蕭縣EPC項(xiàng)目施工組織設(shè)計
導(dǎo)讀:就愛閱讀網(wǎng)友為您分享以下“蕭縣EPC項(xiàng)目施工組織設(shè)計”資訊,希望對您有所幫助,感謝您對92to的支持!
蕭縣陳圈東路一期、陳圈西路、興業(yè)路二期、污
水泵站、黃圣路一期、徐山路、前堤河建設(shè)工程總承包(EPC)
施工組織設(shè)計
編制:
審核:
批準(zhǔn):
施工單位:合肥市公路橋梁工程有限責(zé)任公司
編制日期:2017年6月1日
1目錄
一、編制依據(jù)和工程概況·························································2
二、項(xiàng)目部建設(shè)·····································································4
三、施工進(jìn)度········································································5
四、主要施工方案··································································8
4.1測量放線······································································8
4.2給排水工程····································································8
4.3路基工程·····································································25
4.4水泥穩(wěn)定碎石施工方案和工藝··········································29
4.5透層、封層、粘層·························································34
4.6瀝青砼面層施工方案及工藝··············································35
4.7路緣石、人行道道板安裝················································44
4.8橋梁工程·····································································46
4.9照明工程·····································································53
4.10交通工程···································································60
4.11電力排管施工·····························································70
4.12綠化工程施工·····························································73
4.13涵洞工程施工·····························································81
4.14河道工程施工·····························································83
4.15水穩(wěn)拌和站建設(shè)··························································87
4.16主要工程施工工藝框圖·················································92
2五、確保工程質(zhì)量控制體系及技術(shù)組織措施·······························98
六、確保安全生產(chǎn)的技術(shù)組織措施··········································109
七、確保工期的技術(shù)組織措施················································117
八、確保文明施工的技術(shù)組織措施··········································122
九、投入的主要施工機(jī)械、設(shè)備·············································124
投入本項(xiàng)目的主要施工機(jī)械設(shè)備表······································126投入本項(xiàng)目的試驗(yàn)和檢測儀器設(shè)備表·································127
十、投入的主要物資計劃······················································129十一、勞動力安排計劃·························································130
3一、編制依據(jù)和原則
1.1編制依據(jù)
1、本項(xiàng)目建設(shè)工程合同文件
2、本項(xiàng)目建設(shè)工程施工設(shè)計文件
3、《工程建設(shè)標(biāo)準(zhǔn)強(qiáng)制性條文》(城市建設(shè)部分)
4、《市政道路工程質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)》(CJJ1-2008)
5、《市政排水工程質(zhì)量檢驗(yàn)評定標(biāo)準(zhǔn)》(GB50268-2008)
6、《給水排水管道工程施工及驗(yàn)收規(guī)范》GB50268-2008
7、《公路路基施工技術(shù)規(guī)范》JTGF10-2006
8、《公路路面基層施工技術(shù)規(guī)范》JTJ034-2000
9、《公路瀝青路面施工技術(shù)規(guī)范》JTGF40-2004
10、《工程測量規(guī)范》GB50026-2007
11、《城市橋梁工程施工與質(zhì)量驗(yàn)收規(guī)范》CJJ2-2008
12、城市道路養(yǎng)護(hù)技術(shù)規(guī)范(CJJ36-2006)
13、《公路交通安全設(shè)施施工技術(shù)規(guī)范》JTGF71-2006
14、施工現(xiàn)場臨時施工用電技術(shù)規(guī)范(JGJ46-2005)
15、建筑機(jī)械使用安全技術(shù)規(guī)程(JGJ33-2001)
16、施工圖規(guī)定采用的規(guī)范
17、現(xiàn)場踏勘的施工環(huán)境及地理?xiàng)l件。
1.2編制原則
保質(zhì)、保量、按期完成本工程,按爭創(chuàng)優(yōu)質(zhì)質(zhì)量工程獎的原則編制。通過對施工環(huán)境進(jìn)行調(diào)查,制定出切實(shí)可行的施工方案。
2、工程概況
2.1工程位置與主要特點(diǎn)
本項(xiàng)目工程共分為5條道路、一座污水泵站及一條河道治理,具體如下:
1、陳圈東路市政工程,位于鳳山新區(qū)東起站前路,止于發(fā)展大道,道路全長1009.178米,規(guī)劃紅線24米,兩側(cè)綠化帶退讓各15米,雙向兩車道,道路等級為城市支路。
2、陳圈西路市政工程,位于鳳山新區(qū)西起站前路,東至龍騰大道,道路全
4長593米,規(guī)劃紅線24米,兩側(cè)綠化帶退讓各15米,雙向兩車道,道路等級為城市支路;
3、興業(yè)路二期市政工程,位于鳳山新區(qū),西起岱河路,東至鳳山路,道路全長1685.72米,規(guī)劃紅線36米,兩側(cè)綠化帶退讓各15米,雙向六車道,道路等級為城市次干道;
4、黃圣路一期市政工程,位于鳳山新區(qū),西起徐山路,東至龍騰大道,道路全長444.036米,規(guī)劃紅線24米,兩側(cè)綠化帶退讓各15米,雙向兩車道,道路等級為城市支路;
5、徐山路市政工程,位于鳳山新區(qū),北起興業(yè)路,南至濱湖路,道路全長932.042米,規(guī)劃紅線16米,兩側(cè)綠化帶退讓各5米,雙向兩車道,道路等級為城市支路;
6、前堤河治理,位于鳳山新區(qū),長4050米,寬50米;
7、污水泵站,位于鳳山新區(qū)、建筑尺寸為30m×35m,占地面積1050平方米。
二、項(xiàng)目經(jīng)理部建設(shè):
項(xiàng)目部位于蕭縣鳳山新區(qū),龍騰大道東側(cè),緊靠龍騰大道,交通極其方便。
1、項(xiàng)目部建設(shè)方案
我司接到業(yè)主的中標(biāo)通知書后,立刻按投標(biāo)承諾組建項(xiàng)目管理機(jī)構(gòu),由公司副總牽頭,協(xié)同項(xiàng)目經(jīng)理和總工對整個項(xiàng)目進(jìn)行了總體規(guī)劃。經(jīng)對現(xiàn)場調(diào)查,并爭得業(yè)主同意后,選定了項(xiàng)目部的位置。
項(xiàng)目部按工程建設(shè)需要進(jìn)行規(guī)劃,租用一套閑置三層辦公樓,辦公區(qū)和生活區(qū)分開。項(xiàng)目部辦公區(qū)設(shè)項(xiàng)目經(jīng)理室、項(xiàng)目副經(jīng)理室、總工程師室、工程部、計劃部、物資設(shè)備部、財務(wù)部、安質(zhì)部、辦公室、試驗(yàn)室辦公室、測量班、資料室、會議室、門衛(wèi)等。
項(xiàng)目部辦公房及庭院適合位置設(shè)置公司企業(yè)的標(biāo)語、項(xiàng)目部的文化宣傳口號等等。
2、辦公室主要布置
保證各職能辦公室能更好的完成各自的工作,在各職能辦公室內(nèi)必須上墻相應(yīng)的崗位職責(zé)牌及其圖表,如:會議室:布置總平面布置圖、施工進(jìn)度計劃圖和項(xiàng)目組織機(jī)構(gòu)圖等;工程技術(shù)部:布置總平面布置圖、施工進(jìn)度計劃圖、主要人
5員崗位職責(zé)牌等,其他各部門根據(jù)各自職能分別進(jìn)行。
3、駐地水、電布置
