中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路第1部分:輸電線路內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書編碼:SDXL-ZW-0886SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書目
次1234567
工程概況及適用范圍····································································································································85編寫依據(jù)························································································································································85作業(yè)流程························································································································································86安全風(fēng)險辨析與預(yù)控····································································································································86作業(yè)準備························································································································································88作業(yè)方法························································································································································89質(zhì)量控制措施及檢驗標準····························································································································98
87中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路11.11.2
工程概況及適用范圍工程簡述包括:工程的總體情況,鐵塔設(shè)計型號,工程量,地形等。鐵塔配置表1-1
鐵塔配置表2
編寫依據(jù)88
表2-1
編寫
依據(jù)序號引用資料名稱1GBJ50233序號引用資料名稱1GBJ50233—2005《110kV~500kV架空送電線路施工及驗收規(guī)范》2GB50017—2003《鋼結(jié)構(gòu)設(shè)計規(guī)范》3JGJ82—1991《鋼結(jié)構(gòu)高強度螺栓連接的設(shè)計、施工及驗收規(guī)范》4DL/T875—2004《輸電線路施工機具設(shè)計、試驗基本要求》5DL409—1991《電業(yè)安全工作規(guī)程電力線路部分》6DL5009.2—2004《電力建設(shè)安全工作規(guī)程第2部分:架空電力線路》7SDZ025—1987《輸電線路鐵塔質(zhì)量分等標準》8DL/T5092—1999《110kV~500kV架空送電線路設(shè)計技術(shù)規(guī)程》9《10kV~500kV輸變電及配電工程質(zhì)量驗收與評定標準第1部分:輸電工程》10《電網(wǎng)建設(shè)安全健康與環(huán)境管理辦法實施細則(計[2004]27號)》11本工程的相關(guān)設(shè)計圖紙12本工程的施工組織設(shè)計13本單位的質(zhì)量管理體系、職業(yè)健康安全管理體系、環(huán)境管理體系的相關(guān)文件14現(xiàn)場調(diào)查情況塔塔號桿塔型號轉(zhuǎn)角方向呼稱高(m)全高(m)連接方式塔身段塔身重(kg)塔腿段號A腿(kg)B腿(kg)C腿(kg)D腿(kg)總重(kg)N1JGD1左28°33′28.542.5插入式角鋼26252.513+11+11+121031.51520.71520.71259.131584.5N2JG21B左38°26′3044插入式角鋼24295.110+10+12+101620.61620.61105.51620.630262.4N3ZBK11B58.563.3插入式角鋼31281.515+15+16+16757.5757.5926.8926.834650.1合計2263549SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書3
作業(yè)流程圖3-1
作業(yè)(工序)流程圖4
安全風(fēng)險辨析與預(yù)控4.1
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)前,施工項目部根據(jù)該項目作業(yè)任務(wù)、施工條件,參照《電網(wǎng)建設(shè)施工安全基準風(fēng)險指南》(下簡稱《指南》)開展針對性安全風(fēng)險評估工作,形成該任務(wù)的風(fēng)險分析表。4.2
按《指南》中與內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)相關(guān)聯(lián)的《電網(wǎng)建設(shè)安全施工作業(yè)票》(編碼:SDXL-ZW-08-01/01),結(jié)合現(xiàn)場實際情況進行差異化分析,確定風(fēng)險等級,現(xiàn)場技術(shù)員填寫安全施工作業(yè)票,安全員審核,施工負責(zé)人簽發(fā)。4.3
施工負責(zé)人核對風(fēng)險控制措施,并在日站班會上對全體作業(yè)人員進行安全交底,接受交底的作業(yè)人員負責(zé)將安全措施落實到各作業(yè)任務(wù)和步驟中。4.4
安全施工作業(yè)票由施工負責(zé)人現(xiàn)場持有,工作內(nèi)容、地點不變時可連續(xù)使用10天,超過10天須重新辦理作業(yè)票,在工作完成后上交項目部保存?zhèn)洳?。?-1作業(yè)任務(wù)安全基準風(fēng)險指南89序號危害名稱風(fēng)險種類風(fēng)險等級風(fēng)險控制措施1人員打錨大錘脫手失誤物體打擊低風(fēng)險人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面2清理塔材滑動或墜落物體打擊低風(fēng)險清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉3抬運重物刮碰傷人割傷低風(fēng)險1.人員正確使用個人勞動防護用品。2.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致,同起同落4抬運工具質(zhì)量不合格碰撞低風(fēng)險1.運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。2.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮5不方便搬運物品的通道物體打擊低風(fēng)險1.