項(xiàng)目專項(xiàng)施工方案
開發(fā)項(xiàng)目F地塊
施工組織設(shè)計(jì)
編號(hào):
編制:
審核:
審批:
中國(guó)建筑第八工程局有限公司
CHINACONSTRUCTIONEIGHTHENGINEERINGDIVISIONCORP.LTD
2023.9發(fā)布2023.9實(shí)施
項(xiàng)目專項(xiàng)施工方案
目錄
1編制依據(jù)......................................................................................................................................................1
2工程概況......................................................................................................................................................7
2.1工程建設(shè)概況.....................................................................................................................................7
2.2建筑設(shè)計(jì)概況.....................................................................................................................................8
2.2.1建筑設(shè)計(jì)概況........................................................................................................................8
2.2.2建筑總平面圖......................................................................................................................10
2.2.3總剖面圖..............................................................................................................................11
建筑效果圖......................................................................................................................................12
2.2.5建筑結(jié)構(gòu)概況......................................................................................................................12
2.2.6機(jī)電及設(shè)備安裝概況..........................................................................................................13
2.3工程施工條件...................................................................................................................................15
3施工部署....................................................................................................................................................16
3.1項(xiàng)目管理組織...................................................................................................................................16
3.2項(xiàng)目管理目標(biāo)...................................................................................................................................22
3.3各項(xiàng)資源安排...................................................................................................................................22
3.4施工流水段劃分及施工工藝流程...................................................................................................24
3.4.1施工區(qū)段的劃分..................................................................................................................24
3.4.2各施工區(qū)段內(nèi)流水段劃分..................................................................................................24
3.4.3施工總流程..........................................................................................................................28
3.5工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施...........................................................................................29
3.6新技術(shù)應(yīng)用計(jì)劃...............................................................................................................................31
4施工進(jìn)度計(jì)劃............................................................................................................................................16
5施工準(zhǔn)備與資源配置計(jì)劃........................................................................................................................32
5.1施工準(zhǔn)備計(jì)劃...................................................................................................................................32
5.1.1技術(shù)準(zhǔn)備............................................................................................................................32
5.1.2施工現(xiàn)場(chǎng)準(zhǔn)備計(jì)劃............................................................................................................39
5.1.3資金準(zhǔn)備..............................................................................................................................40
5.2資源配置計(jì)劃...................................................................................................................................40
勞動(dòng)力配置計(jì)劃..............................................................................................................................40
工程用原材料需要量計(jì)劃..............................................................................................................42
工程施工主要周轉(zhuǎn)材料配置計(jì)劃..................................................................................................42
施工機(jī)具配置計(jì)劃..........................................................................................................................42
測(cè)量設(shè)備配置計(jì)劃..........................................................................................................................44
6主要施工方案............................................................................................................................................32
6.1測(cè)量工程主要施工方法和技術(shù)措施...............................................................................................45
6.1.1總體思路............................................................................................................................45
6.1.2測(cè)量準(zhǔn)備..............................................................................................................................46
6.1.3基準(zhǔn)控制點(diǎn)(網(wǎng))的復(fù)測(cè)..................................................................................................46
6.1.4布設(shè)原則及精度..................................................................................................................46
6.1.5平面控制網(wǎng)..........................................................................................................................47
6.1.6高程控制網(wǎng)的建立..............................................................................................................47
6.2基坑支護(hù)方案...................................................................................................................................48
項(xiàng)目專項(xiàng)施工方案
6.2.1基坑支護(hù)工程概況..............................................................................................................48
6.2.2工藝流程..............................................................................................................................48
6.2.3施工方法..............................................................................................................................49
6.3防水施工方案...................................................................................................................................50
6.3.1防水混凝土施工方法..........................................................................................................51
6.3.2卷材防水施工方法..............................................................................................................52
6.3.3涂膜防水施工方法..............................................................................................................52
6.4鋼筋工程主要施工方法和技術(shù)措施...............................................................................................53
6.4.1工藝流程............................................................................................................................53
6.4.2施工方法............................................................................................................................53
6.4.3質(zhì)量保證措施....................................................................................................................61