項(xiàng)目部駐地生活用水采用自來水;駐地用電主要采用當(dāng)?shù)鼐W(wǎng)電接入315KV變壓器。駐地用電必須符合《施工現(xiàn)場臨時用電安全技術(shù)規(guī)范》及其他用電安全規(guī)范的要求。用電采用TN-S系統(tǒng)(三相三線制),設(shè)專用保護(hù)零線(PE線),實(shí)行三級配電、兩級保護(hù)。總配電箱設(shè)過載、短路保護(hù)和漏電保護(hù)開關(guān),分配電箱設(shè)過載、短路保護(hù)開關(guān)箱做到設(shè)過載、短路保護(hù),做到一機(jī)一閘一漏電保護(hù)。各配電箱、開關(guān)箱均采用金屬制作,有門有鎖,專人管理,箱內(nèi)電器選用優(yōu)秀產(chǎn)品。干線架空或埋地敷設(shè),支線敷設(shè)符合要求。
1、配電箱應(yīng)設(shè)置室內(nèi)總配電箱和室外總配電箱、分配電箱、開關(guān)箱,實(shí)行分級配電,配電箱的設(shè)置與規(guī)格滿足規(guī)范要求,所有用電開關(guān)均需使用防爆開關(guān)。
2、用電設(shè)備配備有各自專用的開關(guān)箱,必須實(shí)行“一機(jī)一閘一漏”制。嚴(yán)禁用同一個開關(guān)器直接控制二臺及三臺以上用電設(shè)備。
3、用電線路、配電箱、用電設(shè)備必須由專業(yè)電工定期管理,定期檢修。
4、駐地安全文明及消防
1、我項(xiàng)目部對派駐工地的一切人員進(jìn)行教育,做好工程開工前文明施工技術(shù)交底;
2、項(xiàng)目部四周圍墻采用砌磚基礎(chǔ),通透式柵欄,圍墻做到封閉嚴(yán)密,完整牢固,美觀大方,圍墻內(nèi)外粉刷。在項(xiàng)目部大門口設(shè)立工程簡介牌,內(nèi)容為工程名稱、工程概況、建設(shè)單位、質(zhì)檢單位、監(jiān)理單位、設(shè)計單位、施工單位名稱。
3、建立消防組織,設(shè)立防火小組和義務(wù)消防隊,建立完善的消
防安全制度,對員工進(jìn)行消防安全教育,進(jìn)行定期和經(jīng)常性的防火檢查,及時消除火災(zāi)隱患,項(xiàng)目上成立消防領(lǐng)導(dǎo)小組,由項(xiàng)目經(jīng)理擔(dān)任組長,專職安全主任擔(dān)任副組長,項(xiàng)目安全員及各相關(guān)班組班長、其他項(xiàng)目管理人員擔(dān)任組員,項(xiàng)目上定期進(jìn)行消防安全教育。
三、總進(jìn)度計劃
開工日期:2017年6月1日,計劃竣工日期:2018年2月26日,總工期273日歷日。主要分部分項(xiàng)工程節(jié)點(diǎn)計劃:
6(一)、陳圈東路一期工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月3日;
2、管線工程:2017年6月4日~2017年10月4日;
3、道路工程:2017年7月1日~2017年12月31日;
4、橋涵工程:2017年6月9日~2017年11月29日;
5、照明工程:2017年12月1日~2018年1月31日;
6、景觀工程:2017年12月1日~2018年1月31日;
7、交通工程:2018年1月1日~2018年2月26日;
8、竣工驗(yàn)收:2018年2月27日~2018年2月28日;
(二)、陳圈西路工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月2日;
2、管線工程:2017年6月3日~2017年8月3日;
3、道路工程:2017年6月28日~2017年9月30日;
4、橋涵工程:2017年6月10日~2017年7月31日;
5、照明工程:2017年9月25日~2017年10月30日;
6、景觀工程:2017年10月1日~2017年11月20日;
7、交通工程:2017年10月1日~2011年11月5日;
8、竣工驗(yàn)收:2018年2月26日~2018年2月27日;
(三)、興業(yè)路二期工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月3日;
2、管線工程:2017年6月4日~2017年10月31日;
3、道路工程:2017年7月1日~2017年12月31日;
4、橋涵工程:2017年6月10日~2017年12月31日;
5、照明工程:2017年12月1日~2018年1月31日;
6、景觀工程:2017年11月20日~2018年2月22日;
7、交通工程:2018年1月1日~2018年2月26日;
8、竣工驗(yàn)收:2018年2月27日~2018年2月28日;
(四)、徐山路工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月3日;
72、管線工程:2017年6月4日~2017年9月30日;
3、道路工程:2017年7月1日~2017年11月30日;
4、橋涵工程:2017年6月15日~2017年10月15日;
5、照明工程:2017年11月15日~2018年1月10日;
6、景觀工程:2017年11月10日~2018年2月10日;
7、交通工程:2017年12月5日~2018年1月31日;
8、竣工驗(yàn)收:2018年2月25日~2018年2月26日;
(五)、黃圣路一期工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月2日;
2、管線工程:2017年6月3日~2017年8月31日;
3、道路工程:2017年7月1日~2017年9月30日;
4、照明工程:2017年9月15日~2017年10月31日;
5、景觀工程:2017年10月1日~2017年11月20日;
6、交通工程:2017年11月1日~2017年11月30日;
7、竣工驗(yàn)收:2018年2月24日~2018年2月25日;
(六)、發(fā)展大道污水泵站工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月2日;
2、地基與基礎(chǔ)工程:2017年6月3日~2017年8月31日;
3、主體結(jié)構(gòu)工程:2017年9月1日~2017年10月31日;
4、附屬構(gòu)筑物工程:2017年11月1日~2017年11月30日;
5、房屋建筑工程:2017年10月10日~2017年11月30日;
6、金屬結(jié)構(gòu)制作及安裝工程:2017年12月1日~2017年12月31日;
7、機(jī)電設(shè)備及安裝:2017年12月6日~2017年12月31日;
8、竣工驗(yàn)收:2018年2月23日~2018年2月24日;
(七)、前堤河市政工程
1、施工準(zhǔn)備:2017年6月1日~2017年6月5日;
2、河道開挖工程:2017年6月6日~2017年7月31日;
3、重力式漿砌塊石擋墻工程:2017年6月10日~2017年10月31日;
4、連鎖式生態(tài)護(hù)坡工程:2017年7月10日~2017年11月30日;
85、生態(tài)景觀綠化工程:2017年12月1日~2017年12月20日;
6、休閑步道工程:2017年12月21日~2018年1月20日;
7、竣工驗(yàn)收:2018年2月22日~2018年2月23日;
四、主要施工方案
4.1測量放線
在業(yè)主單位提供完整的導(dǎo)線點(diǎn)和水準(zhǔn)點(diǎn)后,組織技術(shù)人員對導(dǎo)線點(diǎn)、水準(zhǔn)點(diǎn)進(jìn)行閉合測量,確認(rèn)無誤后,引測/布置各單位工程導(dǎo)線控制網(wǎng)和水準(zhǔn)控制網(wǎng)。導(dǎo)線網(wǎng)允許偏差:邊長L/15000,角度閉合差±15”;水準(zhǔn)網(wǎng)允許偏差:±√12L。依據(jù)單位工程導(dǎo)線網(wǎng)測設(shè)各構(gòu)筑物定位線和溝槽開挖線,并標(biāo)出與管線沖突的地上、地下構(gòu)筑物位置,校對永久水準(zhǔn)點(diǎn),建立臨時水準(zhǔn)點(diǎn),測量管理線地面高程,以確定挖深。
4.2給排水工程
本工程給排水工程主要為雨水管、污水管、給水管道等。
4.2.1測量放線
(1)排水工程測量流程圖
定線測量高程控制測量
9
(2)根椐控制網(wǎng)放出主干管的中線,并在施工管段的起止端設(shè)置中樁,便于在施工過程中不斷用全站儀進(jìn)行監(jiān)控,保證管道的順直。同時根據(jù)中線分別設(shè)置開挖邊線、墊層、管座、管肩的邊樁,并利用邊樁用水準(zhǔn)儀分別標(biāo)記溝底、墊層面、流水位和管肩的高程。每一工序完成后應(yīng)立即通線進(jìn)行復(fù)測,及格后方可進(jìn)入下一工序。
(3)用紅外測距儀沿著主干管中線定出各檢查井的井心位置。再在井心依序放出開挖邊線、墊層、基礎(chǔ)、井身內(nèi)壁邊線,在各井旁設(shè)立施工水準(zhǔn)點(diǎn),并設(shè)立標(biāo)志牌分別標(biāo)記清楚各井的坑底、墊層、基礎(chǔ)、收口、雨水口及井環(huán)面高程,便于砌筑井身時使用。
(4)各個排水管井也利用全站儀(或通線)及水準(zhǔn)儀進(jìn)行施工監(jiān)控,方法與主干管井相同。
(5)由于排水管位于不同的里程段。所以排水管井施工前要復(fù)測上下標(biāo)段的流水位標(biāo)高或測量控制點(diǎn),根據(jù)管道坡度及長度進(jìn)行推算結(jié)果與施工圖相符后方可施工,否則應(yīng)立即知會設(shè)計人及監(jiān)理工程師。
4.2.2鋼筋混凝土管的施工方法:
(1)管溝開挖
10
①基坑坡度
根據(jù)現(xiàn)場挖取探坑鑒別土的類別為粉質(zhì)黏土,由于溝槽開挖以后,溝槽周邊會有機(jī)械行走施工,現(xiàn)場開挖基坑最陡不低于1:0.67放坡,當(dāng)槽深開挖深度大于
3.5米的,采用分層開挖斷面形式,分層平臺按照1米控制,開挖基坑最陡不低于1:0.67放坡。
②排水基坑土方開挖采用機(jī)械開挖?;拥拈_挖寬度,必須考慮以后各工序的操作方便和利于排水,基坑的寬度除能滿足結(jié)構(gòu)尺寸外,還應(yīng)有側(cè)面工作位寬度,并在確定的寬度彈放邊線。
③基底土經(jīng)自然沉降后,已有一定密實(shí)度和承載能力,不過溝槽開挖以后還要與相關(guān)部門聯(lián)合見證地基承載力是否能夠達(dá)到100Kpa,達(dá)到100Kpa方可進(jìn)行下道工序施工。管溝開挖后若遇淤泥小于60公分時,應(yīng)換填1:1砂石,并用平板夯,夯實(shí),密實(shí)度不小于95%,大于60公分時按照拋石擠瘀處理,然后再填碎石至管道基礎(chǔ)底部,再按照管道基礎(chǔ)施工。
④挖出的土方離基坑邊線1.5m以外堆放,堆放高度不超過1.5m,并修整臨時邊溝,以免雨水流入溝內(nèi)。