施工人員應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境。作業(yè)前,先清除附近障礙物或采取其他措施。2.運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。序號危害名稱風(fēng)險種類風(fēng)險等級風(fēng)險控制措施1人員打錨大錘脫手失誤物體打擊低風(fēng)險人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面2清理塔材滑動或墜落物體打擊低風(fēng)險清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉3抬運重物刮碰傷人割傷低風(fēng)險1.人員正確使用個人勞動防護用品。2.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致,同起同落4抬運工具質(zhì)量不合格碰撞低風(fēng)險1.運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。2.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮5不方便搬運物品的通道物體打擊低風(fēng)險1.施工人員應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境。作業(yè)前,先清除附近障礙物或采取其他措施。2.運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路90序號危害序號危害名稱風(fēng)險種類風(fēng)險等級風(fēng)險控制措施3.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。4.雨雪后抬運物件時,應(yīng)有防滑措施6抱桿質(zhì)量不合格物體打擊中等風(fēng)險1.抱桿組立前應(yīng)進行外觀檢查。2.抱桿組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊。3.抱桿有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600。局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊。②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少7拉線收放失誤或綁扎不牢物體打擊中等風(fēng)險起立抱桿必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作8構(gòu)件失穩(wěn)致登高墜落墜落中等風(fēng)險1.高處作業(yè)人員必須使用安全帶。2.抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高9場地不平整、塔片墊物失穩(wěn)或塔片滑動夾傷可接受的風(fēng)險1.組裝場地應(yīng)平整,障礙物應(yīng)清除。2.選料應(yīng)由上往下搬動,不得強行抽拉。3.山坡上組裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施10組裝人員將手指伸入螺孔找正剪切可接受的風(fēng)險嚴禁將手指伸入螺孔找正11地面組裝豎立的塔片支撐不牢物體打擊可接受的風(fēng)險組裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施12地面組裝帶鐵固定不牢物體打擊低風(fēng)險分片組裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固13*未按技術(shù)方案起吊塔片物體打擊中等風(fēng)險吊裝方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定;工器具不得超規(guī)定使用14人員缺乏經(jīng)驗站位失誤物體打擊低風(fēng)險1.組立桿塔過程中,吊件垂直下方嚴禁有人。2.作業(yè)現(xiàn)場除必要的施工人員外,其他人員應(yīng)離開桿塔高度的1.2倍距離以外。3.在受力鋼絲繩的內(nèi)角側(cè)嚴禁有人15不按規(guī)定使用安全工器具*/個人防護用品墜落低風(fēng)險1.高處作業(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器。2.不得登爬單根主材進行高處作業(yè)16不按規(guī)定程序作業(yè)物體打擊低風(fēng)險抱桿提升前,應(yīng)將提升腰滑車處及其以下塔身的輔材裝齊,并擰緊螺栓17拉線收放控制失誤或綁扎不牢物體打擊低風(fēng)險升降抱桿必須有人統(tǒng)一指揮,四側(cè)拉線應(yīng)均勻收放及綁扎應(yīng)由技工操作18下托繩綁扎錯誤位置物體打擊低風(fēng)險內(nèi)拉線抱桿的拉線應(yīng)綁扎在塔身節(jié)點處,承托繩應(yīng)綁扎在節(jié)點上方,且緊靠節(jié)點處19抱桿腰環(huán)設(shè)置不符合要求物體打擊低風(fēng)險提升抱桿應(yīng)設(shè)置兩道腰環(huán);采用單腰環(huán)時,抱桿頂部應(yīng)設(shè)臨時拉線控制20主要受力工器具不合格物體打擊中等風(fēng)險嚴格按施工技術(shù)措施要求選用合格工器具21*受力錨樁不按規(guī)定布置物體打擊中等風(fēng)險嚴格按施工技術(shù)措施要求布置受力錨樁22塔片就位誤操作墜落低風(fēng)險主材和側(cè)面大斜材未全部連接牢固前,不得在吊SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書55.1
作業(yè)準備人員配備表5-1
人員配備表5.2
主要工器具及儀器儀表配置表5-2
主要工器具及儀器儀表配置表表5-2(續(xù))
91序號工作崗位人數(shù)備注1現(xiàn)場指揮1重要崗位2安全監(jiān)督1重要崗位,必須專責(zé)3塔上作業(yè)8重要崗位,持證上崗4地面組裝155機動絞磨手2重要崗位,持證上崗6拉磨繩27控制大繩(8)由地面組裝人員兼任合計29說明:根據(jù)實際工程量配置。序號工作崗位人數(shù)備注1現(xiàn)場指揮1重要崗位2安全監(jiān)督1重要崗位,必須專責(zé)3塔上作業(yè)8重要崗位,持證上崗4地面組裝155機動絞磨手2重要崗位,持證上崗6拉磨繩27控制大繩(8)由地面組裝人員兼任合計29說明:根據(jù)實際工程量配置。序號序號危害名稱風(fēng)險種類風(fēng)險等級風(fēng)險控制措施件上作業(yè)23高處物件失穩(wěn)墜落物體打擊低風(fēng)險1.桿塔材、工具嚴禁浮擱在桿塔及抱桿上。2.傳遞小型工具或材料不得拋擲24抱桿拆除操作失誤或措施不當(dāng)物體打擊低風(fēng)險拆除抱桿應(yīng)事先采取防止拆除段自由傾倒措施,然后逐段拆除,嚴禁提前擰松或拆除部分連接螺栓25搬運工具質(zhì)量不合格碰撞低風(fēng)險1.運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。2.重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮序號序號名稱規(guī)格/編號單位數(shù)量備注1抱桿500mm×500mm×24m副1角鋼格構(gòu)式抱桿2腰環(huán)□700mm×700mm副2按抱桿型號配置3機動絞磨3T臺14起重滑車5T(雙輪)只25起重滑車3T(單輪)只26地錨3T個47地錨5T個1序號序號名稱規(guī)格/編號單位數(shù)量備注8U形掛環(huán)5T個109U形環(huán)3T個20中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路66.1
