1、1.1.1. PPR 管道施工工藝 PPR pipe installation method1.1.1.1. 編制依據(jù) Basis of drawing up1.1給水排水管道工程施工及驗(yàn)收規(guī)范GB50268-97 。Construction and acceptance norm of Water supply and drains piping engineering。1.2室內(nèi)管道支架及吊架 03S402 Piping support indoor 。1.1.1.2. 施工工藝: Construction technique:根據(jù)現(xiàn)場(chǎng)各種管線布置情況和流程順序確定工藝流程,本工程采用如下

2、工藝流程:施工準(zhǔn)備7材料進(jìn)貨檢驗(yàn) 7PPR 管預(yù)制加工 7支吊架制作安裝 7PPR 管安裝 7PPR 管試驗(yàn)According to the arrangement and flow order of field all kinds of pipelines, confirm the processsupport andflow. This engin eeri ng ado pts the follow ing pro cess flow: con struct ion prep arati on material stocking test 7PPR pipe pre-processing

3、 7manufacture and installation of7 PPR pipe testhan ger in stallati on of PPR pipe1) . 施工準(zhǔn)備: Construction preparation施工工作及技術(shù)人員認(rèn)真熟悉原圖紙,領(lǐng)會(huì)設(shè)計(jì)意圖, 對(duì)圖紙中和實(shí)際管道布置清楚后,才能施工。Construction work and techniciansare strictly familiarwith the original drawing,comprehenddesign purpose, and carry out theconstruction af

4、ter theclarity to drawing and actual pipelinearrangement.施工人員須熟悉 PPR 管的一般性能,掌握必須的操作要點(diǎn)。在各項(xiàng)預(yù)制加工項(xiàng)目開始前,根據(jù)實(shí)際編制材料計(jì)劃,將需要的材料、設(shè)備等按規(guī)格、型號(hào)準(zhǔn)備好,運(yùn)至現(xiàn)場(chǎng)。Constructer must know well the general performanceof PPR, master necessary operationpoints,Before each precast processing project, according to the plan of practical

5、 schedulingmaterial, well prepare the needed material and equipment according to specification and modeland transport to the field.材料設(shè)備要求: 到現(xiàn)場(chǎng)的管材、 管件等提供的管材和管件應(yīng)符合設(shè)計(jì)規(guī)定,并附有產(chǎn)品說明書和質(zhì)量合格證書,須認(rèn)真檢查并經(jīng)業(yè)主驗(yàn)明材質(zhì),核對(duì)質(zhì)保書,規(guī)格、型號(hào)等,合格后方能入庫,并分別作好標(biāo)識(shí)。Material equipment requirements: The offered field pipe and pipe fittings s

6、hould accord withdesign prescription, adding with product stipulation and quality certification. Strictly examine and identify material by owner, check quality guarantee, specification and models etc, warehouse after qualification, and mark separately.管材和管件的內(nèi)外壁應(yīng)光滑平整,無氣泡、裂紋、脫皮和明顯的痕紋、凹陷,色澤應(yīng)基本一致。不 得使用有

7、損壞跡象的材料。如發(fā)現(xiàn)管道質(zhì)量有異常,應(yīng)在使用前進(jìn)行復(fù)檢。The internal and external surface of pipe and pipe fittings should be smooth and flat, without air bladder, crack, desquamate, obvious trace and hollow, and the color and luster should be consistent. The material with damaged mark should be forbidden. If it is discovered

8、 that there is problem in the pipeline quality, recheck it before using.管材的端面應(yīng)垂直于管材的軸線。管件應(yīng)完整、無缺損、無變形。End face of pipe should be upright to the axes of pipe. The pipe fittings should be intact, without lack and distortion.管件和管材不應(yīng)長期置于陽光下照射, 為避免管子在儲(chǔ)運(yùn)時(shí)彎曲, 堆放應(yīng)平整。 搬運(yùn)管材和管件時(shí), 應(yīng)小心輕放,避免油污,嚴(yán)禁劇烈撞擊,與尖銳物觸碰和拋、摔、拖。

9、管材開口處應(yīng)及時(shí)封堵,以 免管道堵塞造成不必要的浪費(fèi)。Pipe fitting and pipe should not be placed in the sunshine for a long time to avoid the pipe curve in storage and transportation, and piling up them should be level. When conveying pipe and pipe fittings, they should handled with care and avoid oil stain. Strong bump, cast

10、, throw and draw is使其溫度接近forbidden. Pipe hatch should be immediately plugged to avoid pipe jam and unnecessary waste.施工現(xiàn)場(chǎng)與材料存放處溫差較大時(shí), 應(yīng)于安裝前將管件和管材在現(xiàn)場(chǎng)放置一定時(shí)間, 施工現(xiàn)場(chǎng)環(huán)境溫度。When there is large difference in construction field and storage temperature, should place pipe fitting and pipe at the field before in

