項(xiàng)目專項(xiàng)施工方案
高新智谷一期EPC項(xiàng)目
B1號(hào)樓模板專項(xiàng)施工方案
(B類方案)
編制單位:中國(guó)建筑第八工程局有限公司
編制人:
日期:2023年5月
-1-
項(xiàng)目專項(xiàng)施工方案
目錄
1編制依據(jù)......................................................................................................-1-
2工程概況......................................................................................................-2-
2.1工程建設(shè)概況......................................................................................................................................-2-
2.2設(shè)計(jì)概況..............................................................................................................................................-3-
2.2.1危大模板說(shuō)明...........................................................................................................................-3-
2.2.2危大工程概況...........................................................................................................................-4-
2.3工程施工條件......................................................................................................................................-5-
3施工安排......................................................................................................-6-
3.1項(xiàng)目管理組織......................................................................................................................................-6-
3.2管理目標(biāo)..............................................................................................................................................-7-
3.3各項(xiàng)資源供應(yīng)方式..............................................................................................................................-7-
3.3.1勞務(wù)資源安排一覽表...............................................................................................................-7-
3.3.2工程用大宗物資供應(yīng)一覽表....................................................................................................-7-
3.3.3大型機(jī)械設(shè)備采購(gòu)供應(yīng)安排一覽表........................................................................................-7-
3.4施工流水段的劃分及施工工藝流程...................................................................................................-7-
3.4.1施工流水段劃分.......................................................................................................................-7-
3.4.2施工工藝流程...........................................................................................................................-7-
3.5工程施工重點(diǎn)難點(diǎn)分析及應(yīng)對(duì)措施...................................................................................................-8-
4施工進(jìn)度計(jì)劃...............................................................................................-9-
5施工準(zhǔn)備與資源配置計(jì)劃..........................................................................-10-
5.1施工準(zhǔn)備計(jì)劃....................................................................................................................................-10-
5.1.1技術(shù)準(zhǔn)備.................................................................................................................................-10-
5.1.2現(xiàn)場(chǎng)準(zhǔn)備.................................................................................................................................-10-
5.2資源配置計(jì)劃....................................................................................................................................-10-
5.2.1勞動(dòng)力配置計(jì)劃.....................................................................................................................-10-
5.2.2工程原材料需用量計(jì)劃.........................................................................................................-11-
5.2.3施工機(jī)具配置計(jì)劃.................................................................................................................-11-
5.2.4測(cè)量計(jì)量?jī)x器配置計(jì)劃.........................................................................................................-11-
6施工方法及工藝要求..................................................................................-13-
6.1方案及技術(shù)參數(shù)................................................................................................................................-13-