作業(yè)方法施工準備6.1.16.1.1.16.1.1.2
技術(shù)準備鐵塔組立施工前,必須對全體施工人員進行技術(shù)交底。施工人員熟悉鐵塔組裝施工圖紙,并對所負責(zé)鐵塔組立的樁位的地形、地貌、適宜采用哪種組立方法,應(yīng)做到心中有數(shù)。6.1.1.3
做好立塔試點工作。每個立塔組對每種塔型的首基都要進行試點。立塔試點需項目部技術(shù)、安全、質(zhì)量負責(zé)人和施工隊長、技術(shù)員、治安員及工程監(jiān)理人員參加。試點的目的是為了檢驗技術(shù)交底的內(nèi)容是否可行,總結(jié)經(jīng)驗,為全面開展組立作好準備。6.1.26.1.2.1
機具準備立塔施工所使用的工具應(yīng)經(jīng)項目部安監(jiān)部和工程部進行檢驗,并標識。檢驗合格者方可在本工程施工中使用。使用前必須進行外觀檢查,并進行標識。不合格者嚴禁使用,并且不得以小代大。6.1.2.2
本工程使用的計量儀器(游標卡尺、經(jīng)緯儀、扭矩扳手、鋼尺)應(yīng)經(jīng)有相應(yīng)資格的檢測單位檢驗,檢驗合格者方可使用。6.1.2.3
各種工器具運往現(xiàn)場前必須清理檢查,主要工器具檢查要求如下:(1)機動絞磨在使用前必須仔細檢查各部件,特別是剎車裝置是否完好。(2)各種抱桿必須確認符合組立要求方準使用,抱桿必須無裂紋、脫皮、嚴重銹蝕及彎曲等缺陷。(3)抱桿頂、底座的各焊縫應(yīng)完好無裂紋,轉(zhuǎn)動部分應(yīng)靈活無卡滯,連接螺栓不得變形。(4)鋼絲繩有下列情況之一者應(yīng)報廢或截除:1)在一個節(jié)距內(nèi)(每股鋼絲繩捻一周的長度)的斷絲根數(shù)超過表6-1規(guī)定報廢標準者。2)鋼絲繩中有斷股者。3)鋼絲磨損或腐蝕深度達到原直徑40%以上者,或本身受過嚴重火燒或局部電燒者。4)壓扁變形和表面毛刺嚴重者。5)斷絲數(shù)量雖不多,但斷絲增加很快者。92
表6-1
鋼絲繩一節(jié)距內(nèi)斷絲數(shù)報廢標準10角鐵樁∠7510角鐵樁∠75×8×1500根1011鋼絲繩15×50m條4內(nèi)拉線12鋼絲繩20×30m條4承托繩13鋼絲繩13×15m條2腰環(huán)用14鋼絲繩13×200m條1提升抱桿用15鋼絲繩13×300m條1絞磨繩16鋼絲繩9×130m條1調(diào)整繩17鋼絲繩15×20m條4鋼絲繩吊套說明:工具配備可根據(jù)現(xiàn)場需要進行調(diào)整,所有受力器具應(yīng)通過受力計算才可使用。規(guī)格規(guī)格安全系數(shù)6×19=114+16×37=222+16×61=366+118×19=342+1規(guī)格安全系數(shù)順捻逆捻順捻逆捻順捻逆捻順捻逆捻小于6126221136183618SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書6.1.2.46.1.2.5
編插鋼絲繩套時,插接段長度不得小于鋼絲繩直徑的15倍,且不得小于300mm。滑車必須經(jīng)常檢查及加潤滑油,其邊緣有裂紋或嚴重磨損、軸承變形者、吊鉤外觀檢查有裂紋或明顯變形者均不得使用。6.1.36.1.3.1
材料準備組立鐵塔前必須對運往現(xiàn)場的塔材進行清點數(shù)量和檢查質(zhì)量,質(zhì)量不合格者不得使用,缺少主材和包鋼者不得組立。6.1.3.26.1.3.36.1.46.1.4.16.1.4.26.1.4.3
組立用的螺栓、墊圈、腳釘必須齊全,同時注意螺栓種類的不同。地面已組裝好的塔段,經(jīng)檢查合格后方準吊裝。現(xiàn)場布置根據(jù)鐵塔結(jié)構(gòu)及組立現(xiàn)場,做好場地平整,清除影響立塔的障礙物?,F(xiàn)場布置應(yīng)符合文明施工要求,材料堆放整齊,現(xiàn)場設(shè)置施工標志牌和安全警示牌。施工現(xiàn)場必須設(shè)置安全警示牌和施工標志牌,并插彩旗及安全標語。在鄰近公路、村莊等施工現(xiàn)場設(shè)置有效的安全作業(yè)圍閉。6.1.4.4
拉線、絞磨必須使用地錨,嚴禁使用角鐵樁錨固。地錨坑的開挖應(yīng)滿足下述要求:(1)地錨坑深度可視土質(zhì)及地錨受力大小確定??蓞⒄毡?-2選擇使用。表6-2
地錨坑深度表(2)地錨坑必須開挖馬道。馬道對地面夾角應(yīng)盡量與受力方向一致,一般不應(yīng)大于40°。馬道寬度不得太寬,以0.1~0.3m為宜,如圖6-1所示。圖6-1
地錨埋設(shè)示意圖(3)當(dāng)?shù)劐^坑位于松軟地質(zhì)或泥沼地帶時,必須根據(jù)地錨受力情況采取下述方法加固,必要時要求項目部技術(shù)人員確認:1)增加地錨坑深度。2)加大地錨規(guī)格或用雙地錨。3)在地錨的受力側(cè)增打角鐵樁或擋板。4)地錨選用表見表6-3。93地錨受力(kN)堅硬土(m)一般土(m)泥沼土(m)備注(相當(dāng)受力kg·f)29.41.41.52.0300049.01.61.72.4500058.81.71.92.66000地錨受力(kN)堅硬土(m)一般土(m)泥沼土(m)備注(相當(dāng)受力kg·f)29.41.41.52.0300049.01.61.72.4500058.81.71.92.6600066~7147261338193819大于7168301540204020中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路表6-3(4)地錨受力前需進行全面檢查。
地錨選用表6.1.4.5
抱桿的組裝。抱桿的提升孔應(yīng)安裝在下端,連接抱桿的螺栓必須帶好墊圈,以增強抱桿的連接強度,減少抱桿彎曲變形;抱桿連接后,隨即檢查其彎曲度,不得超過桿長的1/600,否則應(yīng)進行調(diào)整。6.1.56.1.5.16.1.5.2
地面組裝鐵塔地面組裝前必須清點運往樁位的構(gòu)件及螺栓、墊圈等數(shù)量是否齊全,質(zhì)量是否符合要求。塔構(gòu)件的清點應(yīng)遵守下列規(guī)定:(1)清點構(gòu)件的數(shù)量,核實實物與材料清單、組裝圖是否相符,并做好缺料、余料的填表登記,及時上報項目部。(2)清點構(gòu)件時,應(yīng)逐段按編號順序排好。(3)構(gòu)件應(yīng)鍍鋅完好,如因運輸造成局部鍍鋅層磨損時,應(yīng)涂上廠家提供的防銹涂料,進行防銹處理。涂刷前,應(yīng)將磨損處清洗干凈保持干燥。(4)檢查構(gòu)件的彎曲度,角鋼的彎曲度不應(yīng)超過相應(yīng)長度的1/800。(5)嚴格按設(shè)計圖紙組裝,注意角鐵的里、外的區(qū)分。6.1.5.36.1.5.4助材)。6.1.5.5
根據(jù)地形及設(shè)備條件,確定地面的組裝方法及鐵塔組立方法,確定構(gòu)件的布置方向。根據(jù)抱桿可能的提升高度、抱桿的允許承載能力等,合理確定吊裝構(gòu)件的分片及應(yīng)帶附鐵(輔地面組裝的塔片,由于地形的限制,需要重疊放置的,必須注意先吊裝的塔片后組裝,后吊裝的先組裝。塔片之間應(yīng)支墊平衡,防止變形。6.1.5.66.1.5.76.1.5.8
如果發(fā)現(xiàn)塔型的部分構(gòu)件容易變形時,應(yīng)用圓木進行補強。每段塔片兩主材之間的各輔助材應(yīng)盡可能裝齊,連接螺栓要擰緊。兩塔片之間的各種輔助材盡可能連帶在主材上。附鐵在兩片之間的分配要均衡。附鐵與主材的連接螺栓不要擰得太緊,螺帽帶平即可?;顒拥母借F應(yīng)活動端向下與主材用麻繩綁扎在一起。6.2
內(nèi)拉線懸浮抱桿分解組立技術(shù)措施94
6.2.16.2.1.16.2.1.2