11、stallation for certain time and make its temperature closure to environment temperature of construction field.本項(xiàng)目 PPR 管道采用熱熔連接,施工前應(yīng)仔細(xì)檢查所使用的熱熔機(jī)具、割刀是否符合要求和正常 使用,使用的電源及電線是否正常和安全。如下圖:This project pipe-PPR pipe adopts heat fusion. Before construction, should carefully examine whether the using hot melt e

12、quipment and cutter knife accord with requirements and normal service, the using power supply and wire are normal and security. as the following drawings.材料進(jìn)貨檢驗(yàn):Material-stocking test10%,管材同一截面的壁厚偏差應(yīng)v為確保安裝質(zhì)量,材料進(jìn)貨時(shí)應(yīng)嚴(yán)格檢驗(yàn),其管徑橢圓率應(yīng)V14% ,內(nèi)外壁應(yīng)光滑、平整,無氣泡、裂口、裂紋、凹陷、脫皮和嚴(yán)重的冷斑及明顯的痕跡。For insuring the installation

13、quality, should strictly test the material when it is stocked. The ellipticity of pipe diameter should be less than 10%. The wall thickness deviation in the same pipe section should be less than 14%. The internal and external surface should be smooth, flat, without air bladder, crack, hollowing desq

14、uamate, severe cold appearance and obvious trace.2) . PPR 管道預(yù)制加工 : Precast processing of inner pipe PEpipelinePE 管連接:采用熱熔連接方式。熱熔連接最為可靠,操作方便,氣密性好,接口強(qiáng)度高。本方案 中熱熔焊接為關(guān)鍵工序,具體方案如下:PPR pipe connection: adopt hot melt connection method. Hot melt method is the most reliable, with convenient operation and good

15、 air tightness and high joint strength. In this project, sweating soldering is the key working procedure; the detail project is as the followings.1 ) PPR 管道接觸式焊接安裝 PE pipe touch welding installation其施工方法及技術(shù)措施如下:Method of execution of works and actions to be taken管道連接采用熱熔焊接。 熱熔焊接為關(guān)鍵工序, 必須嚴(yán)格控制。 The pi

16、ping conjunction adopts hot melt to weld. The hot melt weld is the key work , have to control strictly. 管道焊接主要程序: The piping welds main procedure:A :設(shè)置焊機(jī)的初始值(液壓值、溫度)Establish the initial value of the welding machine(the liquid presses value, temperature)液壓值的設(shè)置:The constitution of the liquid presses

17、value管徑 DN100MM 以下,液壓值設(shè)定為 0.2 MPa;Diameter of pipe is DN100 MM the following, the liquid presses value to set for 0.2 MPa;管徑 DN100-350MM 時(shí),液壓值設(shè)定為 0.4-0.5MPa;Diameter of pipe is DN100-DN350 MM, the liquid presses value to set for 0.4-0.5 MPa;溫度的設(shè)置 : The constitution of the temperature加熱板預(yù)熱時(shí),溫度設(shè)定為210

18、C ;Heat plank prepare hot, the temperature sets to 210加熱焊口時(shí),溫度設(shè)定為190-210 C .While heating the welding , the temperature sets to 190-210c.B :固定焊管,保證待焊接的管及管件中心在一條直線上,錯(cuò)口應(yīng)在2毫米以內(nèi);Fix the welding pipe, assurance treats to welding pipe and fittingcenter i's osn a straight line,Distance of shunt should

19、at 2mm in;C :拋磨管端口 ,保證端口平整,再用醫(yī)用酒精清洗管端口,保證端口內(nèi)外壁的清潔;Throw to whetpipe 's head, promise pipe 's head neat, use again to cure to clean pipe' s head with the alcohol,promise the inside and outside wall of pipe' s head to clean;D :室外溫度為 20 °C時(shí)加熱管及管件端口焊接參數(shù)如下表Outdoor temperature is at 2

20、0 °Cheating pipe and tube port welding parameters following tableE:取出焊接好的管段,檢查焊口,焊口寬度、高度、形狀、均勻度等均符合焊接標(biāo)準(zhǔn)即為合格,方可安裝。 Take out to welding pipe, check the welding sew , the welding sew width, height, shape,even degree.etc. all matching to weld standard is qualified, then be able to install.3). 管道試壓及

21、沖洗 Pipeline Pressure Testing and Flushinga). 管道試壓: Pipeline Pressure Testing管道安裝完畢, 應(yīng)按設(shè)計(jì)規(guī)定對(duì)管道系統(tǒng)進(jìn)行強(qiáng)度、嚴(yán)密性等試驗(yàn),以檢查管道系統(tǒng)及各連接部位的工程質(zhì)量。 After installation, pipeline should betaken strength testing and hermetic testingaccording to design as well as the quality test of pipeline system and connections.管道用水作介質(zhì)進(jìn)行

22、強(qiáng)度及嚴(yán)密性試驗(yàn); 應(yīng)按照設(shè)計(jì)的具體規(guī)定采用。 如設(shè)計(jì)無規(guī)定時(shí),工作壓力 不低于 0.07MPa 的管道一般采用水壓試驗(yàn),工作壓力低于 0.07MPa 的管道一般采用氣壓試驗(yàn)。Media of strength testing and hermetic testing is water and the water used for test should meet the relative standards. If no request in design, it usually goes like below: pipeline with work pressure more than 0