⑤機(jī)械挖槽應(yīng)保證槽底土壤結(jié)構(gòu)不被擾動和破壞,當(dāng)開挖至槽底高程以上大約20cm時,應(yīng)即停挖,待下一工序開工時再用人工清底。
⑥若管溝開挖后不能及時鋪砼墊層,則槽底30cm土應(yīng)暫不挖,以免被水泡軟土基。
(2)管道基礎(chǔ)施工、安管
①基坑開挖至設(shè)計標(biāo)高,溝槽底松木樁施打完成,用細(xì)木板條相連接固定,經(jīng)復(fù)測無誤后,經(jīng)業(yè)主與派駐現(xiàn)場監(jiān)理工程師驗(yàn)收合格后方可進(jìn)行基底墊層的施工。
②鋪好墊層后即放樣安裝管座模板?;A(chǔ)管座模板一般采用木模板或鋼木混合模板。
③平基模板安裝后灌筑平基砼。砼采用商品砼,平基砼在管底中線至兩側(cè)各20cm左右取平,其余留粗糙面以便和管座砼接合。砼強(qiáng)度達(dá)到5MPa才允許下管安裝。
④下管前要清理溝內(nèi)雜物,砼基面要清洗干凈,然后彈放管道中線,復(fù)核基
11面標(biāo)高。準(zhǔn)備工作做好后,才許下管。
⑤下管方法可以根據(jù)具體情況,以安全操作方便為原則,下管機(jī)械采用吊機(jī)。深基坑開挖的排水管要采用吊機(jī)下管。下管要有專人指揮,低速輕放。下管及安管應(yīng)自下游向上游進(jìn)行,承口向上游,下管到基礎(chǔ)后,分別由前向后推移,在管基上推移管道必須加木板墊,以免壓壞管基。。
⑥下管以后,應(yīng)將管渠排好,然后對線校正,要注意管內(nèi)流水位是否相平,不相平的應(yīng)墊平。
⑦雨水管口為柔性承插式時:采用橡膠圈接口,雨水管口為平口式時:采用1:2水泥砂漿及鋼絲網(wǎng)片抹帶,管口應(yīng)先鑿毛,施工完成后,并淋水養(yǎng)護(hù)不少于3d。
(3)鋼筋混凝土檢查井①施工均采用標(biāo)準(zhǔn)圖集06MS201-3,鋼筋混凝土井室,砼材料采用C25、S4,鋼筋混凝土蓋板,流槽為Mu7.5磚砌。
②施工前按設(shè)計要求放樣,放出井位中心點(diǎn)和澆筑位置,并復(fù)核基礎(chǔ)面高程、平面尺寸是否符合要求。③進(jìn)場鋼筋符合設(shè)計和規(guī)范要求。用于工程的鋼筋無節(jié)疤,不彎曲和沒有其它破損。鋼筋保持清潔,無銹蝕、銹屑、氧化皮、油、泥土、油漆、混凝土垢及任何可能影響混凝土與鋼筋間結(jié)合的其它材料。堆放鋼筋的場地上方要遮蓋,鋼筋放在木板和支墩上,離地凈距大于15cm。
④保持鋼筋保護(hù)層的墊塊用與現(xiàn)澆混凝土同等強(qiáng)度、顏色和配合比的混凝土制成。鋼筋的安放要求確保位置正確并牢固地固定,保護(hù)鋼筋位置的支托為同等鋼筋或相適應(yīng)的其他鋼制品。綁扎鋼筋的金屬絲為20~22#的軟鐵絲,所有鋼筋的交叉處均用軟鐵絲扎牢,其端頭彎入混凝土中。施工中先將直鋼筋切割到要求的長度,由經(jīng)驗(yàn)豐富的鋼筋工進(jìn)行冷彎。嚴(yán)格按施工規(guī)范的相關(guān)規(guī)定進(jìn)行鋼筋的切割、冷彎。按鋼筋焊接及驗(yàn)收規(guī)范的規(guī)定要求,進(jìn)行鋼筋焊接作業(yè)。無論是在混凝土澆筑之前或以后都不得將已綁扎的鋼筋彎曲或拉直。
⑤模板工程:模板采用輕型組合鋼模板,采用廠家訂購。在混凝土振搗時,模板縫必須達(dá)到不漏漿的要求,模板接縫處加設(shè)海綿條,海綿條與模板內(nèi)表面平
12齊。緊固采用φ48鋼管扣件,鋼筋混凝土井壁采用對拉螺栓,鋼管扣件支撐。根據(jù)圖紙所示永久工程的真實(shí)形狀和尺寸測量放樣。模板安裝做到位置正確、支撐穩(wěn)定,有足夠的支柱、撐桿和拉條,并能承受混凝土澆筑及振搗時產(chǎn)生的側(cè)向壓力,并不受氣候的影響。立模時,模板要均勻、平直地布置,使接縫處的混凝土表面平整均勻。模板的接縫設(shè)計要與結(jié)構(gòu)物的外觀相諧調(diào),使豎向和平面的縫均保持平直。模板不得與結(jié)構(gòu)鋼筋直接連接,亦不得與施工腳手架連接,以免引起模板的變形、錯位。模板內(nèi)表面涂刷脫模劑,以防止與混凝土的粘結(jié)和便于拆模。在進(jìn)行涂覆操作時,不得污染鄰近的混凝土結(jié)構(gòu)或鋼筋結(jié)構(gòu)。混凝土在澆筑前,清除模板成型面上的鋸末、刨花、灰塵、其他雜務(wù)和滯水。按圖紙要求的位置和高程將預(yù)埋件或預(yù)留管固定在模板上。澆筑混凝土前,確定預(yù)埋件和預(yù)留孔洞的位置和數(shù)量與設(shè)計圖一致,安裝牢固。模板拆除時的混凝土強(qiáng)度應(yīng)符合設(shè)計規(guī)范的有關(guān)要求。已拆除模板和支架的結(jié)構(gòu),在混凝土強(qiáng)度達(dá)到設(shè)計混凝土強(qiáng)度等級后,方可承受全部使用荷載。
⑥混凝土工程:混凝土采用攪拌站集中拌和,混凝土運(yùn)輸車運(yùn)輸,吊車吊料斗入模,施工要求與注意事項(xiàng)如下:
a澆筑前,對支架、模板、鋼筋和預(yù)埋件進(jìn)行檢查,模板內(nèi)的雜物、積水和鋼筋上的污垢清理干凈;模板如有縫隙,應(yīng)填塞嚴(yán)密,模板內(nèi)面應(yīng)涂刷脫模劑。
b澆注前,檢查混凝土的均勻性和坍落度。
c對澆注混凝土使用的腳手架,應(yīng)便于人員與料具上下,且必須保證安全。d混凝土應(yīng)按一定厚度、順序和方向分層澆筑,應(yīng)在下層混凝土初凝或能重塑前澆筑上層混凝土,混凝土分層澆筑厚度不超過40cm。
e澆筑混凝土?xí)r,采用插入式振搗棒搗固。振搗應(yīng)符合下列規(guī)定:
f使用插入式振動棒時,移動間距不應(yīng)超過振搗棒作用半徑的1.5倍;與側(cè)模應(yīng)保持5~10cm的距離;插入下層混凝土5~10cm;每一處振搗完畢后邊振動邊徐徐提出振動棒;避免振動棒碰撞模板、鋼筋及其他預(yù)埋件。
g對每一振動部位,必須振動到該部位混凝土密實(shí)為止。密實(shí)的標(biāo)志是混凝土停止下沉、不再有氣泡冒出、表面呈現(xiàn)平坦、泛漿。
13⑦混凝土的澆筑必須連續(xù)進(jìn)行,如因故間斷,間斷時間應(yīng)小于前層混凝土的初凝時間或能重塑的時間。允許間斷時間應(yīng)經(jīng)試驗(yàn)確定,若超過允許間斷時間,須采取保證質(zhì)量措施或按工作縫處理。在混凝土澆筑過程中,應(yīng)注意觀測:
a、隨時觀察所設(shè)置的預(yù)埋螺栓、預(yù)留孔是否移動,若發(fā)現(xiàn)移位時應(yīng)及時校正。
b、預(yù)留孔的成型設(shè)備及時抽拉松動。
c、在灌注過程中應(yīng)注意模板、支架等支撐情況,設(shè)專人檢查,如有變形,移位或沉陷應(yīng)立即校正并加固,處理后方可繼續(xù)澆筑。
d在澆筑過程中或澆筑完成時,如混凝土表面泌水較多,須在不擾動已澆筑混凝土的條件下,采取措施將水排除。繼續(xù)澆筑混凝土?xí)r,應(yīng)查明原因,采取措施,減少泌水。
e混凝土澆筑完成后,對混凝土裸露面應(yīng)及時進(jìn)行修整、抹平,定漿后還應(yīng)第二遍壓光或拉毛。
f混凝土達(dá)到一定強(qiáng)度后,要及時灑水養(yǎng)護(hù),天氣干燥時還應(yīng)覆蓋養(yǎng)護(hù)。⑧砌體工程:砌體所用標(biāo)準(zhǔn)磚須先澆水濕潤。在混凝土基礎(chǔ)上砌磚時,先清掃鑿毛基礎(chǔ),并用水沖刷干凈,然后在基礎(chǔ)面上鋪一層10mm厚座漿,再壓磚砌筑。砌磚時,嚴(yán)格按一鏟灰、一塊磚、一揉擠法砌筑,禁止用灌漿法砌筑。實(shí)心砌體采用一順一丁、梅花丁或三順一丁的砌筑形式。磚砌體的灰縫應(yīng)橫平豎直、厚薄均勻,并填滿砂漿。砌體水平灰縫的砂漿飽滿度不小于80%,厚度以10mm為準(zhǔn)。豎縫采用擠漿或加漿方法,不得出現(xiàn)明縫,嚴(yán)禁用水沖漿灌縫,控制厚度為10~12mm。
砂漿采用機(jī)械拌合,拌合時間不少于2min,隨拌隨用,砌筑砂漿采用M7.5水泥砂漿,座漿、抹三角灰、流槽抹面均采用1:2防水水泥砂漿。水泥砂漿抹面一般分兩道抹面,第一道砂漿抹面后,將表面搓成粗糙面或劃出紋道。待砂漿收水后抹第二道砂漿,再用木板搓平,最后抹光,保證砂漿密實(shí),光潔美觀。檢查井爬梯按設(shè)計圖紙要求設(shè)置,做到安裝牢固、灌漿密實(shí)。
(3)溢流井施工
①砌筑井前必須將基礎(chǔ)面洗刷干凈,定出井中點(diǎn),劃上砌筑位置和砌筑高度,
14以便操作人員掌握。
②砌筑圓井,要掛線校核內(nèi)徑,看有無偏移。在井下部干管伸入處,特別是管底兩側(cè),要用砂漿碎磚搗插密實(shí),其余則要逐層用磚砌包妥當(dāng),務(wù)使不滲漏。收口高度要事先算出,可按規(guī)范每圈縮入寬度計算。
③渠管伸入進(jìn)水井和檢查井內(nèi)的部分,要把它鑿至與內(nèi)壁齊平,并用砂漿抹修平整。
④溢流井每天的砌筑高度,不宜超過2m。
⑤井砌完后,應(yīng)及時澆筑混凝土,然后安裝井蓋,安裝前應(yīng)校核井環(huán)面標(biāo)高與路面標(biāo)高是否一致,無誤后,才許座漿墊穩(wěn)。
⑥檢查井井內(nèi)流槽應(yīng)平順,踏步應(yīng)安裝牢固,位置準(zhǔn)確,不得有建筑垃圾等雜物。
(4)閉水試驗(yàn)(污水):
①以相鄰兩檢查井為一分段帶井試驗(yàn),嚴(yán)密性試驗(yàn)應(yīng)在管區(qū)填土完成后進(jìn)行,試驗(yàn)水頭≤5m,或以井口高度為準(zhǔn)。
②管道嚴(yán)密性試驗(yàn)時,應(yīng)向管道內(nèi)充水并保持上游管頂以上2m水力的壓力,不得發(fā)生集中漏水現(xiàn)象,并且按下式計算:
式中Q——每1km管道長度24h的允許滲水量;
Di——管道內(nèi)徑
(5)管溝回填
a.在管道安裝完畢后,在基坑干管兩側(cè)分層回填中粗砂至管帶頂上50cm;并用水沖實(shí)。管頂50cm以上回填按路基標(biāo)準(zhǔn)要求回填,虛鋪層厚30cm,密實(shí)度要達(dá)到92%。管頂以上500mm內(nèi)不得回填大于100mm的石塊、磚塊等雜物,并用壓路機(jī)分層壓實(shí)。
b.溝槽回填的順序應(yīng)按溝槽排水方向由高向低分層進(jìn)行,溝槽兩側(cè)應(yīng)同時回填夯實(shí),防止管道位移。
c.管溝填土施工必須同步進(jìn)行,嚴(yán)禁單側(cè)回填,兩側(cè)填土填筑高差不得大于30公分,不應(yīng)超過一個土層厚度;填土應(yīng)分層夯實(shí),每層的虛鋪厚度按設(shè)計要求,采用重型機(jī)械壓實(shí),虛鋪厚度不大于300mm;用輕型機(jī)具壓實(shí),虛鋪厚度不大于200mm。管節(jié)處局部加深槽坑,應(yīng)仔細(xì)夯實(shí)。