現(xiàn)場布置內(nèi)拉線抱桿單吊組塔現(xiàn)場布置示意如圖6-2所示。內(nèi)拉線抱桿雙吊組塔現(xiàn)場布置示意如圖6-3所示。名稱規(guī)格名稱規(guī)格(m)一般土埋深(m)相當(dāng)受力(kg·f)抱桿拉線1.4×0.31.54000抱桿拉線1.4×0.31.86000抱桿拉線2.0×0.51.88000絞磨1.2×0.21.53300絞磨1.4×0.31.54000注:土壤上拔角取20°。SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書圖6-2
內(nèi)拉線抱桿單吊組塔現(xiàn)場布置示意圖1—抱桿;2—拉線;3—被吊構(gòu)件;4—控制繩;5—承托繩;6—起吊繩;7—起吊滑車組;8—地滑車圖6-3
內(nèi)拉線抱桿雙吊組塔現(xiàn)場布置示意圖1—被吊塔片;2—起吊鋼繩;3—起吊滑車組;4—腰滑車;5—地滑車;6—承托繩;7—攀根繩;8—抱桿;9—控制繩;10—朝地滑車;11—平衡滑車;12—絞磨以使用500mm×500mm×24m角鋼格構(gòu)式抱桿為例,抱桿額定負荷為284kN(最大軸向壓力),根據(jù)抱桿的試驗數(shù)據(jù)及本工程具體塔型的構(gòu)造,經(jīng)驗算后確定,吊重應(yīng)限制在2000kg以下。受力分析:當(dāng)抱桿傾斜5°,起吊角15°,拉線對地夾角60°時,起吊重量2000kg,則偏拉繩受力6.2kN,吊點千斤受力28.3N,抱桿內(nèi)拉線受力18.7kN,抱桿軸向壓力68.6kN。6.2.26.2.2.1
抱桿的布置內(nèi)拉線抱桿的組成:(1)由朝天滑車、朝地滑車及抱桿本身組成。在抱桿兩端的適當(dāng)位置上,設(shè)有連接拉線系統(tǒng)和承托系統(tǒng)用的固定裝置。(2)朝天滑車聯(lián)接于抱桿頂端,其主要作用是穿過起吊繩以提升鐵塔構(gòu)件并將起吊重力以軸向傳遞給抱桿。單吊法用單輪朝天滑車,雙吊法用雙輪朝天滑車。朝天滑車與抱桿的聯(lián)接,一般采用套接方式。要求朝天滑車還能在抱桿頂端沿抱桿軸線水平轉(zhuǎn)動,以適應(yīng)起吊繩在任何方向都能順利通過。(3)朝地滑車聯(lián)接于抱桿下端,其作用在于提升抱桿。6.2.2.2
抱桿宜分段聯(lián)接于抱桿下端,當(dāng)用花蘭連接時,應(yīng)使用內(nèi)花蘭,以便在提升抱桿時,能順利通過腰環(huán)。如果為外花蘭接頭,提升抱桿過程中,腰環(huán)應(yīng)隨時解開,以利接頭通過。6.2.2.3
本工程選用抱桿為角鋼格構(gòu)式500mm×500mm×24m抱桿。根據(jù)本工程具體塔型的構(gòu)造,經(jīng)驗算后確定,500mm×500mm抱桿的吊重應(yīng)限制在2000kg以下。6.2.2.4
抱桿在塔上位置如圖6-4所示。抱桿露出已組塔段的長度及插入已組塔段上平面的長度應(yīng)保持一定比例。一般是:L1:L2=7:3。為了95中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路方便構(gòu)件安裝就位,抱桿可以稍向吊件側(cè)傾斜,其傾角不得大于5°。圖6-4
抱桿位置示意圖6.2.2.5
根據(jù)鐵塔的實際分段長度及其根開尺寸,抱桿長度選取為L=1.5~1.75Hi式中:L——抱桿長度;Hi——鐵塔分段中最長一段高度。6.2.36.2.3.1
抱桿上拉線的布置抱桿拉線的長度L拉線計算22式中:L4——抱桿拉線露出拉線綁扎點的高度,m;E1——拉線綁扎點塔身斷面的對角線距離,m。6.2.3.2
抱桿上拉線是由四根鋼絲繩及相應(yīng)卡具所組成。鋼絲繩的一端用卡具分別固定于已組塔段四根主材的上端。6.2.3.36.2.4
上拉線與塔身的連接點,一定要先在分段接頭處的水平材附近,或頸部K節(jié)點的連接板附近。承托系統(tǒng)的布置承托繩的長度L承托計算22式中:L3——抱桿底與承托繩綁扎點的高差,m;E2——承托繩綁扎點塔身斷面的對角線距離,m。承托系統(tǒng)(亦稱下拉線)由承托鋼繩、平衡滑車、卡具和手板葫蘆等組成。承托系統(tǒng)示意圖如圖6-5所示。圖6-5
承托系統(tǒng)示意圖1—塔段主材;2—承托鋼繩;3—平衡滑車;4—抱桿;5—墊木;6—麻袋96E1L拉線L240.5E2L承托L23E1L拉線L240.5E2L承托L230.5SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書下拉線由兩根鋼繩穿越各自的平衡滑車,其端頭直接纏繞在已組塔段主材的上端,用U形環(huán)固定。也可以通過專用夾具固定于鐵塔主材上。下拉線在已組塔段上的固定點,一定要選擇在鐵塔接頭處的水平材附近,或者頸部的K節(jié)點附近。為了保持抱桿根部處于鐵塔結(jié)構(gòu)中心,應(yīng)盡可能使承托系統(tǒng)的兩分肢拉線及手扳葫蘆為等長。兩平衡滑車根據(jù)吊物位置可以前后或左右布置。當(dāng)被吊構(gòu)件在塔的左右側(cè)起吊時,平衡滑車應(yīng)布置在抱桿的左、右方向,前、后側(cè)起吊時,平衡滑車應(yīng)布置在抱桿的前、后方向,即前、后布置方式。采取這樣的布置方式,在起吊過程中可使抱桿的下拉線受力接近均勻,還可防止抱桿在提升過程中其底部沿平衡滑車滑動。6.2.5
起吊繩的布置單吊組塔時,起吊繩是由被吊構(gòu)件經(jīng)朝天滑車、腰滑車、地(或底)滑車引到牽引設(shè)備間的鋼絲繩。雙吊組塔時,起吊繩在地滑車之后還應(yīng)通過平衡滑車。單吊組塔時,起吊繩必須與牽引繩分開,牽引磨繩不能直接與塔材連接。雙吊組塔時,起吊繩與牽引繩通過平衡滑車相連接。起吊繩的規(guī)格,應(yīng)按每次最大受力工況來選取。6.2.6
牽引設(shè)備的布置絞磨應(yīng)盡可能順線路或橫線路方向設(shè)置。距塔位的距離一般應(yīng)不小于1.2倍塔高。牽引設(shè)備盡可能設(shè)在平坦地帶。牽引機手應(yīng)能觀測到起吊構(gòu)件的操作。6.2.7
攀根繩和控制繩的布置綁扎在被吊塔片下端的繩為攀根繩。當(dāng)被吊塔片重量超過500kg時,必須選用鋼繩。其作用是控制被吊塔片不與已組塔段相碰。綁扎在被吊塔片上端的繩習(xí)慣稱為控制大繩,通常選用16~20的棕繩。其作用是調(diào)整被吊構(gòu)件的位置及協(xié)助塔上操作人員就位時對孔找正。在正常起吊構(gòu)件中,控制大繩不受力,處于備用狀態(tài)。攀根繩的受力大小,對抱桿拉線系統(tǒng)及承托系統(tǒng)的受力有較大影響。而攀根繩與地面夾角的大小,直接影響著自身的受力,一般要求夾角不大于45°。攀根繩一般只有一根,用V形鋼繩套與被吊塔片相連接。攀根繩必須連在V形套的頂點處。控制大繩一般用兩根,分別綁于被吊塔片兩側(cè)主材上端。當(dāng)塔片較寬,為協(xié)助塔片就位,也可以用4根,兩根綁在主材上端,兩根綁在主材下端。6.2.8
地滑車(或底滑車)和腰滑車腰滑車是為了減少抱桿所受軸向壓力以及避免牽引繩與塔段或抱桿相碰所設(shè)置的一種轉(zhuǎn)向裝置。每根牽引繩都應(yīng)有自己的腰滑車,不可共用。一般情況下,腰滑車應(yīng)布置在已組塔段上端接頭處(起吊構(gòu)件對側(cè))的主材上。固定腰滑車的鋼繩套越短越好,以增大牽引繩與抱桿軸線間的夾角,從而減少抱桿所受的水平力。地滑車是將通過內(nèi)部腰滑車的牽引繩引向塔外,直至絞磨。若為雙吊組塔時,兩條起吊繩引至塔外后應(yīng)穿過平衡滑車后與牽引繩相連接。6.2.96.2.9.1
腰環(huán)內(nèi)拉線抱桿提升過程中,采用上下兩副腰環(huán)以穩(wěn)定抱桿,使抱桿始終保持豎直狀態(tài);采用單腰環(huán)時,抱桿頂部應(yīng)設(shè)臨時拉線控制。6.2.9.26.2.9.3增大。6.2.9.46.2.9.5