6.1.1基礎(chǔ)施工.................................................................................................................................-13-
6.1.2樓板架體搭設(shè)參數(shù).................................................................................................................-13-
6.1.3梁架體搭設(shè)參數(shù).....................................................................................................................-13-
6.1.4梁側(cè)模加固參數(shù).....................................................................................................................-14-
6.2施工工藝流程....................................................................................................................................-14-
-1-
項(xiàng)目專項(xiàng)施工方案
6.2.1墻柱模板施工.........................................................................................................................-14-
6.2.2梁板模板施工.........................................................................................................................-14-
6.3施工要點(diǎn)............................................................................................................................................-14-
6.3.1鋼管腳手架支撐體系.............................................................................................................-14-
6.3.2可調(diào)托撐.................................................................................................................................-16-
6.3.3剪刀撐.....................................................................................................................................-16-
6.3.4水平兜網(wǎng)設(shè)置.........................................................................................................................-16-
6.3.5混凝土澆筑.............................................................................................................................-16-
6.3.6模板拆除.................................................................................................................................-17-
6.3.7監(jiān)測(cè)監(jiān)控措施.........................................................................................................................-18-
6.3.8排水措施.................................................................................................................................-19-
6.4驗(yàn)收標(biāo)準(zhǔn)............................................................................................................................................-20-
6.5驗(yàn)收程序............................................................................................................................................-20-
6.6驗(yàn)收內(nèi)容............................................................................................................................................-21-
6.7驗(yàn)收人員............................................................................................................................................-22-
7各項(xiàng)管理計(jì)劃.............................................................................................-23-
7.1綠色施工管理計(jì)劃............................................................................................................................-23-
7.1.1節(jié)材與材料資源利用.............................................................................................................-23-
7.1.2節(jié)水與水資源利用.................................................................................................................-23-
7.1.3節(jié)能與能源利用.....................................................................................................................-23-
7.1.4節(jié)地與土地資源保護(hù).............................................................................................................-23-
7.1.5人力資源節(jié)約.........................................................................................................................-23-
7.1.6環(huán)境保護(hù).................................................................................................................................-23-
7.2進(jìn)度管理計(jì)劃....................................................................................................................................-23-
7.3質(zhì)量管理計(jì)劃....................................................................................................................................-25-