15d.管腋部填土必須塞嚴(yán)、搗實(shí),保持與管道緊密接觸。
e.管道的管頂部分填土施工應(yīng)采用人工夯打或輕型機(jī)械壓實(shí)。嚴(yán)禁壓實(shí)機(jī)具直接作用在管道上。
3.2.3HDPE纏繞管施工方法:
①管溝開挖
a.管溝開挖前設(shè)置測量控制網(wǎng)點(diǎn),清理和平整場地,并使場地排水暢通。
b.從管溝內(nèi)挖出的土,宜在管溝兩側(cè)堆成土堤,防止地表水浸入管溝。受地表徑流威脅的管線段,在管道施工時做好臨時防洪和排洪設(shè)施,嚴(yán)禁地表水及雨水泄入管溝淹毀地基、浮起管道、泥沙淤泥或堵塞管道等事故發(fā)生。
c.土堤坡腳至管溝邊緣的距離不宜小于500mm。
d.地下水位高于開挖溝槽槽底高程的地區(qū),地下水位應(yīng)降至槽底最低點(diǎn)以下0.3—0.5m。管道在安裝、回填的全部過程中,槽底不得積水。必須在回填土回填到管道的抗浮穩(wěn)定的高度后才可停止降低地下水。
e.塑料波紋管的管溝寬度,除了考慮便于管道鋪設(shè)和安裝,考慮夯實(shí)機(jī)具便于操作和地下水便于排出的因素外,更重要是考慮管溝回填區(qū)處所提供管道側(cè)向的支撐,制約管道的水平變形的問題。所以挖土?xí)r應(yīng)該注意控制好,保證管兩側(cè)有基本的回填土提供管道側(cè)向的支撐。
f.溝槽開挖深度是根據(jù)設(shè)計井面標(biāo)高或原地面標(biāo)高、流水位標(biāo)高、纏繞管壁厚及基礎(chǔ)厚度計算而得。
g.基坑坡度根據(jù)現(xiàn)場挖取探坑鑒別土的類別為粉質(zhì)黏土,由于溝槽開挖以后,溝
16槽周邊會有機(jī)械行走施工,現(xiàn)場開挖基坑最陡不低于1:0.67放坡,當(dāng)槽深開挖深度大于3.5米的,采用分層開挖斷面形式,分層平臺按照1米控制,開挖基坑最陡不低于1:0.67放坡。
h.管溝開挖時如有積水或地下水應(yīng)及時排水。當(dāng)開挖深度接近基底設(shè)計標(biāo)高,而又不能進(jìn)行下一工序時,宜在管基高程以上保留300mm厚的土層,待繼續(xù)施工時開挖。
i.開挖溝槽,嚴(yán)格控制基底高程,不得擾動基底原狀土。溝槽開挖以后還要與相關(guān)部門聯(lián)合見證地基承載力是否能夠達(dá)到100Kpa,達(dá)到100Kpa方可進(jìn)行下道工序施工。管溝開挖后若遇淤泥小于60公分時,應(yīng)換填1:1砂石,并用平板夯,夯實(shí),密實(shí)度不小于95%,大于60公分時按照拋石擠瘀處理,然后再填碎石至管道基礎(chǔ)底部,再按照管道基礎(chǔ)施工。
j.在管道接口部分,宜局部挖成槽坑,使管節(jié)聯(lián)接(粘接或焊接)作業(yè)方便。雨季施工時,應(yīng)盡可能縮短開槽長度,且成槽快、回填快,并采取防泡槽措施一旦發(fā)生泡槽,應(yīng)將受泡的軟化土層清除,換填砂石料或中粗砂。
②管道基礎(chǔ)施工、安管
a.基坑開挖至設(shè)計標(biāo)高,溝槽底松木樁施打完成,用細(xì)木板條相連接固定,經(jīng)復(fù)測無誤后,經(jīng)業(yè)主與派駐現(xiàn)場監(jiān)理工程師驗(yàn)收合格后方可進(jìn)行基底墊層的施工。b.基底墊層施工要填筑材料,并加以夯實(shí)平整。
c.下管前要清理溝內(nèi)雜物,墊層面要清洗干凈,然后施放管道外邊線,(離開管道外邊1cm),將管道放置在正確位置上。在完成連管工序后,再檢查管道放置位置是否正確,才開始填筑及夯實(shí)管腋部回填材料。回填時不能擾動管道中線及高程。
d.纏繞管,管道安裝可采用人工安裝。槽深不大時可由人工抬管入槽。嚴(yán)禁用金屬繩索勾住兩端管口或?qū)⒐懿淖圆圻叿瓭L拋入槽中。
e.調(diào)整纏繞管管長短時可用手鋸切割,斷面應(yīng)垂直平整,不應(yīng)有損壞。
f.下管過程中,嚴(yán)禁將塑料波紋管管子從上往下自由滾放,以防止塊石等重物撞擊管身,并且必須保證溝槽排水暢通。雨季施工時,應(yīng)盡可能縮短開槽長度,且成槽快、回填快,并采取防止泡槽措施一旦發(fā)生泡槽,應(yīng)將受泡的軟化土層清除,換填砂石料或中粗砂。
g.下管以后,應(yīng)將管道排好,然后對線校正,要注意管內(nèi)流水位是否相平,
17不相平的應(yīng)墊平。
h.管道在安裝完畢尚未填土?xí)r,一旦遭水浸泡,應(yīng)進(jìn)行中心線和高程復(fù)測和外觀檢查,如發(fā)生位移,飄浮等現(xiàn)象,應(yīng)做返工處理。
③管溝回填
a.在管道安裝完畢后,在基坑干管兩側(cè)分層回填中粗砂至管帶頂上50cm;并用水沖實(shí)。管頂50cm以上回填按路基標(biāo)準(zhǔn)要求回填,虛鋪層厚30cm,密實(shí)度要達(dá)到92%。管頂以上500mm內(nèi)不得回填大于100mm的石塊、磚塊等雜物,并用壓路機(jī)分層壓實(shí)。
b.溝槽回填的順序應(yīng)按溝槽排水方向由高向低分層進(jìn)行,溝槽兩側(cè)應(yīng)同時回填夯實(shí),防止管道位移。
c.管溝填土施工必須同步進(jìn)行,嚴(yán)禁單側(cè)回填,兩側(cè)填土填筑高差不得大于30公分,不應(yīng)超過一個土層厚度;填土應(yīng)分層夯實(shí),每層的虛鋪厚度按設(shè)計要求,采用重型機(jī)械壓實(shí),虛鋪厚度不大于300mm;用輕型機(jī)具壓實(shí),虛鋪厚度不大于200mm。管節(jié)處局部加深槽坑,應(yīng)仔細(xì)夯實(shí)。
d.管腋部填土必須塞嚴(yán)、搗實(shí),保持與管道緊密接觸。
e.管道的管頂部分填土施工應(yīng)采用人工夯打或輕型機(jī)械壓實(shí)。嚴(yán)禁壓實(shí)機(jī)具直接作用在管道上。
f.填土的施工含水量應(yīng)控制在最優(yōu)含水量的±3%的范圍內(nèi)。
g.管區(qū)上部的填土,筑路時,應(yīng)按道路要求的密實(shí)度施工。
4.2.3污水泵站工程施工
本工程為發(fā)展大道污水泵站工程項(xiàng)目,構(gòu)筑物池體采用現(xiàn)澆鋼筋混凝土結(jié)構(gòu)。
1、基坑規(guī)模:
基坑周長73.1m,面積166.95m2。
2、基坑挖深:
本工程原地面標(biāo)高34.15m基坑底層標(biāo)高為24.044m,基坑挖深10.106m。根據(jù)上述對本工程基坑特點(diǎn)的分析,本著“安全可靠、經(jīng)濟(jì)合理、技術(shù)可行、方便施工”的原則,結(jié)合基坑開挖深度、施工工藝、施工周期及場地地質(zhì)條件等因素,本工程基坑支護(hù)方案采用如下形式:
基坑普遍采用二級放坡開挖,坡面做掛網(wǎng)噴漿處理。
基坑內(nèi)采用管井降水,降水井布設(shè)位置于一級平臺?;悠马斣O(shè)置截排水溝,
18攔截地表水流入基坑。
3、施工進(jìn)度計劃安排
開挖前15天開始抽水、掛網(wǎng)護(hù)坡按土方開挖進(jìn)度要求完成,降水在主體結(jié)構(gòu)施工完成、基坑回填土完成后停止抽水。
1、施工進(jìn)度計劃
(1)施工準(zhǔn)備:2天
(2)降水井及降水施工:15天
本工程共8口降水井,深25米,井口直徑為50公分。
(3)土方施工:20天
土方開挖約5000m3,根據(jù)砼護(hù)坡(土釘墻)施工要求,穿插分層分段進(jìn)行。
(4)砼護(hù)坡(土釘墻)護(hù)坡施工:10天
本工程約1000m2。
4、施工工期保證措施
(一)設(shè)立項(xiàng)目經(jīng)理部,由項(xiàng)目經(jīng)理在現(xiàn)場統(tǒng)一協(xié)調(diào)指揮,制定詳細(xì)的材料用量計劃和預(yù)算,編制好施工進(jìn)度計劃,每周一次質(zhì)量、進(jìn)度、安全例會,針對施工中存在問題作出對策,采取有效措施加以改進(jìn),保證工程進(jìn)度按計劃執(zhí)行。
(二)工程實(shí)行項(xiàng)目法管理,實(shí)行計件工資和質(zhì)量獎懲制,從而在保證工程質(zhì)量的基礎(chǔ)上提高工作效率。
(三)保證設(shè)備投入數(shù)量,同時做好保養(yǎng)維修工作,并在現(xiàn)場設(shè)立維修點(diǎn),備足易損件,及時修復(fù)故障設(shè)備,提高設(shè)備效率。
(四)保證材料供應(yīng),現(xiàn)場要確保一定的材料的儲備量。
(五)合理安排總體施工順序,總體按計劃實(shí)施,分階段按現(xiàn)場實(shí)際情況調(diào)整以消除互相干擾和加以總體平衡。
(六)嚴(yán)格按總平面圖布置施工,合理安排現(xiàn)場,避免不同工種之間相互干擾而出現(xiàn)工作停頓。
(七)施工中如遇到特殊土層或其他無法預(yù)見的因素而影響工程進(jìn)度時,可立即增加施工機(jī)械設(shè)備,確保工期按期完成。
(八)協(xié)調(diào)好外部有關(guān)單位(如市容委、環(huán)衛(wèi)等)之間的關(guān)系,保證工程順利進(jìn)行。
5、基坑土方開挖施工方案
191、基坑土方開挖施工說明
1.1本工程基坑場地較平坦,施工障礙物較少,施工條件較好,板底標(biāo)高為24.044米。整個土方開挖分三-四層開挖完成,第一層土方挖至30.65米,第二層挖至27.15米,第三層土方挖至24.344米,第四層改為人工挖土,開挖至設(shè)計標(biāo)高。
1.2基坑開挖過程中應(yīng)防止碰撞支護(hù)結(jié)構(gòu)、工程樁或擾動原狀土。
1.3開挖過程中若發(fā)生異常情況,應(yīng)立即停止挖土,并立即查明原因,待采取措施后,方能繼續(xù)施工。
1.4挖至基坑底時應(yīng)預(yù)留不少于300mm厚人工開挖,以確保坑底土體原狀結(jié)構(gòu)。
1.5每區(qū)在開挖到底后應(yīng)迅速封底,嚴(yán)禁長時間暴露。
1.6施工機(jī)械配備:PC220挖掘機(jī)4臺,裝載機(jī)2臺,自卸車20輛。
1.7勞動力計劃:配備司機(jī)5人,土方工20人,機(jī)械工6人,共31人。
2、基坑土方施工流程圖
20
5.1施工測量定位:
(1)首先對甲方提供的定位點(diǎn)和高程基準(zhǔn)點(diǎn)進(jìn)行復(fù)測;確認(rèn)無誤后對基準(zhǔn)點(diǎn)