腰環(huán)與抱桿接觸處應(yīng)設(shè)置滾輪,以利抱桿順利提升。同一根抱桿,上下兩副腰環(huán)間的垂直距離,一般應(yīng)保持在3m以上,抱桿越長,垂直距離也應(yīng)上腰環(huán)應(yīng)布置在已組塔身的最上端,下腰環(huán)應(yīng)布置在相應(yīng)抱桿根部最終提升的位置。腰環(huán)一般用棕繩固定在已組塔段主材上。
97中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路6.2.106.2.10.16.2.10.2
塔腿組立使用地腳螺栓式基礎(chǔ)的鐵塔,應(yīng)首先將鐵塔腿組立好,以便固定抱桿,再進行塔片吊裝作業(yè)。塔腿組立一般有兩種方法:(1)分件組裝法,即先立主材而后逐一裝輔材的方法。該法適用于塔腿較重,根開較大的鐵塔;需用工器具較少,適用于山區(qū)地形。(2)半邊塔腿整體組立方法。該法適用于地形平坦的樁位,使用工具較多。6.2.10.3
分件組裝塔腿的方法:(1)先將鐵塔腳底座置放在基礎(chǔ)上用地腳螺栓固定好。然后將塔腿主材下端與底座立板連上一個螺栓,利用此螺栓作為起立塔腿主材的支點。(2)使用叉桿將主材立起,將主材與底板相連的螺栓全部裝上,并打好臨時拉線。用同樣的方法組立其余三根主材。6.2.116.2.11.1
豎立抱桿豎立抱桿之前,應(yīng)作好如下準備工作:(1)將運到現(xiàn)場的各段抱桿按順序組合起來并進行調(diào)整,使其成為一個完整而正直的整體。連接螺栓應(yīng)擰緊。(2)將提升抱桿用的腰環(huán)套在抱桿上。(3)將朝天滑車、朝地滑車、承托系統(tǒng)平衡滑車等裝在抱桿上,把各部連接螺栓及止動螺栓擰緊。(4)將起吊鋼繩穿入朝天滑車。(5)將抱桿臨時拉線(上拉線)與抱桿頭部連接。6.2.11.2
利用塔腿豎立內(nèi)拉抱桿:(1)豎立抱桿時,抱桿根應(yīng)用攀根繩控制,使抱桿慢慢移向塔身內(nèi)。(2)當(dāng)抱桿立至80°時,停止?fàn)恳?,在塔腿上方收緊抱桿拉線達到抱桿立正的目的。同時將抱桿拉線固定于塔腿主材上。(3)抱桿立正后,利用抱桿腰環(huán)及套繩調(diào)正抱桿。然后拆除立抱桿的牽引繩索。6.2.11.3
抱桿豎立后,還應(yīng)完成如下工作:(1)將塔腿的開口面輔助材補裝齊全并擰緊螺栓。(2)將上拉線及承托系統(tǒng)固定在塔腿的規(guī)定位置上。(3)如抱桿夠高時,可作吊裝構(gòu)件準備;如抱桿不夠高時,則準備提升抱桿。6.2.126.2.12.1
提升抱桿提升抱桿的布置一般有兩種方式:一種是利用原有的起吊索具,另一種是另外準備一套抱桿提升索具。兩種方式均可滿足提升抱桿的需要。6.2.12.2
提升抱桿的布置:(1)將提升抱桿的提升鋼繩的一端綁扎在已組塔段上端的主材節(jié)點處。(2)反向腰滑車應(yīng)布置在已組塔段上端與提升鋼繩綁扎點成對角,且與之對稱的一側(cè)。如此,抱桿可在提升中始終處在鐵塔結(jié)構(gòu)中心。(3)地滑車應(yīng)位于腰滑車的下方基礎(chǔ)邊。6.2.12.3
提升抱桿的操作步驟如下:(1)綁好上腰環(huán)及下腰環(huán),使抱桿直立在鐵塔結(jié)構(gòu)中心位置。(2)將4根上拉線由原綁扎點解下,提升到新的綁扎位置上予以固定。一般情況下,上拉線應(yīng)固定在已組塔段各主材最上端的節(jié)點處,各拉線固定方式應(yīng)相同,拉線呈松弛狀態(tài)。(3)將提升鋼絲繩從已組塔段最上端綁扎點經(jīng)朝地滑車、反向腰滑車、地滑車至絞磨。(4)啟動絞磨及牽引繩(即提升鋼繩),使抱桿提升一個小高度,解去原抱桿受力狀態(tài)下的承托系統(tǒng)。(5)繼續(xù)啟動絞磨使抱桿逐步升高至預(yù)定位置。98SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書(6)將4條承托繩串聯(lián)手扳葫蘆后固定于已組塔段主材頂端的上拉線綁扎點之下,收緊承托繩使受力一致。(7)由4人登塔調(diào)整抱桿上拉線,使抱桿達到所需要的傾斜度,然后收緊4條上拉線并固定之。(8)松開上下腰環(huán)。(9)拆去提升抱桿的工器具,為起吊塔片做好準備。6.2.12.4
抱桿提升高度的控制:(1)抱桿提升高度,既要方便塔片就位,又要使上拉線及承托繩受力較小。(2)一般經(jīng)驗是:塔片就位時,抱桿頂高出被吊構(gòu)件吊點位置約3m為適當(dāng)。(3)抱桿伸出已組塔體的高度不得超過抱桿長度的2/3。6.2.12.5
抱桿傾斜度的控制:(1)應(yīng)盡量使抱桿頂?shù)你U垂線接近于塔片就位點。(2)一般經(jīng)驗是:抱桿與鉛垂線的夾角應(yīng)小于5°。6.2.12.6
鐵塔側(cè)向斷面尺寸較小時,僅用腰環(huán)不能確保抱桿提升的穩(wěn)定性,此時,應(yīng)在抱桿頂端增加順線路的落地臨時拉線。6.2.136.2.13.1
構(gòu)件的綁扎構(gòu)件的綁扎包括三項內(nèi)容:(1)吊點鋼繩與構(gòu)件的綁扎。(2)對需要進行補強的構(gòu)件進行補強綁扎。(3)攀根繩及控制大繩在構(gòu)件上的綁扎。6.2.13.2
吊點繩系以鋼絲繩組成的V形繩套。構(gòu)成V形的兩肢可以是一根鋼繩也可以是兩根鋼繩。在V形套的頂點穿一只卸扣,其上端與起吊繩相連。6.2.13.3
吊點鋼繩在構(gòu)件上的綁扎位置,必須位于構(gòu)件的重心以上;綁扎后的吊點繩中點或其合力線,應(yīng)位于構(gòu)件的中心線上,以保持起吊過程中構(gòu)件平穩(wěn)上升。6.2.13.4
吊點鋼繩的兩端應(yīng)綁扎在被吊構(gòu)件的兩根主材的對稱節(jié)點處,以防滑動。該節(jié)點距塔片上端的距離應(yīng)小于塔片長度的40%。吊點繩呈等腰三角形,其頂點高度不小于塔身寬度的1/2,以保證吊點繩夾角不大于90°。6.2.13.5
直線塔的塔身及塔頭中導(dǎo)線橫擔(dān)吊裝時,一般均應(yīng)綁扎補強圓木(吊點薄弱時,在吊點間加補強木;根部薄弱時,在塔片底部加補強木)。其梢徑不小于100,長度視構(gòu)件長度而定。補強木與被吊構(gòu)件間的綁扎可利用吊點繩纏繞后再用U形環(huán)聯(lián)接;也可用單獨的9鋼繩或8號鐵線纏繞固定。6.2.13.6
長橫擔(dān)的吊點繩及補強方式,如圖6-6所示。圖6-6
長橫擔(dān)的吊點繩及補強示意圖(a)長橫擔(dān)吊點繩示意圖;(b)補強方式示意圖1—起吊繩;2—吊點繩;3—補強圓木;4—橫擔(dān);5—滑車;6—鋼絲繩吊套6.2.13.7
攀根繩應(yīng)綁扎在構(gòu)件最下端的主材節(jié)點處,一般相似于吊點繩的綁扎,由一根繩操作。當(dāng)構(gòu)件較寬(如橫擔(dān))時,則由兩根繩操作。99中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路6.2.13.8
控制繩一般為兩根16白棕繩,分別綁扎在構(gòu)件兩側(cè)最上端的主材節(jié)點處。長橫擔(dān)的攀根繩同時作為控制繩使用。6.2.146.2.14.1
構(gòu)件的吊裝構(gòu)件吊裝前應(yīng)做好如下準備工作:(1)對于分段接頭處無水平材的已組塔段,應(yīng)安裝臨時水平材。(2)已組塔段的各種輔材必須安裝齊全。(3)已組塔段的連接螺栓應(yīng)擰緊。(4)塔片上端水平材處綁一根小圓木,以避免吊點繩與水平材(角鋼)互相磨傷。(5)對于待吊塔片的大斜材接至下一段的主材上的聯(lián)接方式應(yīng)作如下補強措施:吊塔片之前,應(yīng)在主材下端綁兩根木杠接長主材,防止大斜材著地受彎變形。塔片完全離地后拆除木杠。(6)構(gòu)件吊裝前,攀根繩應(yīng)收緊。6.2.14.2
