK1+504.034?

DD-139.165DD-141.541

YK1+545.575ZK1+545.573

本暗挖區(qū)間工程同時(shí)存在平曲線和豎曲線。其中:右線含有R=400m的平曲線,

R=5000m的豎曲線,且含有2個(gè)變坡點(diǎn),坡度分別為5.83樂2.08%及0.43%;左線含有

R=400m的平曲線,R=3000m及R=5000m的豎曲線,且含有3個(gè)變坡點(diǎn),坡度分別為:0.47%.

6.22%,2%及0.43%,詳見圖2-2及圖2-3所示。

s

4.

s

9s

七+

變喙里程明暗挖分界里程YJ0K1+125.510變形經(jīng)工程o

區(qū)間行線設(shè)計(jì)起點(diǎn)里程變形繼里程將井及橫通道中心里程(聯(lián)絡(luò)通道兼廢水泵房)三-

熱力溝(的石1000X1000)明暗挖分界里程二3

VJDKIH84I,816YJMWP843.816…仁心「力6叵w

YJDKCK1S3,SI:-;[,』、。,",5.37X支g.f

OY.IDK1+258.034。兇A

變形縫里程變形繾里程8?

S明暗檢分界電程史

、I而if,].;:、;:SS§?變的維里程

YJDK1H66.306一

8S5.O舌YJDKb543.575

S一

明暗挖分界里程科紿里程.SY.JDKI+256.031S

Ta'

YJDKCH891.668YJDKCH893,668sT-

-8

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。

評論

0/150

提交評論