進(jìn)入基礎(chǔ)施工
21進(jìn)行引測,引測至施工影響不到的位置,用木樁固定、水泥墩圍護(hù),保證其穩(wěn)固;
(2)測定每一層周邊土及中心土開挖的標(biāo)高、坡率、開挖時采用水準(zhǔn)儀跟蹤測定。
(3)在開挖過程中,隨時測標(biāo)高,控制坑底預(yù)留土層標(biāo)高,機(jī)械開挖土方應(yīng)避免坑底超挖。基坑及邊坡修整、清理完畢后,對基槽進(jìn)行測量,完全符合設(shè)計圖紙及施工規(guī)范要求后,繪出基槽標(biāo)高測量圖。
5.2土方開挖施工方法:
(1)基坑土方分為周邊土和中間土兩個部分,按施工方案要求第一層采取中心島(墩)式挖土法,先開挖周邊土部分,后開挖中間土,第二層采用盆式挖土法,先開挖基坑中間部分的土。第三層挖至基坑底以上300mm,改為人工開挖。
(2)土方主要采用PC-220挖掘機(jī)開挖,自卸車運(yùn)土,人工輔助施工,開挖方式為退挖。土方清底及坑中坑采用小型挖掘機(jī)開挖,人工輔助施工。
(3)土方運(yùn)輸車輛通過坡道運(yùn)往指定棄土場,退口坡道寬度為7m,坡度1:2,兩側(cè)按照1:1自然放坡,邊坡網(wǎng)噴加固,轉(zhuǎn)彎半徑按6米考慮,保證車輛通行安全。
(4)土方分層開挖順序:
第一層土方,開挖到標(biāo)高30.65米,開挖深度為3.5米,先挖四周土方為周邊網(wǎng)噴提供工作面,后挖中間土。土方采取以機(jī)械為主、人工配合的開挖方法。邊坡網(wǎng)噴面機(jī)械大面修理后,人工修坡為主。
第二層土方從30.65米開挖,開挖深度為3.5m,開挖至27.15米
第三層土方開挖2.806m,挖至24.344,為防止機(jī)械對基底的擾動,留300mm人工清理,清理的土方隨大量土方機(jī)械轉(zhuǎn)挖運(yùn)出坑,。
第四層土方人工挖土施工:
第四層土方24.344m以下開挖,開挖以1:1自然放坡,工作面500mm考慮挖土。
6、坡道收尾土方開挖施工示意圖:
22
卸土場:本工程預(yù)留土質(zhì)較好土方,作為泵站回填。采用自卸汽車裝運(yùn)至業(yè)主指定的臨時卸土場。
7、基坑土方開挖施工要點(diǎn)
7.1挖土前有項(xiàng)目技術(shù)負(fù)責(zé)人對挖土現(xiàn)場的各類施工人員進(jìn)行安全技術(shù)交底。
7.2本層土方開挖前,上層的基坑支護(hù)強(qiáng)度已經(jīng)達(dá)到設(shè)計強(qiáng)度要求。
7.3挖土深度應(yīng)嚴(yán)格控制,挖土順序嚴(yán)格按照方案設(shè)計進(jìn)行,安排專人對基底標(biāo)高進(jìn)行控制,機(jī)械開挖時應(yīng)預(yù)留300mm厚土用人工進(jìn)行平整,以免擾動基底土。
7.4本工程采用分段,分層開挖,嚴(yán)格按照基坑支護(hù)方案采取放坡開挖。
7.5土方開挖之前鋪設(shè)臨時道路,進(jìn)車與出車分道行駛,保證道路暢通。
7.6基坑開挖時,操作人員之間距離應(yīng)大于2.5m,多臺機(jī)械開挖,在挖土機(jī)工作范圍之內(nèi),不許進(jìn)行其他作業(yè)。挖土應(yīng)由上而下逐層進(jìn)行,嚴(yán)禁先挖坡腳或逆坡挖土。
7.7按照方案要求進(jìn)行分層開挖,嚴(yán)禁一次性開挖至基坑底部。
7.8基坑開挖過程中應(yīng)及時做好基坑周圍變形觀測,注意基坑四周土壁的變化情況,如發(fā)現(xiàn)有裂紋或部分坍塌現(xiàn)象,應(yīng)及時向有關(guān)單位反饋信息并做好支撐或放坡。
8、基坑土方施工信息及動態(tài)管理
23在施工過程中及時收集土方開挖所揭露的地層和地下水位、水量等資料,并與原設(shè)計依據(jù)相對比。如存在差異時,及時向設(shè)計單位及有關(guān)單位匯報,將新收集到的有關(guān)資料整理后,以文字、圖表的形式遞交給設(shè)計方作參考,在向有關(guān)主管人員匯報后并征得設(shè)計同意后,施工工藝和施工參數(shù)也應(yīng)作相應(yīng)的調(diào)整。
8.1土方開挖時,派專職施工員跟進(jìn)指揮、觀察,如土方開挖揭露的土質(zhì)情況較差,應(yīng)縮小開挖段的長度,抓緊時間施工盡量減少坑壁裸露的時間并加強(qiáng)觀測;
8.2施工過程中應(yīng)嚴(yán)格按監(jiān)測要求進(jìn)行基坑監(jiān)測,測得的數(shù)據(jù)應(yīng)及時進(jìn)行整理、分析,發(fā)現(xiàn)異常情況時采取相應(yīng)的處理措施,并及時向設(shè)計等有關(guān)單位反映;
8.3在基坑開挖施工過程中,應(yīng)派人員輪值巡視基坑周邊的變形情況,如發(fā)現(xiàn)細(xì)小裂縫,應(yīng)及時安排人員用水泥漿修補(bǔ),如發(fā)現(xiàn)裂縫較大或發(fā)展速度較快時,應(yīng)采取緊急處理措施并及時通知設(shè)計等有關(guān)單位;
8.4施工過程中觀察地下水的變化情況,如發(fā)現(xiàn)地下水量較大,對周邊邊坡應(yīng)加密布置泄水孔進(jìn)行引水;在正常天氣情況下,如已布置的泄水孔水流量突然增大時,應(yīng)注意觀察周邊排水溝、地下管線等是否開裂滲漏,如發(fā)現(xiàn)滲漏應(yīng)及時進(jìn)行修補(bǔ),同時分析引起開裂滲漏的原因,并采取相應(yīng)的處理措施;對底板采用增加管的方法增加降水量。
8.5施工過程中,應(yīng)根據(jù)施工進(jìn)度和工程需要,及時進(jìn)行施工機(jī)械、施工人員的調(diào)度,確保施工機(jī)械、施工人員能滿足工程進(jìn)行要求;
8.6發(fā)現(xiàn)異常情況,技術(shù)負(fù)責(zé)人應(yīng)迅速組織技術(shù)人員進(jìn)行研究分析,同時向設(shè)計等單位反映,確定處理措施,組織施工人員進(jìn)行處理。項(xiàng)目部應(yīng)安排施工員24小時輪值巡查基坑安全,并根據(jù)施工進(jìn)度及工程需要及時調(diào)配施工機(jī)械和施工人員,保證滿足施工需要。
9、施工現(xiàn)場平面布置
施工現(xiàn)場平面布置是保證工程質(zhì)量與工期的重要條件,是文明、安全施工的必要條件,施工平面布置時首先將施工平面布置圖報監(jiān)理、業(yè)主審核批準(zhǔn)后,方可進(jìn)行施工現(xiàn)場進(jìn)行平面布置。進(jìn)入施工現(xiàn)場主干道旁懸掛施工現(xiàn)場平面布置圖等“五圖一牌”,規(guī)劃好施工道路,水、電線路的架空與埋設(shè),儲漿池的布設(shè)與砌筑,儲漿池1個,吊車的行走路線。本工程投入1臺插筋(錨桿)鉆機(jī)施工
24支護(hù)樁、1套錨噴設(shè)備。施工現(xiàn)場平面布置應(yīng)根據(jù)施工現(xiàn)場實(shí)際需要,實(shí)行階段性的調(diào)整,動態(tài)管理,滿足現(xiàn)場安全、文明施工的需要。
4.2.5給水管施工方法:
?管道高程控制:管道應(yīng)根據(jù)圖示高程做成上升或下降的坡度,在管道高點(diǎn)設(shè)置排氣閥,地點(diǎn)設(shè)置排泥井。
?管材及接口形式
①管材:本工程管材采用PE管和球墨鑄鐵給水管,球墨鑄鐵給水管,管道公稱壓力1.0Mpa;管內(nèi)防腐采用水泥內(nèi)襯形式,外防腐形式采用鋅加瀝青防腐。
②接口形式:PE管采用熱熔焊接,球墨鑄鐵管采用承插式膠圈柔性接口連接,與閥門的連接采用法蘭連接。
?管道鋪設(shè)
①給水球墨鑄鐵管道在人行道下覆土深度不小于0.6米。
②球墨鑄鐵管道鋪設(shè)在原狀土層上,在管底鋪厚100mm以上的細(xì)砂或細(xì)土回填密實(shí)。
?管道附屬設(shè)施
①閥門:給水管采用軟密封法蘭閘閥。伸縮器采用蝶閥伸縮器。閥門井采用井下操作立式閥門井。
②消火栓:采用室外地上式消火栓,型號SS100/65-1.0,消火栓間距不大于120米,消火栓與主干管連接管(DN100)采用球墨鑄鐵管。
③排氣閥:設(shè)置在管道凸起處,采用CARX排氣閥。
④支墩設(shè)置:支管管徑DN300及以上管道設(shè)置支墩,支墩材料采用C15砼,設(shè)置在彎管、三通、管堵處。
⑤給水井蓋:人行道下檢查井蓋分別采用輕型球墨鑄鐵井蓋及支座,并具有防盜功能。
?管道水壓試驗(yàn)
①管道水壓試驗(yàn)的分段長度不應(yīng)大于1.0km,球墨鑄鐵管道試驗(yàn)壓力為0.8MPa。
25②管道試壓前應(yīng)進(jìn)行如下檢查:管道安裝檢查合格后,管頂以上回填土厚度不應(yīng)小于0.5m,管口處暫不回填,以便檢查和修理;對管道、節(jié)點(diǎn)、接口、支墩等其他附屬構(gòu)筑物的外觀進(jìn)行認(rèn)真檢查,管件的支墩、錨固設(shè)施應(yīng)達(dá)到設(shè)計強(qiáng)度;對排氣管、試壓后的排水設(shè)備及排水出路進(jìn)行檢查和落實(shí)。
?給水管道沖洗與消毒
①沖洗時,應(yīng)避開用水高峰,沖洗流速不小于1.0m/s,連續(xù)沖洗。
②管道第一次沖洗應(yīng)用清潔水沖洗至出水口水樣濁度小于3NTU為止,沖洗流速應(yīng)大于1.0m/s。
③管道第二次沖洗用有效氯離子含量不低于20mg/L的清潔水浸泡24h后,再用清潔水進(jìn)行第二次沖洗至水質(zhì)檢測、管理部門取樣化驗(yàn)合格為止。
4.3路基工程
4.3.1場地清理及路基處理
(1)人工配合機(jī)械伐樹木、灌木,挖掘樹墩、樹根及構(gòu)筑物基礎(chǔ)和草皮,人工拆除建筑物、障礙物和原有設(shè)施。
(2)機(jī)械清除原地表腐植土。
(3)具備機(jī)械作業(yè)條件的大坑穴,使用機(jī)械按設(shè)計要求依施工規(guī)范進(jìn)行回填,不具備機(jī)械回填條件的坑穴,用人工回填法作業(yè),配振動夯機(jī)夯實(shí)。
(4)原路面挖除采用液壓破碎錘配合挖掘機(jī)施工,自卸車運(yùn)輸。
4.3.2路基挖方(包括借土開挖)
路基挖方是指路基開挖土方。
(1)開挖土方采用挖掘機(jī)挖土,自卸車運(yùn)土的調(diào)運(yùn)施工方法。
(2)挖臺階采用人工開挖成形。
(3)挖淤泥采用挖掘機(jī)挖掘配合自卸車運(yùn)輸。
4.3.3路基填方
路基填方是指路基利用挖方填方和借土填方的有關(guān)作業(yè)。
(1)施工準(zhǔn)備:
按照設(shè)計文件要求,在開工前組織測量隊對全合同段進(jìn)行恢復(fù)定測測量,補(bǔ)齊必要的坐標(biāo)樁、中樁、水準(zhǔn)點(diǎn)等。