構(gòu)件(被吊構(gòu)件,下同)起吊過程中的操作要點:(1)構(gòu)件開始起吊,攀根繩應(yīng)收緊,控制繩完全放松。起吊過程中,在保證構(gòu)件不碰已組塔段的原則下,盡量松出攀根繩以減少各部索具受力。(2)構(gòu)件開始起吊,構(gòu)件著地的一端,應(yīng)設(shè)專人看護,以防塔材受力變形。(3)構(gòu)件離地面后,應(yīng)暫停起吊,進行一次全面檢查,檢查內(nèi)容包括:1)牽引設(shè)備的運轉(zhuǎn)是否正常。2)各綁扎處是否牢固。3)各處的錨樁是否牢固。4)各處的滑輪是否轉(zhuǎn)動靈活。5)已組塔段在受力后有無變形。(4)構(gòu)件上端吊至與已組塔段相平時,塔上人員應(yīng)密切監(jiān)視構(gòu)件起吊情況,嚴防構(gòu)件掛住塔身。塔上作業(yè)人員不宜超過4人,其中一人為塔上作業(yè)組長,負責(zé)與地面現(xiàn)場指揮人取得聯(lián)系,協(xié)調(diào)塔上人員工作,做到密切配合,步調(diào)統(tǒng)一。(5)構(gòu)件下端吊至超過已組塔段上端時,應(yīng)暫停牽引,由塔上作業(yè)組長指揮慢慢松出攀根繩;構(gòu)件主材對準已組塔段主材時,慢慢松出牽引繩,直至就位。(6)塔上作業(yè)人員應(yīng)分清內(nèi)外鐵,用手拉動斜材,調(diào)整主材位置。固定主材時,先穿上尖扳手,再連一個螺栓。在主材往下落時,應(yīng)先到位的主材先就位,后到后就位。兩主材都就位后,安裝并擰緊全部接頭螺栓。裝主材接頭螺栓時,應(yīng)先兩頭,后中間。(7)構(gòu)件就位且接頭螺栓安裝完畢,即可松出起吊繩及吊點繩。然后,安裝斜材及水平材。(8)解開攀根繩、控制繩及補強木,準備另側(cè)塔片及以上塔段的吊裝。6.2.14.3
地線支架的吊裝:(1)地線支架的吊裝,應(yīng)根據(jù)抱桿的高度及塔型特點選擇不同的吊裝方法:一是整體垂直吊裝,二是整體水平吊裝,三是分片水平吊裝。(2)整體垂直吊裝:在不提升抱桿的情況下仍能滿足直接吊裝支架要求時,可利用抱桿垂直起吊整段地線支架,直至就位完成。(3)整體水平吊裝:地線支架較輕,抱桿高度不能滿足垂直起吊地線支架,但可以滿足平放在已裝橫擔(dān)上的高度要求時,可采取整體水平起吊,使支架平放于橫擔(dān)上平面上,裝好里側(cè)連接板間的一個螺栓,以此螺栓為回轉(zhuǎn)軸,由塔上作業(yè)人員抬起,直至外側(cè)連接板上的螺栓裝好為止。(4)分片水平吊裝:地線支架較重時,可以分前后兩個側(cè)面水平吊裝。先吊裝一個側(cè)面至橫擔(dān)上平面上,對準方位,塔上人員將其扶起,安裝支架與橫擔(dān)間的連接螺栓并擰緊。兩個側(cè)面就位后,由下至上安裝輔助斜材,直至裝齊并擰緊全部螺栓。100SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書6.2.14.4
鐵塔橫擔(dān)的吊裝:(1)導(dǎo)線橫擔(dān)較重,不能隨塔身同段吊裝,通常利用已安裝好的地線支架分片吊裝。(2)將橫擔(dān)分成前后兩片在地面組裝,轉(zhuǎn)角外側(cè)的跳線橫擔(dān)應(yīng)同時組裝,并隨掛兩片之間的水平材。橫擔(dān)較輕時,可將橫擔(dān)(指一相導(dǎo)線用)整體地面組裝后起吊。(3)現(xiàn)場布置時應(yīng)注意:1)根據(jù)橫擔(dān)的長度和重心位置不同,在地線支架的適當(dāng)位置(應(yīng)當(dāng)是節(jié)點處)懸掛起吊滑車。2)在地線支架和塔身連接處懸掛轉(zhuǎn)向滑車,塔腳底座和基礎(chǔ)連接處安置地滑車,均為3t開口。3)將牽引繩通過滑車后和橫擔(dān)綁扎的吊點繩相連。4)橫擔(dān)(指一個立面)兩端各掛一根16棕繩,作起吊控制及攀根繩,以利橫擔(dān)就位時調(diào)整。(4)鐵塔橫擔(dān)吊裝的操作要點是:1)吊裝過程中收緊攀根繩,使橫擔(dān)上的角鐵離開已組塔身0.2~0.3m。2)當(dāng)橫擔(dān)吊至設(shè)計位置后應(yīng)暫停牽引,利用控制繩使橫擔(dān)主材(包括上、下)與塔身聯(lián)板(或主材)對準孔位,安裝連接螺栓并擰緊材制。3)第一片橫擔(dān)就位后,應(yīng)將橫擔(dān)與塔身連接的水平材裝上,使橫擔(dān)立面處于穩(wěn)定狀態(tài)。4)第二片橫擔(dān)就位后,應(yīng)自里向外(塔身中心為里,掛導(dǎo)線處為外)按順序組裝輔助斜材。先下平面,后上平面。6.2.14.5
構(gòu)件吊裝過程中的注意事項:(1)現(xiàn)場工作人員特別是塔上作業(yè)人員要密切配合,統(tǒng)一指揮統(tǒng)一成功。(2)主材接頭螺栓安裝完畢,側(cè)面的必要斜材已安裝,構(gòu)件已基本組成整體,方準登塔進行拆除起吊繩、攀根繩、控制繩等作業(yè)。(3)控制繩解開后,可將其直接綁在起吊繩的下端。放松起吊繩時,利用控制繩將起吊繩拉至下一吊裝構(gòu)件處進行綁扎工作。(4)塔段的正側(cè)面輔助材全部組裝完成方準提升抱桿。6.2.156.2.15.1
拆除抱桿鐵塔吊裝完成后,即可開始拆除抱桿??衫盟^頂端作支持點拆除抱桿。支持點應(yīng)選在鐵塔主材的節(jié)點處,該節(jié)點處的螺栓應(yīng)全部擰緊。6.2.15.2
抱桿拆除的操作程序:(1)拆除抱桿上拉線,啟動絞磨。(2)將抱桿提升到適當(dāng)高度,絞磨停止?fàn)恳?,拆除承托系統(tǒng)。(3)再啟動絞磨,回松牽引繩使抱桿徐徐下降,同時拉緊抱桿根部棕繩,將抱桿引出塔身之外。(4)當(dāng)抱桿頭部降至橫擔(dān)處滑車以下時,用棕繩套將抱桿上部與牽引繩圈住,以防抱桿翻轉(zhuǎn)。(5)繼續(xù)回松牽引繩使抱桿落地,抱桿根部棕繩要始終拉緊。(6)拆除牽引繩及塔上其他吊裝工具。7
質(zhì)量控制措施及檢驗標準工程的質(zhì)量要求是達到100%的優(yōu)良率,施工中必須嚴格按《110kV~500kV架空送電線路施工及驗收規(guī)范》及《10kV~500kV輸變電及配電工程質(zhì)量驗收與評定標準(第1部分:輸電工程)》施工。各工序要認真檢查組裝質(zhì)量,發(fā)現(xiàn)問題及時處理,不合格不得進入下一道工序施工。7.17.1.17.1.27.1.3
質(zhì)量控制措施現(xiàn)場構(gòu)件應(yīng)分類、分段號擺放。不得用角鋼作其他承力使用,如:當(dāng)撬棍等。防止構(gòu)件彎曲變形。如因運輸造成局部鍍鋅層磨損時(小于100mm2),應(yīng)噴防銹漆,進行防銹處理。噴前應(yīng)將磨損處
101中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路清洗干凈并保持干燥。7.1.47.1.57.1.67.1.6.17.1.6.27.1.6.37.1.7
檢查構(gòu)件的彎曲度,角鋼的彎曲度不應(yīng)超過相應(yīng)長度的1/800。螺栓防盜栓槽統(tǒng)一朝上。螺栓連接構(gòu)件組裝規(guī)定:鐵塔各構(gòu)件的組裝應(yīng)牢固,交叉處有空隙者,應(yīng)按設(shè)計圖紙加裝對應(yīng)厚度的墊片。螺栓應(yīng)與構(gòu)件面垂直,螺栓頭平面與構(gòu)件不應(yīng)有空隙。螺母擰緊后螺桿露出螺帽的長度,對單螺母不應(yīng)小于兩個螺距,對雙螺母可與螺母相平。螺栓數(shù)量不得缺少,規(guī)格必須符合設(shè)計圖紙要求,穿向應(yīng)符合本工程的統(tǒng)一規(guī)定和鐵塔圖紙會審紀要的要求。7.1.87.1.9
螺桿與螺母的螺紋有滑牙或螺母棱角磨損以至扳手打滑的螺栓必須更換。鐵塔組裝有困難時,嚴禁強行組裝,應(yīng)查明原因。對于有誤的板件應(yīng)劃印,逐件登記交材料站退回廠家處理。7.1.10
塔材需切角時,其邊距尺寸應(yīng)滿足表7-1的要求,切角后應(yīng)涂漆防銹。表7-1
塔材切角邊距尺寸7.1.11