23、.07MPa should be taken water pressure testing; pipeline with work pressure less than 0.07MPa should be taken air pressure test.1) 管道系統(tǒng)試驗(yàn)前應(yīng)具備以下條件:Following conditions should be met before testing:Finish the pipeline system installationA.管路系統(tǒng)施工安裝完畢,且符合設(shè)計(jì)和規(guī)范的要求。B.全部支、吊架安裝完畢且合格。and meet the design and s

24、pecification request.Supports installation should be finished and qualified.C.管道位置、標(biāo)高、坡度、坡向等經(jīng)復(fù)查合格;試驗(yàn)用的臨時(shí)加固措施經(jīng)檢查確認(rèn)安全可靠。Pipeline ' s position, elevation, gradient and slop direction should be qualified. The temporary facility1.5 級(jí),表的滿刻度值為最大被測(cè)壓used for test should be stable and safe.D.試驗(yàn)用的壓力表經(jīng)校驗(yàn)合格,

25、并做好標(biāo)識(shí);精度不低于力的 1.52 倍;試驗(yàn)壓力表不少于 2 塊。 Pressure meter used for test should be ok and marked with precision no less than 1.5-level. The full scale value should be 1.5-2 times as biggest tested-pressure.2)具體試驗(yàn)方法宜采用分區(qū)、分層試壓和系統(tǒng)試壓相結(jié)合的方法。分區(qū)、分層試壓時(shí),待系統(tǒng)充滿水且放凈空氣后進(jìn)行加壓,先把管網(wǎng)或管段的壓力升至試驗(yàn)壓力,穩(wěn)壓 10 分鐘,壓力不得下降,再將壓 力降至工作壓力, 在

26、60分鐘內(nèi)壓力不得下降、外觀檢查無滲漏為合格。 系統(tǒng)試壓時(shí)以最低點(diǎn)壓力為準(zhǔn),The test壓力升至試驗(yàn)壓力后, 穩(wěn)壓 10 分鐘, 壓力下降不得大于 20Kpa ,再將系統(tǒng)壓力降至工作壓力, 外觀檢 查無滲漏為合格。通知有關(guān)人員驗(yàn)收、辦理交接手續(xù),然后把水泄凈、拆除試壓泵和水源。method is to be chosen the combination of subarea test and delamination test. When doing test, add pressure after pipe is full of water and without air in. Fir

27、st increase the pressure of pipeline net or pipe section to tested pressure and keep it for 10min with no descending of work pressure. Then lower the pressure to work pressure for 60min to check if there are any leakages. No leakages are qualified.When doing test for pipeline system, first increase

28、the pressure from the lowest to tested-pressure and keep it for 10min with pressure decline less than 20Kpa. Then lower the system pressure to work pressure to check if there are any leakages. No leakages are qualified. Finally notice relative personnel for check and discharge the water in pipe and

29、remove the pressure-testing pump and shut off water supply.3) 試驗(yàn)時(shí)不得敲擊管道。Don' t beat the pipe when testing .4)試壓完畢后, 恢復(fù)原有的設(shè)備、 表計(jì),并拆除隔斷用盲板, 試驗(yàn)后填寫試壓記錄并作好驗(yàn)收簽證。Recover the equipment and meter and remove the blind plate for partition after test. Then fill the test record.b). 管道沖洗 Pipeline blowing and

30、flushing管道水系統(tǒng)沖洗: Pipeline Flushing of Water Pipe System: 1)調(diào)試、運(yùn)行前必須進(jìn)行系統(tǒng)的沖洗:水系統(tǒng)主、干管必須開式進(jìn)行沖洗排污,反復(fù)多次直至確認(rèn)清潔,然后才允許轉(zhuǎn)入封閉式循環(huán)過濾(管網(wǎng)、機(jī)組、設(shè)備整體進(jìn)行),反復(fù)清理過濾器,直到整 個(gè)系統(tǒng)干凈、清潔。 It must do flushing after test and commissioning: main pipe and branches should be down flushing repeatedly and then it may be in closed circling filtration (includepipeline net, units, equipment). Clean the filter again and again until the system is clean.2)管道系統(tǒng)在清洗前必須把設(shè)備與系統(tǒng)分離開(即關(guān)閉設(shè)備進(jìn)出口閥門),開啟旁通閥(可以臨時(shí)設(shè)置),向管網(wǎng)最高點(diǎn)灌水,直到系統(tǒng)灌滿水為止;接著從系統(tǒng)的最低點(diǎn)處把臟水放出,按上述方 法反復(fù)多次,直至系統(tǒng)無臟物;然后啟動(dòng)冷凍水泵、冷卻水

溫馨提示

  • 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
  • 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
  • 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
  • 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
  • 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
  • 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
  • 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。

評(píng)論

0/150

提交評(píng)論