26根據(jù)設(shè)計圖放出路堤邊線,重新測繪出橫斷面圖,復(fù)核土石方數(shù)量。
基底處理:在路基施工前,清除施工范圍內(nèi)的植被、垃圾、軟土、淤泥、有機(jī)物殘渣及原地面草皮和表土,嚴(yán)格按照設(shè)計文件挖土質(zhì)臺階,臺階頂作成2%~4%的內(nèi)傾斜坡,臺階寬度滿足攤鋪和壓實(shí)設(shè)備操作的需要。
用推土機(jī)將地面基本整平后,用振動壓路機(jī)進(jìn)行碾壓,達(dá)到要求的壓實(shí)度為止。
試驗(yàn)路段:
在開工前,用路堤填料在全幅路基范圍內(nèi)鋪筑長度不小于200米的試驗(yàn)路段。
根據(jù)試驗(yàn)路段確定壓實(shí)設(shè)備的類型、最佳組合方式、碾壓遍數(shù)及碾壓速度、工序,每層材料的松鋪厚度、材料的含水量等。
(2)挖方路基:機(jī)動車道挖路床頂面以下800mm范圍內(nèi)的需用6%石灰土處理,壓實(shí)度不小于94%。
(3)填方施工:機(jī)動車道路基石方填筑施工中,為使每道工序互不干擾,并滿足規(guī)范要求,便于作業(yè)和檢查,確保每個施工段的填筑碾壓質(zhì)量。
a.填筑施工時(山皮石),自卸汽車卸車后,直接用挖掘機(jī)整平。將合格的材料均勻平整地攤鋪在路堤的整個寬度上,填料在質(zhì)量及級配合格的條件下進(jìn)行碾壓。
b.填方作業(yè)要分層平行攤鋪,每層松鋪厚度,根據(jù)壓實(shí)設(shè)備、壓實(shí)方法現(xiàn)場試驗(yàn)確定。不同石質(zhì)的填料要分層填筑。
c.路基每層填筑時,要保持表面平整,并做成2~4%的雙向橫坡以利排水。每層填料鋪設(shè)的寬度每側(cè)要超出設(shè)計寬度至少50厘米,以保證修整路基邊坡后的路堤邊緣有足夠的壓實(shí)度。
d.路堤基底未經(jīng)監(jiān)理工程師驗(yàn)收,不得進(jìn)行填筑。
e.碾壓時,從低處向高處排壓,前后兩次輪跡須重疊二分之一輪寬,達(dá)到無漏壓,無死角,確保碾壓均勻。
f.當(dāng)路基填筑至路基頂部時,攤鋪平整后,首先用重型壓路機(jī)快速碾壓一遍,以暴露不平部位。平地機(jī)細(xì)平后,再用重型壓路機(jī)碾壓,確保路基頂部平整密實(shí)。
g.為保證施工質(zhì)量和壓實(shí)效果,必須控制土山皮石的級配比例。路基填筑過
27程中,每層壓實(shí)厚度不得大于500m。
h.涵洞兩側(cè)、錐坡等填土,使用透水性好的材料對稱分層填筑壓實(shí)。涵洞填土與錐坡填土同時進(jìn)行,并按設(shè)計寬度一次填足。填料嚴(yán)格按設(shè)計要求填筑。
i.填土路堤分段施工時,其交接處不在同時間填筑則先填段按1:1坡度分層留臺階;如兩段同時施工時,則分層相互交疊銜接,其搭接長度不小于2米。
j.整修。路基填筑成型后,檢查路基的路線位置、寬度、縱坡、橫坡、邊坡及相應(yīng)的標(biāo)高等,然后編制出整修計劃。土質(zhì)路基采用人工或機(jī)械刮土或補(bǔ)土,配合機(jī)械碾壓的方法整修成型。邊溝的整修應(yīng)掛線進(jìn)行,對各種水溝的縱坡用儀器檢測,修整到符合設(shè)計及規(guī)范要求。
k.在整個路基施工中,嚴(yán)格控制“五度”。即:寬度、坡度、平整度、填筑高度、密實(shí)度。重點(diǎn)是密實(shí)度。
4.3.4石灰改善土施工
施工工藝流程,場拌法的施工工藝流程是石灰土拌和、石灰土運(yùn)輸、石灰土攤鋪、粗平整型、穩(wěn)壓、精平整型、碾壓成活、養(yǎng)生。
①拌和:原材料進(jìn)場驗(yàn)收合格后,按照生產(chǎn)配合比生產(chǎn)石灰土,當(dāng)原材料發(fā)生變化時,必須重新調(diào)試灰土比。出場石灰土的含水量應(yīng)根據(jù)當(dāng)時天氣情況綜合考慮,晴天、有風(fēng)天氣一般稍大1%~2%,應(yīng)對石灰土的含水量、灰劑量進(jìn)行及時監(jiān)控,檢驗(yàn)合格后才能出場。
②運(yùn)輸:采用有覆蓋裝置的車輛進(jìn)行運(yùn)輸,按照需求量、運(yùn)距和生產(chǎn)能力合理配置車輛的數(shù)量,運(yùn)輸車按既定路線進(jìn)出場,禁止在作業(yè)面上急剎車、急轉(zhuǎn)彎、掉頭和超速行駛。
③攤鋪:在濕潤的下承層上按照設(shè)計厚度計算出每延米需灰土的虛方數(shù)量,設(shè)專人按固定間隔、既定車型、既定的車數(shù)指揮卸料。攤鋪前人工按虛鋪厚度用白灰標(biāo)出高程點(diǎn),用推土機(jī)、平地機(jī)進(jìn)行攤鋪?zhàn)鳂I(yè),必要時用裝載機(jī)配合。
④粗平整型:用推土機(jī)先粗平1~2遍,粗平后宜用推土機(jī)在路基全寬范圍內(nèi)進(jìn)行排壓1~2遍,找出潛在不平整部位。對局部高程相差較大(一般指超出設(shè)計高程±50mm時)的面,用推土機(jī)整平,高程相差不大時(±30mm以內(nèi)時)用平地機(jī)整平。
⑤穩(wěn)壓:先用平地機(jī)初平一次,及時檢測其含水量,必要時可通過灑水和晾
28曬來調(diào)整含水量,等含水量合適后,用輪胎壓路機(jī)快速全寬靜壓一遍。
⑥精平整型:人工標(biāo)出高程點(diǎn),平地機(jī)精平1~2次,然后檢測高程、平整度和橫坡度,對局部細(xì)集料集中現(xiàn)象進(jìn)行人工處理。對局部高程稍低的灰土面嚴(yán)禁直接采取薄層找補(bǔ),應(yīng)先人工或機(jī)械松耕100m左右再進(jìn)行找補(bǔ)。
⑦碾壓:石灰土攤鋪長度約50m時宜進(jìn)行試碾壓,在最佳含水量-1%~+2%時進(jìn)行碾壓,試壓后及時進(jìn)行高程復(fù)核,碾壓原則上以“先慢后快”、“先輕后重”、“先高后低”為宜。注意事項(xiàng)有:碾壓時應(yīng)重疊200mm~300mm,后輪必須超過兩段的接縫;壓路機(jī)的碾壓速度頭兩遍以1.5~1.7km/h為宜,以后宜采用2~2.5km/h;壓路機(jī)先靜壓一遍,再振動壓實(shí)3~5遍,然后根據(jù)壓實(shí)檢測結(jié)果確定振動壓實(shí)的遍數(shù),最后用鋼輪壓路機(jī)和輪胎壓路機(jī)靜壓1~2遍,最終消除輪跡;在涵洞、橋頭等難以用壓路機(jī)碾壓的部位,用蛙夯或沖擊夯壓實(shí)。
⑧接茬的處理:工作間斷或分段施工時,應(yīng)在石灰接茬處預(yù)留300mm~500mm不予壓實(shí),與新鋪石灰土銜接,碾壓時應(yīng)灑水濕潤;宜避免縱向接茬縫,當(dāng)需縱向接茬時,茬縫宜設(shè)在路中線附近,接茬應(yīng)做成梯形,梯級寬約500mm。
⑨養(yǎng)生:壓實(shí)成活后進(jìn)行灑水養(yǎng)生,養(yǎng)生期不少于7天。養(yǎng)生期間封閉交通,如分層連續(xù)施工應(yīng)在24小時內(nèi)完成。
4.3.5級配碎石填方施工
按照圖紙設(shè)計厚度,碎石采用集中廠拌,自卸卡車運(yùn)輸,推土機(jī)攤鋪,平地機(jī)整型,振動壓路機(jī)碾壓,灑水車灑水。
①準(zhǔn)備
a.材料選擇碎石,碎石應(yīng)質(zhì)地堅硬,碎石顆粒中細(xì)長扁平顆粒的含量不應(yīng)超過20%。碎石做路基填料時,級配中最大粒徑宜小于53mm,其他指標(biāo)符合技術(shù)規(guī)范及設(shè)計要求。在拌和場采用穩(wěn)定粒料拌和設(shè)備進(jìn)行拌和。
b.施工前先要對土基的中線、標(biāo)高、壓實(shí)度、彎沉、橫坡度、平整度、厚度等作必要的復(fù)測,并做好記錄。如有不符合設(shè)計要求或未達(dá)優(yōu)良標(biāo)準(zhǔn),待予以完善后,達(dá)到優(yōu)良標(biāo)準(zhǔn)后再施工。
②施工放樣
用全站儀恢復(fù)中線,每25m設(shè)一樁,同時將兩側(cè)邊樁放出(在兩側(cè)路肩邊緣外0.3m~0.5m設(shè)指示樁)。對兩側(cè)指示樁進(jìn)行水準(zhǔn)測量,按設(shè)計標(biāo)高標(biāo)
29出碎石層頂面的施工標(biāo)高,此25m斷面上的三點(diǎn)可作為沉降觀測點(diǎn)。在施工過程中,標(biāo)樁如有丟失或移動,及時補(bǔ)樁抄平。
③運(yùn)輸
原材料運(yùn)輸采用15噸的自卸車,車況良好,數(shù)量滿足運(yùn)輸要求。
④攤鋪
攤鋪采用推土機(jī)、平地機(jī)攤鋪,在攤鋪機(jī)前應(yīng)配備一個熟練的工人指揮自卸車的卸料,達(dá)到均勻卸料,以避免碎石堆積在一處。要求平整度控制符合有關(guān)技術(shù)要求。
⑤整型
用推土機(jī)按照擬定的厚度攤鋪、粗平;同時達(dá)到穩(wěn)壓作用,然后用平地機(jī)進(jìn)行精平,精平后進(jìn)入下道工序。
⑥碾壓
碎石料的碾壓使用22t振動壓路機(jī)進(jìn)行碾壓,作業(yè)時速度控制在≤2km/h.碾壓從路基邊緣向路基中間碾壓,輪跡重疊1/2輪。壓實(shí)作業(yè)的施工順序?yàn)椋合葔郝坊吘?,后壓路基中間,先慢后快、先靜壓后振動的操作規(guī)程進(jìn)行碾壓。含水量低于最佳含水量時可適當(dāng)灑水后壓實(shí),壓實(shí)層頂面穩(wěn)定,不再下沉(無輪跡)時,可判定為密實(shí)狀態(tài)。”
4.4水泥穩(wěn)定碎石施工方案和工藝
4.4.1施工工藝
水泥穩(wěn)定碎石施工工藝主要為:施工準(zhǔn)備→拌和→運(yùn)輸→攤鋪→碾壓→養(yǎng)生→檢測驗(yàn)收
4.4.2施工方案
(1)施工準(zhǔn)備
①材料質(zhì)量要求
Ⅰ.水泥:采用初凝時間3h以上和終凝時間在6h以上的普通硅酸鹽水泥,并優(yōu)先采用低標(biāo)號路用水泥,快硬、早強(qiáng)水泥以及受潮結(jié)塊變質(zhì)的水泥不得使用。
Ⅱ.碎石:最大粒徑31.5㎜(方孔篩)。一律采用規(guī)格料配制,不得使用大于31.5㎜的混合料,壓碎值不大于26%,針片狀含量應(yīng)12%。對所選用的碎石應(yīng)預(yù)先篩分成4個不同粒級,然后配合,使顆粒組成符合級配范圍。
Ⅲ.水:水在使用前,應(yīng)按照現(xiàn)行《公路工程水質(zhì)分析操作規(guī)程》要求進(jìn)行
30試驗(yàn),并得到監(jiān)理工程師的批準(zhǔn)。
Ⅳ.水穩(wěn)集料中有機(jī)質(zhì)含量不應(yīng)超過2%;硫酸鹽含量不應(yīng)超過0.25%;含泥量小于2%。
②材料儲備:集料堆放場地及場內(nèi)道路按合同要求進(jìn)行硬化,并儲備不少于總量30%的集料,拌和場附近生產(chǎn)用水豐富。