7.3.1質(zhì)量控制目標(biāo)分解.................................................................................................................-25-
7.3.2質(zhì)量管理的組織機(jī)構(gòu)和職責(zé)分工..........................................................................................-25-
7.3.3質(zhì)量管理制度.........................................................................................................................-25-
7.3.4質(zhì)量控制點(diǎn).............................................................................................................................-26-
7.3.5質(zhì)量保證措施.........................................................................................................................-27-
7.4安全管理計(jì)劃....................................................................................................................................-28-
7.4.1職業(yè)健康安全管理分解目標(biāo)..................................................................................................-28-
7.4.2安全管理組織機(jī)構(gòu)和職責(zé)分工..............................................................................................-28-
7.4.3職業(yè)健康安全重大危險(xiǎn)源.....................................................................................................-29-
7.4.4職業(yè)健康安全資源配置計(jì)劃..................................................................................................-30-
7.4.5安全生產(chǎn)管理制度.................................................................................................................-30-
7.4.6安全生產(chǎn)一般保證措施.........................................................................................................-31-
7.4.7預(yù)防坍塌事故的技術(shù)措施.....................................................................................................-32-
7.4.8預(yù)防高空墜落事故安全技術(shù)措施..........................................................................................-32-
7.6新冠疫情應(yīng)急預(yù)案............................................................................................................................-33-
7.6.1組織機(jī)構(gòu)及職責(zé).....................................................................................................................-33-
7.6.2項(xiàng)目?jī)?chǔ)備防疫物資.................................................................................................................-35-
7.6.3施工現(xiàn)場(chǎng)準(zhǔn)備.........................................................................................................................-35-
-2-
項(xiàng)目專項(xiàng)施工方案
7.6.4疫情預(yù)防及復(fù)工前后應(yīng)急措施..............................................................................................-36-
7.6.5疫情防控檢查、演練及培訓(xùn)交底..........................................................................................-39-
7.6.6疫情防控設(shè)備、物資、藥品清單及急救醫(yī)院......................................................................-39-
7.7成品保護(hù)計(jì)劃....................................................................................................................................-40-
8應(yīng)急預(yù)案.....................................................................................................-41-
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)........................................................................................................................-41-
8.2事故風(fēng)險(xiǎn)分析....................................................................................................................................-41-
8.3事故救援程序....................................................................................................................................-42-
8.3.1處置程序.................................................................................................................................-42-
8.3.2應(yīng)急救援醫(yī)院.........................................................................................................................-42-
8.4應(yīng)急處置措施....................................................................................................................................-42-
8.5應(yīng)急物資準(zhǔn)備....................................................................................................................................-43-