地面組裝完成以后,應(yīng)對組裝質(zhì)量做一次全面檢查,如發(fā)現(xiàn)有質(zhì)量缺陷應(yīng)按規(guī)定處理后再轉(zhuǎn)入下一道工序。其內(nèi)容包括:(1)構(gòu)件是否齊全,缺少的構(gòu)件是送料缺件,還是原構(gòu)件加工尺寸錯誤裝不上。(2)各部位尺寸是否正確,特別是分段連接處包鋼是否正確。(3)組裝的構(gòu)件有無歪扭和彎曲,是否有空隙未加墊圈。(4)螺栓是否齊全,緊固。(5)鍍鋅層有無剝落。7.1.127.1.137.1.147.1.157.1.167.1.177.1.17.1
鐵件與鋼絲繩的接觸面必須墊麻袋等軟物,保護鍍鋅層。斷面較大或主材單薄的塔片必須用圓木補強。節(jié)點螺栓規(guī)格必須一致,在復(fù)緊全塔螺栓時應(yīng)檢查。腳釘?shù)膹濄^應(yīng)一致向上,由塔腿沿主材向上望,逐個調(diào)整,方向一致后再緊固螺栓。四角主材節(jié)點彎曲是否超標,直線塔k節(jié)點主材是否有彎曲,整基塔的傾斜,均要一一檢查處理。嚴格執(zhí)行三級驗收制度。項目施工隊鐵塔組立完后,進行自檢、消缺、填寫自檢記錄表,自檢后的塔位填寫驗收申請報項目部進行驗收。7.1.17.27.1.17.37.1.17.47.1.18
項目部驗收后,填寫缺陷表交項目隊進行消缺,消缺后再進行復(fù)檢并填寫驗收記錄表。項目部驗收合格后,填寫驗收申請報公司進行驗收,并組織項目隊對公司驗收意見進行消缺。完成三級驗收并消缺后,由項目部報工程監(jiān)理部進行鐵塔驗收。各立塔隊必須對每基塔立好后及時檢修,及時發(fā)現(xiàn)質(zhì)量問題,在其余樁位的立塔施工改進施工工藝,以保證質(zhì)量控制。102螺栓規(guī)格(mm)M12螺栓規(guī)格(mm)M12M16M20M24螺孔直徑(mm)最小邊距(mm)13.51817.52321.52825.533切角邊距示意圖:SDXL-ZW-08
內(nèi)拉線懸浮抱桿分解組立鐵塔作業(yè)指導(dǎo)書7.2
質(zhì)量控制表表7-2
質(zhì)量控制表7.3
檢驗標準質(zhì)量檢驗按《10kV~500kV輸變電及配電工程質(zhì)量驗收與評定標準
第1部分:輸電工程》中的Q/CSG表1-6.3.1、Q/CSG表1-7.0.8、Q/CSG表1-6.3.2、Q/CSG表1-6.3.3、Q/CSG表1-B.12、Q/CSG表1-B.13、Q/CSG表1-B.15規(guī)定執(zhí)行。103序號控制點控制方式序號控制點WHS1自立式鐵塔組立●注:W:見證點;H:停工待檢點;S:旁站點。序號控制點控制方式序號控制點WHS1自立式鐵塔組立●注:W:見證點;H:停工待檢點;S:旁站點。中國南方電網(wǎng)有限責(zé)任公司電網(wǎng)建設(shè)施工作業(yè)指導(dǎo)書第1部分:輸電線路附件1安全施工作業(yè)票編碼:SDXL-ZW-08-01/01104工作時間工作地點技術(shù)員現(xiàn)場安全員工作時間工作地點技術(shù)員現(xiàn)場安全員現(xiàn)場負責(zé)人安全風(fēng)險分析及控制措施序號危害名稱風(fēng)險種類風(fēng)險等級風(fēng)險控制措施1人員打錨大錘脫手失誤物體打擊□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊。□抱桿有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。2清理塔材滑動或墜落物體打擊□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施。□人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高。□山坡上組裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固。□吊裝方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。3抬運重物刮碰傷人割傷□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器。□特種作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗。□施工人員應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面。□清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高。□山坡上組裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺??!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。4抬運工具質(zhì)量不合格碰撞□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面。□清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉。□運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。□重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查。□抱桿組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少。□起立抱桿必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺??!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。5不方便搬運物品的通道物體打擊□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩模瑧?yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺??!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施。□分片組裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。6抱桿質(zhì)量不合格物體打擊□中等風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊。□抱桿有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺??!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固。□吊裝方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。7拉線收放控制失誤物體打擊□中等風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗。□施工人員應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺?。□組裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。8構(gòu)件失穩(wěn)致登高墜落墜落□中等風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩模瑧?yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。9場地不平整,塔片墊物失穩(wěn)或塔片滑動夾傷□可接受的風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗。□施工人員應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施。