③配合比設(shè)計:對所需的各種原材料按合同規(guī)范要求必須在使用前進(jìn)行選定,選取料場中有代表性的試樣按現(xiàn)行《公路土工試驗(yàn)規(guī)程》進(jìn)行試驗(yàn)合格并由監(jiān)理工程師認(rèn)可后方可選擇購料進(jìn)場,進(jìn)場的集料按各種規(guī)格隔離堆放。按規(guī)范要求且得到駐地監(jiān)理工程師確認(rèn)后的材料才可進(jìn)行混合料試驗(yàn)配比設(shè)計,提前56天完成配合比設(shè)計方案并上交,每種混合料設(shè)計均應(yīng)說明水泥、碎石的正確百分比(設(shè)計水泥用量4.5%),同時應(yīng)附上試驗(yàn)室對混合料原材料的符合性試驗(yàn)數(shù)據(jù)。設(shè)計應(yīng)按現(xiàn)行《公路工程無機(jī)結(jié)合料穩(wěn)定材料試驗(yàn)規(guī)程》規(guī)定的方法進(jìn)行。試件要在相對濕度大于90%,溫度為20℃±2℃的條件下養(yǎng)生6d。其7d無側(cè)限抗壓強(qiáng)度不小于4.0Mpa。根據(jù)該標(biāo)準(zhǔn)選定合適的水泥劑量。
④組織技術(shù)交底:包括施工規(guī)范要求、質(zhì)量標(biāo)準(zhǔn)、施工要點(diǎn)及安全措施等。⑤準(zhǔn)備下承層:水泥碎石施工前,對下承層進(jìn)行最后標(biāo)高復(fù)測并徹底清掃,清除各類雜物及散落材料,水泥碎石攤鋪時,要保證下承層表面濕潤。在驗(yàn)收的底基層上進(jìn)行中線恢復(fù),在邊線外側(cè)0.3~0.5m處每隔5m釘立鋼釬樁,并架設(shè)鋼絲線,最終得到駐地監(jiān)理工程師的認(rèn)可。
⑥試驗(yàn)段施工:在試驗(yàn)路段開始前14天,我部提出關(guān)于試驗(yàn)方案的完整的書面說明,送交監(jiān)理工程師批準(zhǔn),并在監(jiān)理工程師指定的路段上,使用監(jiān)理工程師認(rèn)可的配合比和批準(zhǔn)的方案,鋪筑長度不少于100米的試驗(yàn)路段。試驗(yàn)路段的試驗(yàn)結(jié)果應(yīng)達(dá)到規(guī)范要求并取得監(jiān)理工程師的批準(zhǔn)。施工過程中如設(shè)備和工藝須改變,應(yīng)通過試驗(yàn)段確定或有監(jiān)理工程師審定。
(2)拌和
拌和設(shè)備安裝按監(jiān)理工程師的意見辦理,投入一臺自動計量的強(qiáng)制式拌和機(jī),拌和設(shè)備能夠準(zhǔn)確控制各種材料的數(shù)量,保證配料精確,設(shè)備性能良好,完好率高。同時達(dá)到以下要求:
①集料滿足級配要求。
31②料倉或拌缸前有剔除超粒徑石料的篩子。
③拌和現(xiàn)場有一名試驗(yàn)員監(jiān)測拌和時的水泥劑量、含水量和各種集料的配比,發(fā)現(xiàn)異常及時修正或停止生產(chǎn),水泥劑量和含水量按要求的頻率檢查并做好記錄。
④各料斗配備1~2名技術(shù)工人,時刻監(jiān)測下料情況,并人為地幫助料斗下料,不準(zhǔn)出現(xiàn)卡堵現(xiàn)象,否則應(yīng)及時停止生產(chǎn)。拌和含水量可為最佳含水量+1%(水泥±0.5%,集料±2%)。
(3)運(yùn)輸攤鋪
攤鋪采用攤鋪寬度8m的自動找平攤鋪機(jī)攤鋪。
①用大型自卸汽車運(yùn)輸拌和料至施工現(xiàn)場。如果施工中氣溫較高或路途較遠(yuǎn),對運(yùn)輸?shù)淖孕盾嚰右愿采w,以防止水份蒸發(fā),同時裝載高度應(yīng)均勻一致,速度控制在30km/h以內(nèi),以減少不均勻碾壓或車轍,避免對下承層的結(jié)構(gòu)式破壞。
②攤鋪前對下承層灑水,使其表面濕潤,保證水穩(wěn)基層底部強(qiáng)度形成中的水份供應(yīng)。
③兩側(cè)均設(shè)基準(zhǔn)線,中間根據(jù)兩側(cè)的基準(zhǔn)線再布置一道基準(zhǔn)線以控制高程和橫坡。攤鋪時兩臺攤鋪機(jī)的軌跡重疊20cm左右以保證縱縫平順。
④攤鋪時兩側(cè)采用枕木做側(cè)模,按設(shè)計寬度鋪設(shè),可以避免碾壓中的邊部壓實(shí)度不足、塌邊、邊線線型不整齊等缺陷。
(4)碾壓
按實(shí)驗(yàn)段確認(rèn)的碾壓原則進(jìn)行規(guī)范施工,要點(diǎn)如下:
①用振動式壓路機(jī)2臺,及時進(jìn)行碾壓,其方法為首先用振動式壓路機(jī)靜態(tài)穩(wěn)壓二遍,然后振動復(fù)壓(使其達(dá)到相應(yīng)壓實(shí)度),最后再靜態(tài)復(fù)壓,最終達(dá)到要求的壓實(shí)度,并保證表面無輪跡(碾壓遍數(shù)和方法由試驗(yàn)段來確定);
②在碾壓時如表面水份蒸發(fā)過快,應(yīng)及時補(bǔ)灑少量水,但應(yīng)均勻?yàn)⒉迹虎蹓郝窓C(jī)不得在已完成或正在碾壓的路面上急剎車或“調(diào)頭”;
④從加水拌和到碾壓終了,延遲時間不超過3小時,按試驗(yàn)路段確定的合適的延遲時間嚴(yán)格施工;
⑤為提高每個碾壓段銜接位置的平整度,其末端應(yīng)形成階梯形,下一段碾壓時應(yīng)先沿著階梯形進(jìn)行半幅斜向靜壓和振碾以消除縱向碾壓中每個碾壓段銜接
32位置的縱橫向推移。
(5)攤鋪和碾壓現(xiàn)場設(shè)專人檢驗(yàn),修補(bǔ)缺陷
①設(shè)有測量員盯在現(xiàn)場,不斷檢測攤鋪和碾壓后的標(biāo)高(左、中、右)及時糾正施工中的偏差,并對鋼鉸線和攤鋪機(jī)的狀態(tài)作出及時處理。
②挖除大料窩點(diǎn)及含水量超限點(diǎn),并換填合格材料。
③用拌和好的水泥石屑對表面偏粗的部位進(jìn)行精心找補(bǔ)。
④對由于攤鋪機(jī)停頓和碾壓推移產(chǎn)生的擁包、擁坎,用鐵夯人工夯除。⑤用三米直尺逐段丈量平整度,發(fā)現(xiàn)異常馬上處理。
⑥快速檢測壓實(shí)度,壓實(shí)不足盡快補(bǔ)壓。
(6)養(yǎng)生
養(yǎng)生是水泥穩(wěn)定碎石施工中非常重要的一道工序,它直接影響結(jié)構(gòu)層的成型強(qiáng)度和表觀質(zhì)量,為此我們設(shè)專人和專門設(shè)備進(jìn)行養(yǎng)生。
①養(yǎng)生要不少于7天,養(yǎng)生方式可視具體情況采用灑水、鋪設(shè)麻袋、覆蓋薄膜等方式,且必須保持結(jié)構(gòu)層表面濕潤。
②養(yǎng)生期內(nèi)(7天)除灑水車及透封層施工車外,應(yīng)徹底中斷交通,必須有切實(shí)禁止車輛通行的強(qiáng)制措施(如設(shè)路障、專人看管等)。即使超過養(yǎng)生期未作透封層前也必須中斷交通。如不能封閉交通時,則車速應(yīng)限制在30km/h以內(nèi),禁止重型車輛通過。
③養(yǎng)生7天后,對已成型的水泥穩(wěn)定層采用15cm電動取芯機(jī)進(jìn)行取芯,試樣應(yīng)完整、密實(shí)。對試樣松散、不成型路段采取返工處理。
(7)質(zhì)量檢查
級配、水泥劑量、壓實(shí)度等現(xiàn)場指標(biāo)檢驗(yàn)應(yīng)在24小時內(nèi)完成,首先表面應(yīng)均勻無松散(跟蹤檢驗(yàn)),其次上述各項(xiàng)質(zhì)量指標(biāo)應(yīng)滿足標(biāo)準(zhǔn)要求,它不僅影響對該層的質(zhì)量評定,同時也會對瀝青面層的質(zhì)量和經(jīng)濟(jì)效益產(chǎn)生較大的影響。養(yǎng)生7天后對成型基層按監(jiān)理工程師要求進(jìn)行取芯,試樣應(yīng)完整、密實(shí)。壓實(shí)度、強(qiáng)度不合格及取芯試樣不符合要求的段落采取返工處理。平整度指標(biāo)最遲在做透封層或上基層之前,會同駐地監(jiān)理逐段進(jìn)行檢測。
(8)接頭處理
接頭一律為垂直銜接,碾壓后掛線用切割機(jī)直接挖除至標(biāo)準(zhǔn)斷面,用三米直
33尺進(jìn)行檢驗(yàn),以確認(rèn)接頭處理是否到位。
(9)要點(diǎn)提示及質(zhì)量標(biāo)準(zhǔn)
①要點(diǎn)提示
Ⅰ.自加水拌和到碾壓完畢的延遲時間不大于3小時,即一定要在此時間段內(nèi)完成施工和壓實(shí)度檢測。
Ⅱ.在攤鋪機(jī)無法攤鋪的結(jié)構(gòu)物或不規(guī)則斷面處投入推土機(jī)或裝載機(jī)配合人工快速及時的完成水穩(wěn)攤鋪。
Ⅲ.養(yǎng)生期內(nèi)或作透封層前要徹底中斷交通,措施必須跟上。
Ⅳ.水泥碎石施工時一定要精益求精,除銑刨外一切缺陷的修補(bǔ)都要在允許的延遲時間內(nèi)完成。
Ⅴ.攤鋪過程中因故停機(jī)超過2小時,要按工作逢(接頭)處理。
Ⅵ.由于水泥碎石的時效性強(qiáng),各項(xiàng)組織、準(zhǔn)備一定要充分,銜接要緊密,施工要連續(xù)(一天只留一道工作縫,中午不間斷),最大限度地減少施工損失,并提高質(zhì)量。
Ⅶ.廢棄料不準(zhǔn)拋撒在邊坡、路肩及中央分隔帶內(nèi)。
Ⅷ.配料準(zhǔn)確,尤其是水泥劑量更要準(zhǔn)確(至關(guān)重要)。嚴(yán)格控制水泥劑量及含水量并采取措施盡量減少水穩(wěn)層干縮或溫縮等原因引起的橫向裂縫。
Ⅸ.雨季施工時,細(xì)料要覆蓋,防止著雨結(jié)團(tuán),計量失準(zhǔn)。處于養(yǎng)生期間內(nèi)的路段,必須設(shè)置明顯的標(biāo)志牌。
②質(zhì)量標(biāo)準(zhǔn)
Ⅰ.混合料符合設(shè)計和規(guī)范要求,水泥劑量準(zhǔn)確。
表面平整密實(shí)邊線整齊,無松散,無坑洼、軟彈現(xiàn)象。
混合料拌和均勻,無粗細(xì)顆粒離析現(xiàn)象。
施工接縫平整、穩(wěn)定、無輪跡。
Ⅱ.壓實(shí)度、平整度、縱斷高程、寬度、厚度、橫坡、強(qiáng)度等符合技術(shù)規(guī)范要求。Ⅲ.水泥穩(wěn)定碎石基層之間應(yīng)噴灑水泥凈漿,以利于層間粘結(jié)。
Ⅳ.養(yǎng)生應(yīng)符合規(guī)范要求,養(yǎng)生7天后取芯芯樣應(yīng)完整、密實(shí)。
Ⅴ.水泥穩(wěn)定碎石基層實(shí)測項(xiàng)目及標(biāo)準(zhǔn)符合現(xiàn)行規(guī)范標(biāo)準(zhǔn)。
344.5透層、封層、粘層
4.5.1透層