8.6應(yīng)急響應(yīng)、響應(yīng)結(jié)束、演練............................................................................................................-44-
8.6.1人員培訓(xùn).................................................................................................................................-44-
8.6.2應(yīng)急演練.................................................................................................................................-45-
8.6.3事故后處理工作.....................................................................................................................-46-
9計(jì)算書和相關(guān)圖紙......................................................................................-48-
9.1計(jì)算依據(jù)............................................................................................................................................-48-
9.2樓板架體計(jì)算....................................................................................................................................-48-
9.3400*1250計(jì)算...................................................................................................................................-62-
9.4300*900梁計(jì)算.................................................................................................................................-74-
9.5400*1250梁側(cè)模...............................................................................................................................-87-
9.6400*800梁側(cè)模.................................................................................................................................-93-
9.7300*600梁側(cè)模.................................................................................................................................-99-
-3-
項(xiàng)目專項(xiàng)施工方案
-4-
項(xiàng)目專項(xiàng)施工方案
1編制依據(jù)
序
類別文件名稱編號(hào)
號(hào)
國(guó)家主席令第91號(hào)(2023年
1《中華人民共和國(guó)建筑法》
修改版)
2《中華人民共和國(guó)安全生產(chǎn)法》國(guó)家主席令第70號(hào)
3國(guó)家《建設(shè)工程質(zhì)量管理?xiàng)l例》國(guó)務(wù)院令第279號(hào)
行政
4《建設(shè)工程安全生產(chǎn)管理?xiàng)l例》國(guó)務(wù)院令第393號(hào)
文件
5《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理辦法》住建部令(2018)第37號(hào)
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實(shí)施《危險(xiǎn)性較大的分部分項(xiàng)工程
6建辦質(zhì)[2018]31號(hào)
安全管理規(guī)定》有關(guān)問(wèn)題的通知
7《建筑結(jié)構(gòu)荷載規(guī)范》GB50009-2012
8《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
9《混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范》(2015年版)GB50010-2010
10《建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范》GB50007-2011
11《混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50204-2015
12《建設(shè)工程施工現(xiàn)場(chǎng)供用電安全規(guī)范》GB50194-2014
13《混凝土結(jié)構(gòu)工程施工規(guī)范》GB50666-2011
14《建設(shè)工程施工現(xiàn)場(chǎng)消防安全技術(shù)規(guī)范》GB50720-2011
15國(guó)家《建筑施工安全技術(shù)統(tǒng)一規(guī)范》GB50870-2013
16行業(yè)《建筑施工模板安全技術(shù)規(guī)范》JGJ162-2008
17規(guī)范《建筑施工安全檢查標(biāo)準(zhǔn)》JGJ59-2011
18《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
19《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范》JGJ46-2005
20《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-2012
21《建筑施工扣件式鋼管腳手架安全技術(shù)規(guī)范》JGJ130-2011
22《施工現(xiàn)場(chǎng)機(jī)械設(shè)備檢查技術(shù)規(guī)范》JGJ160-2016
23《建筑施工作業(yè)勞動(dòng)防護(hù)用品配備及使用標(biāo)準(zhǔn)》JGJ184-2009
24《建筑施工臨時(shí)支撐結(jié)構(gòu)技術(shù)規(guī)范》JGJ300-2013
25《建筑施工模板和腳手架試驗(yàn)標(biāo)準(zhǔn)》JGJ/T414-2018
26合同施工總承包合同/
設(shè)計(jì)
27施工圖紙/
文件
-1-
項(xiàng)目專項(xiàng)施工方案
2工程概況
2.1工程建設(shè)概況
xx高新智谷一期EPC項(xiàng)目工程建設(shè)概況具體內(nèi)容如表2.1-1所示,工程效果圖如圖2.1-1
所示。
表2.1-1工程建設(shè)概況
序號(hào)內(nèi)容
1項(xiàng)目名稱xx高新智谷一期EPC
2標(biāo)段劃分一期
3建設(shè)地點(diǎn)合肥市高新區(qū)創(chuàng)大道與柏堰灣路交口東南角。
4建設(shè)規(guī)模總建筑面積:5076.59m2㎡
5建設(shè)單位合肥xx高新科創(chuàng)投資發(fā)展有限公司
6監(jiān)理單位合肥工大建設(shè)監(jiān)理有限責(zé)任公司
7設(shè)計(jì)單位同圓設(shè)計(jì)集團(tuán)有限公司
8勘察單位江蘇新亞勘測(cè)設(shè)計(jì)有限公司
9施工單位中國(guó)建筑第八工程局有限公司
圖2.1-1工程效果圖
-2-
項(xiàng)目專項(xiàng)施工方案
2.2設(shè)計(jì)概況
2.2.1危大模板說(shuō)明
根據(jù)《住建部辦公廳關(guān)于實(shí)施<危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定>有關(guān)問(wèn)題的通
知》,危大工程:搭設(shè)高度5m及以上,或搭設(shè)跨度10m及以上,或施工總荷載(設(shè)計(jì)值)10kN/m2
及以上,或集中線荷載(設(shè)計(jì)值)15kN/m及以上。超規(guī)危大工程:搭設(shè)高度8m及以上,或搭
設(shè)跨度18m及以上,或施工總荷載(設(shè)計(jì)值)15kN/m2及以上,或集中線荷載(設(shè)計(jì)值)20kN/m
及以上。本方案主要針對(duì)B1號(hào)樓非超規(guī)危大工程編制的模板專項(xiàng)方案。
典型
序號(hào)荷載設(shè)計(jì)值危大工程判定
代表構(gòu)件
1搭設(shè)高度5.2m/6.1m非超規(guī)危大工程