□人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面。□清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊。□抱桿有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施。□嚴禁將手指伸入螺孔找正?!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。10組裝人員將手指伸入螺孔找正剪切□可接受的風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。□重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少。□起立抱桿必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高。□山坡上組裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施。□嚴禁將手指伸入螺孔找正?!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。11地面組裝豎立的塔片支撐不牢物體打擊□可接受的風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽。□高處作業(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施。□人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉。□運輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查。□重大物件不得直接用肩扛運;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊。□抱桿有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺??!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。12地面組裝帶鐵固定不牢物體打擊□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽。□高處作業(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面。□清理工具或塔材,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮?!跤暄┖筇н\物件時,應(yīng)有防滑措施。□抱桿組立前應(yīng)進行外觀檢查。□抱桿組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施。□嚴禁將手指伸入螺孔找正?!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施。□分片組裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定?!鯂栏癜词┕ぜ夹g(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。13未按技術(shù)方案*起吊塔片物體打擊□中等風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽。□高處作業(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施?!跞斯ご驑稌r,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施?!醣U組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作?!醣U四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高。□山坡上組裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺?。□組裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺帽應(yīng)出扣;自由端朝上時,應(yīng)綁扎牢固?!醯跹b方案和現(xiàn)場布置應(yīng)符合施工技術(shù)措施的規(guī)定。□嚴格按施工技術(shù)措施要求選用合格工器具,工器具不得超規(guī)定使用。14人員缺乏經(jīng)驗站位失誤物體打擊□低風(fēng)險現(xiàn)場作業(yè)應(yīng)嚴格執(zhí)行相關(guān)安全規(guī)程及安全技術(shù)措施,并重點關(guān)注但不限于以下措施:□進入施工現(xiàn)場人員必須戴安全帽?!醺咛幾鳂I(yè)人員必須使用安全帶,組立(拆)高塔必須使用速差自控制器及安全自鎖器?!跆胤N作業(yè)人員如高處作業(yè)、機動絞磨操作員等必須取證上崗?!跏┕と藛T應(yīng)熟悉施工區(qū)域內(nèi)的環(huán)境,作業(yè)前,先清除附近障礙物或采取其他措施。□人工打樁時,打錘人不得戴手套,并應(yīng)站在扶釬人的側(cè)面?!跚謇砉ぞ呋蛩?,應(yīng)由上往下搬動,不得強行抽拉?!踹\輸用的工器具應(yīng)牢固可靠,每次使用前應(yīng)進行認真檢查?!踔卮笪锛坏弥苯佑眉缈高\;抬運時應(yīng)步調(diào)一致、同起同落,并應(yīng)有人指揮。□雨雪后抬運物件時,應(yīng)有防滑措施。□抱桿組立前應(yīng)進行外觀檢查?!醣U組裝應(yīng)正直,連接螺栓的規(guī)格必須符合規(guī)定,并應(yīng)全部擰緊?!醣U有下列情況之一者嚴禁使用:①金屬抱桿,整體彎曲超過桿長的1/600,局部彎曲嚴重、磕癟變形、表面嚴重腐蝕、裂紋或脫焊;②抱桿脫帽環(huán)表面有裂紋、螺紋變形或螺栓缺少?!跗鹆⒈U必須有人統(tǒng)一指揮,四側(cè)臨時拉線應(yīng)均勻收放并由技工操作。□抱桿四周拉線綁扎工作應(yīng)由技工擔(dān)任,未綁扎固定前不得登高?!跎狡律辖M裝塔身時,墊高物應(yīng)穩(wěn)固,且有防塔片滑動的措施?!鯂澜麑⑹种干烊肼菘渍艺!踅M裝斷面寬大的塔身時,在豎立的構(gòu)件未連接牢固前,應(yīng)采取臨時固定措施?!醴制M裝鐵塔時,帶鐵應(yīng)能自由活動,螺
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 煤礦挖機租賃合同范例
- 商品購買合同范例簡易
- 工程保潔設(shè)備合同范例
- 《生活變變變:3 家鄉(xiāng)交通的變遷》教學(xué)實錄-2023-2024學(xué)年四年級下冊綜合實踐活動滬科黔科版
- 裝修主材合作合同范例
- 購買日用品合同范例
- 井字架合同范例
- 房屋銷售置換合同范例
- 2025項目預(yù)咨詢服務(wù)合同范本
- 2025年南昌貨運從業(yè)資格證摸擬考試試題答案
- 2024社區(qū)市民學(xué)校工作計劃社區(qū)市民教育工作計劃
- 抗生素使用及控制制度
- 2024年公文寫作基礎(chǔ)知識競賽試題庫及答案(共130題)
- 信息安全教育培訓(xùn)管理制度(3篇)
- 數(shù)據(jù)管理制度完整
- 電梯改造維修合同范例
- 2024年醫(yī)院客服中心年終工作總結(jié)范例(3篇)
- 雄安新區(qū)容東片區(qū)地下空間專項規(guī)劃-ECADI
- 自然辯證法論述題146題帶答案(可打印版)
- 2024年急診科護理計劃和總結(jié)
- 公司年度培訓(xùn)總結(jié)匯報
評論
0/150
提交評論