透層油施工工藝:施工準(zhǔn)備(材料、機(jī)械)→清掃→噴灑→集料撒布→碾壓→養(yǎng)護(hù)
(1)施工準(zhǔn)備
①材料
透層油采用慢裂乳化瀝青PC-2,用量根據(jù)基層的表面情況通過試灑確定。②機(jī)械
瀝青灑布車、灑水車、森林滅火鼓風(fēng)機(jī)及其它小型工具。
(2)基層或下承層的準(zhǔn)備
透層油緊跟在基層碾壓成型后表面稍變干燥,尚未硬化的情況下噴灑。
(3)透層油噴灑
規(guī)范規(guī)定在氣溫不低于10℃
①用瀝青灑布車均勻?yàn)⒉迹础豆仿坊访娆F(xiàn)場測試規(guī)程》中有關(guān)要求和方法檢測灑布量。
②透層灑布量應(yīng)通過試灑確定,在能透入的先決條件下,以透入基層深度5mm以上為準(zhǔn),否則灑布量以在表面不流淌為準(zhǔn)。灑交接處時,應(yīng)控制使之不超灑,多余的應(yīng)予以清除,在不規(guī)則斷面處采取人工均勻?yàn)⒉肌?/p>
③噴灑區(qū)邊部的路緣石、結(jié)構(gòu)物、樹木等應(yīng)加以遮蓋防護(hù),以免污染。在設(shè)計圖紙和面層攤鋪的范圍內(nèi)應(yīng)全部灑布透層油,特別是起終點(diǎn)、出入道口等部位,以保證連接緊密。避免碾壓中的較大推移和出現(xiàn)裂紋導(dǎo)致不成型。
④應(yīng)均勻?yàn)⒉?,在縱向和橫向噴、風(fēng)速適度、無濃霧不下雨的條件下進(jìn)行噴灑。主要是考慮到破乳的環(huán)境條件。
4.5.2封層施工
改性乳化瀝青稀漿封層使用專用的攤鋪機(jī)進(jìn)行攤鋪。稀漿封層混合料中改性瀝青的用量應(yīng)通過配合比設(shè)計確定,混合料的質(zhì)量應(yīng)符合現(xiàn)行《公路瀝青路面施工技術(shù)規(guī)范》的技術(shù)要求。
4.5.3粘層施工
粘層施工工藝:施工準(zhǔn)備(材料、機(jī)械)→面層清掃→噴灑→養(yǎng)護(hù)
35(1)施工準(zhǔn)備
其施工工藝與透封層油施工基本相同,主要是盡量做到瀝青層的連續(xù)施工,防止其它工序的交叉干擾和污染,對已出現(xiàn)的路面污染要認(rèn)真的清掃沖洗干凈,并達(dá)到干燥狀態(tài),盡量清除被污染的表孔隙內(nèi)泥土。
①材料準(zhǔn)備
粘層瀝青材料采用瀝青面層所用的種類、標(biāo)號相同的石油瀝青經(jīng)乳化或稀釋制成。采用乳化瀝青PCR。
②機(jī)械
投入1臺瀝青灑布車、5T以上灑水車1臺及其它小型工具。
(2)粘層噴灑
①用瀝青灑布車均勻?yàn)⒉?,并按《公路路基路面現(xiàn)場測試規(guī)程》中有關(guān)要求和方法檢測灑布量,每次檢測不少于3處。
②粘層灑布量應(yīng)規(guī)范及招標(biāo)文件的要求。
③粘層瀝青應(yīng)在鋪筑覆蓋層之前經(jīng)24h內(nèi)灑布或涂刷。
④對噴灑區(qū)附近的結(jié)構(gòu)物和樹木及路緣石等采取保護(hù)措施,以免濺上瀝青受到污染。
(3)養(yǎng)護(hù)
①承包人應(yīng)對灑好透層、粘層或封層瀝青的基層和面層保持良好狀態(tài)。當(dāng)出現(xiàn)泛油或監(jiān)理工程師有指示時,應(yīng)按指定用量補(bǔ)撒吸附瀝青材料。
②除運(yùn)送瀝青混合料外,任何車輛均不得在完成的粘層上通行。
4.6瀝青砼面層施工方案及工藝
4.6.1材料要求
材料堆放場地按照要求進(jìn)行場地硬化,防止泥土對材料污染,各種材料堆放整齊,界限清楚。材料要分批檢查。
(1)集料
①料源:本工程的料源必須經(jīng)過考察確定,考察人員必須包括質(zhì)監(jiān)站、業(yè)主代表、監(jiān)理工程師、施工單位、試驗(yàn)室人員??疾毂仨毬鋵?shí)以下問題:集料質(zhì)量(試驗(yàn)確定)、集料生產(chǎn)機(jī)械性能(料場落實(shí))、集料生產(chǎn)能力及供貨能力(料場落實(shí))。
36②質(zhì)量要求:路面下面層集料采用反擊式破碎的優(yōu)質(zhì)石灰?guī)r集料,所有石料均具有良好的顆粒形狀,保證潔凈、干燥、表面粗燥,具有足夠的強(qiáng)度和耐磨性;無雜質(zhì)或其它有害雜質(zhì),并有良好的級配。上面層粗集料使用玄武巖,加工表面粗糙,形狀接近立方體,有良好的嵌擠能力的破碎集料。集料的技術(shù)指標(biāo)必須符合現(xiàn)行規(guī)范規(guī)定:
③拌和站要求
我公司有4000型瀝青拌和站,本標(biāo)段瀝青混合料采用該拌和站。集料運(yùn)輸能力必須滿足拌和站生產(chǎn)要求,已進(jìn)場的各種材料要分倉堆放,采用水泥砼隔墻或磚隔墻隔離,做到堆放整齊,界限清楚,并設(shè)立明顯標(biāo)志標(biāo)牌,標(biāo)明材料的規(guī)格型號、產(chǎn)地、用途、是否已經(jīng)檢驗(yàn)等詳細(xì)內(nèi)容。
(2)瀝青
①檢測要求:
瀝青采用AH-70型重交通道路石油瀝青及改性瀝青。進(jìn)場瀝青必須附有制造廠的證明和出廠試驗(yàn)報告,并說明裝運(yùn)數(shù)量、貨運(yùn)日期及定貨數(shù)量等,并對每批次重新進(jìn)行取樣和化驗(yàn)。其抽檢的頻率滿足規(guī)范要求,施工前將擬用的瀝青、各種集料和礦粉樣品送至中心試驗(yàn)室檢驗(yàn)。
②存放要求:
瀝青在貯藏罐中貯藏時間不要存放太久。若作長期的貯存,為防止其硬化,可令其作間斷的罐內(nèi)循環(huán),但溫度不得低于130℃。瀝青罐裝貯存時,要確保操作安全。當(dāng)大型貯罐內(nèi)的瀝青需加熱時,注意在較長時間內(nèi)作間斷地加熱以防止加熱管和由它形成周圍的部件局部過熱。對于不同種類的瀝青分別存放,不同的瀝青使用不同的路段有明確的記錄。
③礦粉
礦粉采用石灰?guī)r或巖漿巖中的強(qiáng)基性巖石等憎水性石料磨制而成,不含泥土雜質(zhì)和團(tuán)粒,干燥、潔凈,各項(xiàng)指標(biāo)符合規(guī)范及招標(biāo)文件的要求。
④穩(wěn)定劑
用于改性瀝青混合料的纖維穩(wěn)定劑,抗車轍劑,巖瀝青等。
4.6.2配合比設(shè)計
選用符合設(shè)計、規(guī)范要求的材料,參考規(guī)范及招標(biāo)文件提供的資料,用馬歇
37爾試驗(yàn)等方法確定礦料級配及瀝青用量。并通過熱料篩分來設(shè)計生產(chǎn)配合比,最后試拌驗(yàn)證生產(chǎn)配合比。
(1)目標(biāo)配合比設(shè)計階段
首先計算出各種材料的用量比例,配合成符合要求的礦料級配范圍。然后,遵照試驗(yàn)規(guī)和模擬實(shí)際生產(chǎn)狀況,以6個不同的瀝青用量(間隔0.5%),采用試驗(yàn)室小型瀝青混合料拌和機(jī)與礦料進(jìn)行混合料拌和成型及馬歇爾試驗(yàn)(包括浸水馬歇爾試驗(yàn))測定的各項(xiàng)指標(biāo)應(yīng)符合下表所示的熱拌瀝青混合料馬歇爾試驗(yàn)技術(shù)標(biāo)準(zhǔn)的要求,確定最佳瀝青用量。由我單位技術(shù)過硬的試驗(yàn)工程師,在總工協(xié)助下完成,能夠保證試驗(yàn)方法正確,結(jié)果可靠。以此礦料級配及瀝青用量作為目標(biāo)配合比,確定各冷料倉的供料比例、進(jìn)料速度及試拌。
(2)生產(chǎn)配比設(shè)計階段
必須對篩分后進(jìn)入拌和機(jī)冷、熱料倉的各種材料進(jìn)行取樣篩分試驗(yàn)、調(diào)整,使生產(chǎn)時的各種材料滿足目標(biāo)配比的要求,以確定各熱料倉的材料比例,供拌和機(jī)控制室使用,同時反復(fù)檢測冷料倉進(jìn)料比例以達(dá)到供料平衡,并以目標(biāo)配合比設(shè)計的最佳瀝青用量、最佳瀝青用量±0.3%等三個瀝青用量進(jìn)行馬歇爾試驗(yàn),確定生產(chǎn)配合比的最佳瀝青用量,根據(jù)公路車輛渠化要求,面層的最佳瀝青用量宜低于中值0.2~0.3%,但不低于目標(biāo)配合比所定瀝青用量的底限。
(3)生產(chǎn)配比驗(yàn)證階段
拌和機(jī)采用生產(chǎn)配合比進(jìn)行試拌并鋪筑試驗(yàn)段,并用拌和的瀝青混合料及路上鉆取的芯樣進(jìn)行馬歇爾試驗(yàn)和礦料篩分、瀝青用量檢驗(yàn),檢驗(yàn)產(chǎn)品的質(zhì)量符合程度,由此確定生產(chǎn)用的標(biāo)準(zhǔn)配合比,并作為生產(chǎn)控制的依據(jù)和質(zhì)量檢驗(yàn)的標(biāo)準(zhǔn)。標(biāo)準(zhǔn)配合比的礦料級配至少應(yīng)包括0.075mm、2.36mm、4.75mm三檔的篩孔通過率接近要求級配的中值。滿足要求后,即作為生產(chǎn)配合比,施工過程中不得隨意更改,保證各項(xiàng)指標(biāo)符合要求并相對穩(wěn)定,標(biāo)準(zhǔn)偏差盡可能的小。
4.6.3下承層準(zhǔn)備
(1)瀝青面層施工前要對基層進(jìn)行一次認(rèn)真的檢驗(yàn),特別是要重點(diǎn)檢查:標(biāo)高是否符合要求(高出的部分必須洗刨);表面有無松散(局部小面積松散必須徹底清除,用瀝青混合料
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五年度高端不銹鋼門工程安裝與維護(hù)服務(wù)合同3篇
- 二零二五版控制權(quán)爭奪下的企業(yè)并購法律服務(wù)合同3篇
- 二零二五年范文合同失效通知模板與說明3篇
- 二零二五版企業(yè)訂餐福利管理合同3篇
- 2025年P(guān)VC管材綠色生產(chǎn)供應(yīng)鏈采購銷售合同3篇
- 居民住宅改為商用合同(2篇)
- 二零二五年房屋租賃合同出租人租賃房屋租賃權(quán)租賃合同9篇
- 二零二五年度電子信息材料采購合同范本3篇
- 2025年度生物制藥行業(yè)質(zhì)量控制合同3篇
- 2025年度人工智能產(chǎn)業(yè)園區(qū)建設(shè)與運(yùn)營合同3篇
- 湖南省建設(shè)工程施工階段監(jiān)理服務(wù)費(fèi)計費(fèi)規(guī)則【實(shí)用文檔】doc
- GB/T 6913-2008鍋爐用水和冷卻水分析方法磷酸鹽的測定
- GB/T 18717.2-2002用于機(jī)械安全的人類工效學(xué)設(shè)計第2部分:人體局部進(jìn)入機(jī)械的開口尺寸確定原則
- 教案:第三章 公共管理職能(《公共管理學(xué)》課程)
- 中國文化概論(第三版)全套課件
- 117-鋼結(jié)構(gòu)工程質(zhì)量常見問題與管控措施