施工總荷載組合S=1.35×(0.30+25.10×荷載計(jì)算屬于普通模板工程
2150厚樓板0.15)+1.4×0.9×2.50=8.64kN/m2但搭設(shè)高度大于5米,屬于
S<10kN/m2非超規(guī)危大工程
可變荷載控制時(shí)荷載組合:S1=1.2×(0.50×
(0.40+0.90×2)+25.50×0.90×0.40)+1.4×
2.00×0.40=13.46kN/m
對(duì)于本工程梁截面積0.36<
永久荷載控制時(shí)荷載組合:S2=1.35×(0.50×
3梁400X900S≤0.5㎡的梁屬于非超規(guī)危
(0.40+0.90×2)+25.50×0.90×0.40)+1.4×
大工程
0.7×2.00×0.40=14.66kN/m
集中線荷載設(shè)計(jì)值為S=max(S1,S2)=14.66
kN/mS<15kN/m
可變荷載控制時(shí)荷載組合:S1=1.2×(0.50×
(0.30+1.20×2)+25.50×1.20×0.30)+1.4×
2.00×0.30=13.48kN/m
對(duì)于本工程梁截面積0.36<
永久荷載控制時(shí)荷載組合:S2=1.35×(0.50×
4梁300X1200S≤0.5㎡的梁屬于非超規(guī)危
(0.30+1.20×2)+25.50×1.20×0.30)+1.4×
大工程
0.7×2.00×0.30=14.80kN/m
集中線荷載設(shè)計(jì)值為S=max(S1,S2)=14.80
kN/mS<15kN/m
可變荷載控制時(shí)荷載組合:S1=1.2×(0.50×
(0.40+1.25×2)+25.50×1.25×0.40)+1.4×
2.00×0.40=18.16kN/m
永久荷載控制時(shí)荷載組合:S2=1.35×(0.50×對(duì)于本工程已有的梁截面積
5梁400X1250(0.40+1.25×2)+25.50×1.25×0.40)+1.4×0.36<S≤0.5㎡的梁屬于非
0.7×2.00×0.40=19.95kN/m超規(guī)危大工程
所以集中線荷載設(shè)計(jì)值為
S=max(S1,S2)=19.95kN/m
15kN/m≤S<20kN/m
可變荷載控制時(shí)荷載組合:S1=1.2×(0.50×
(0.60+0.90×2)+25.50×0.90×0.60)+1.4×
2.00×0.60=19.64kN/m
永久荷載控制時(shí)荷載組合:S2=1.35×(0.50×對(duì)于本工程梁截面積>0.5
5梁600X900
(0.60+0.90×2)+25.50×0.90×0.60)+1.4×㎡的梁屬于超規(guī)危大工程
0.7×2.00×0.60=21.39kN/m
集中線荷載設(shè)計(jì)值為S=max(S1,S2)=21.39
kN/mS≥20kN/m
-3-
項(xiàng)目專項(xiàng)施工方案
2.2.2危大工程概況
表2.2-1危大模板工程區(qū)域概況表
層頂構(gòu)件
樓層高度跨度(m)尺寸mm危大工況類型
名稱
樓板高度5.2150(計(jì)算取150mm)搭設(shè)高度>5m
200*300、300*500、300*600、
300*650、300*750、300*800、
350*500、200*400、250*750、
梁高度5.2搭設(shè)高度>5m
首層250*600、200*400、250*650、
250*500、250*800、400*800、
400*900、300*1000、
搭設(shè)高度>5m
KL6(2)高度6.1/跨度13300*1000
搭設(shè)跨度>10m
樓板、梁高度5.2110/120/130(計(jì)算取150mm)搭設(shè)高度>5m
200*300、200*400、200*500、
250*500、250*600、250*650、
250*800、300*500、300*650、
梁高度5.2搭設(shè)高度>5m
300*750、300*800、300*900、
300*1200、350*500、400*800、
400*900、
L11高度5.2/跨度16.2300*1200
搭設(shè)高度>5m
KL14高度5.2/跨度13300*800
搭設(shè)跨度>10m
KL14高度5.2/跨度17.2300*800
二層搭設(shè)高度>5m
KL10高度5.2/跨度9.5400*100020KN/m>線荷載>
15KN/m
搭設(shè)高度>5m
搭設(shè)跨度>10m
KL18高度5.2/跨度17400*1200
20KN/m>線荷載>
15KN/m
線荷載>20KN/m
400*1500、700*800、700*1250、詳已編制的需專家
大梁
700*1700、800*1700、800*1800論證的B1號(hào)樓高大
模板專項(xiàng)方案
樓板高度6.1120(計(jì)算取150mm)搭設(shè)高度>5m
200*300、200*400、250*500、
250*600、250*650、300*500、
梁高度6.1搭設(shè)高度>5m
300*600、300*750、300*800、
300*900、300*1200、400*900、
搭設(shè)高度>5m
KL2高度6.1/跨度3400*125020KN/m>線荷載>
三層
15KN/m
WKL13高度6.1/跨度17300*1200搭設(shè)高度>5m
L17高度6.1/跨度17.2300*900搭設(shè)跨度>10m
線荷載>20KN/m
400*1500、600*900、700*900、詳已編制的需專家
大梁
700*1700、800*1700論證的B1號(hào)樓高大
模板專項(xiàng)方案
-4-
項(xiàng)目專項(xiàng)施工方案
2.3工程施工條件
1、我司已與具備相關(guān)資質(zhì)的勞務(wù)分包公司簽訂合同,負(fù)責(zé)架體及模板施工。
2、模板專項(xiàng)施工方案編制并審批完成,施工前對(duì)勞務(wù)進(jìn)行方案與技術(shù)交底。
3、模板、木方及鋼管架等材料進(jìn)場(chǎng)已通過(guò)驗(yàn)收,尺寸及材質(zhì)符合要求。
4、材料堆放:周邊場(chǎng)地內(nèi)均設(shè)置有模板材料堆放及加工場(chǎng)。
5、材料運(yùn)輸:現(xiàn)場(chǎng)設(shè)置1臺(tái)塔吊作為模板材料的主要垂直運(yùn)輸工具。
6、施工用電情況:現(xiàn)場(chǎng)一級(jí)配電箱、二級(jí)配電箱等均已安裝就位,可以滿足模板加工及
現(xiàn)場(chǎng)施工用電。
-5-
項(xiàng)目專項(xiàng)施工方案
3施工安排
3.1項(xiàng)目管理組織
序號(hào)管理職務(wù)姓名職責(zé)和權(quán)限
1)領(lǐng)導(dǎo)施工過(guò)程中總的組織、安排、協(xié)調(diào)和安全總負(fù)責(zé)。
2)明確項(xiàng)目的各項(xiàng)管理目標(biāo)并分解落實(shí),監(jiān)督檢查項(xiàng)目管理人員履行
1項(xiàng)目經(jīng)理其職責(zé)。
3)組織進(jìn)行模板施工機(jī)械設(shè)備、材料、周轉(zhuǎn)工具、勞務(wù)人員等資源的
配置。
2執(zhí)行經(jīng)理協(xié)助項(xiàng)目經(jīng)理開(kāi)展各項(xiàng)工作
1)組織模板施工方案的編制,審核技術(shù)交底。
3項(xiàng)目總工2)組織現(xiàn)場(chǎng)的技術(shù)復(fù)核、分部分項(xiàng)工程的驗(yàn)收工作。
3)主持模板施工的質(zhì)量管理、施工試驗(yàn)、測(cè)量管理等工作
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 事業(yè)單位新型聘用協(xié)議2024版模板版
- 樂(lè)器買賣合同 集合3篇
- 二零二五年高性能混凝土施工技術(shù)勞務(wù)分包合同范本3篇
- 二零二五年度版權(quán)許可合同:網(wǎng)絡(luò)游戲著作權(quán)授權(quán)2篇
- 2025年度不動(dòng)產(chǎn)房產(chǎn)證購(gòu)房合同附帶房地產(chǎn)稅收減免服務(wù)協(xié)議3篇
- 個(gè)性化2024年事故一次性補(bǔ)償合同版B版
- 二零二五版環(huán)境工程實(shí)習(xí)生實(shí)習(xí)勞動(dòng)合同書2篇
- 專項(xiàng)產(chǎn)品購(gòu)銷協(xié)議樣本版B版
- 泰州學(xué)院《教育研究方法(量化)》2023-2024學(xué)年第一學(xué)期期末試卷
- 2024建筑施工合同示范文本范文
- 巖土工程勘察課件0巖土工程勘察
- 《腎上腺腫瘤》課件
- 2024-2030年中國(guó)典當(dāng)行業(yè)發(fā)展前景預(yù)測(cè)及融資策略分析報(bào)告
- 《乘用車越野性能主觀評(píng)價(jià)方法》
- 幼師個(gè)人成長(zhǎng)發(fā)展規(guī)劃
- 2024-2025學(xué)年北師大版高二上學(xué)期期末英語(yǔ)試題及解答參考
- 批發(fā)面包采購(gòu)合同范本
- 乘風(fēng)化麟 蛇我其誰(shuí) 2025XX集團(tuán)年終總結(jié)暨頒獎(jiǎng)盛典
- 2024年大數(shù)據(jù)分析公司與中國(guó)政府合作協(xié)議
- 一年級(jí)數(shù)學(xué)(上)計(jì)算題專項(xiàng)練習(xí)匯編
- 中醫(yī)基礎(chǔ)理論課件
評(píng)論
0/150
提交評(píng)論