6.5模板工程主要施工方法和技術(shù)措施...............................................................................................65
6.5.1模板方案選擇......................................................................................................................66
6.5.2模板體系設(shè)計(jì)......................................................................................................................67
6.5.3模板安裝..............................................................................................................................72
6.5.4模板拆除..............................................................................................................................75
6.5.5模板質(zhì)量保證措施..............................................................................................................76
6.5.6樓板及邊梁精度控制及校核措施......................................................................................76
6.6混凝土工程主要施工方法和技術(shù)措施...........................................................................................77
6.6.1混凝土工程概況..................................................................................................................77
6.6.2混凝土的質(zhì)量檢查標(biāo)準(zhǔn)......................................................................................................81
6.6.3施工縫留設(shè)及施工..............................................................................................................82
6.7.4混凝土養(yǎng)護(hù)..........................................................................................................................82
6.7腳手架工程主要施工方法和技術(shù)措施...........................................................................................83
6.7.1腳手架工程方案選擇概況..................................................................................................83
6.7.2腳手架工程施工組織..........................................................................................................83
6.7.3腳手架搭設(shè)方法..................................................................................................................84
6.7.4腳手架施工技術(shù)措施..........................................................................................................85
6.8砌體工程主要施工方法和技術(shù)措施...............................................................................................85
6.8.1施工組織...............................................................................................................................85
6.8.2砌體工程施工方法..............................................................................................................85
6.8.3技術(shù)措施..............................................................................................................................87
6.9裝飾裝修工程主要施工方法和技術(shù)措施.......................................................................................88
6.9.1裝飾裝修工程概述...............................................................................................................88
6.9.2裝飾工程施工組織..............................................................................................................88
6.9.3裝飾裝修工程施工技術(shù)措施..............................................................................................89
6.10機(jī)電工程主要施工方法和技術(shù)措施.............................................................................................89
6.10.1套管預(yù)留............................................................................................................................89
6.10.2強(qiáng)電安裝工藝流程............................................................................................................91
6.10.3弱電工程施工方案.............................................................................................................96
6.10.4給排水系統(tǒng)工程................................................................................................................98
6.11節(jié)能工程施工技術(shù)措施.............................................................................................................110
6.12季節(jié)性施工方案.........................................................................................................................110
6.12.1雨季施工措施..................................................................................................................110
6.12.2冬季施工措施..................................................................................................................114
項(xiàng)目專項(xiàng)施工方案
6.12.3大風(fēng)施工措施..................................................................................................................115
6.12.4炎熱天氣施工措施..........................................................................................................116
6.13臨時(shí)用電工程施工方案.............................................................................................................116
6.13.1用電說(shuō)明..........................................................................................................................116
6.13.2變壓器容量計(jì)算..............................................................................................................117
6.13.3設(shè)計(jì)配電系統(tǒng)..................................................................................................................118
6.13.4臨時(shí)用電布置..................................................................................................................119
6.13.5配電線路及導(dǎo)線截面的選擇..........................................................................................119
6.13.6配電箱和開關(guān)箱設(shè)計(jì)....................................................................................................120
6.13.7防雷與接地裝置設(shè)計(jì)......................................................................................................120
6.13.8臨時(shí)用電施工安全技術(shù)措施..........................................................................................120
6.14臨時(shí)用水工程施工方案...............................................................................................................122
7施工現(xiàn)場(chǎng)平面布置..................................................................................................................................122
8綠色施工管理計(jì)劃..................................................................................................................................122
8.1資源利用管理計(jì)劃.......................................................................................................................123
8.1.1資源利用管理目標(biāo)..........................................................................................................123
8.1.2資源利用管理機(jī)構(gòu)和職責(zé)分工......................................................................................123
8.1.3資源節(jié)約及利用計(jì)劃及保證措施..................................................................................125
8.1.4資源利用管理制度..........................................................................................................125
8.2環(huán)境管理計(jì)劃...............................................................................................................................126
8.2.1環(huán)境管理目標(biāo)..................................................................................................................126
8.2.2環(huán)境管理組織機(jī)構(gòu)和職責(zé)分工......................................................................................126
8.2.3辨識(shí)重大環(huán)境因素..........................................................................................................128
8.2.4環(huán)境保護(hù)資源配置計(jì)劃..................................................................................................128
8.2.5施工環(huán)境保證措施............................................................................................................129
9進(jìn)度管理計(jì)劃..........................................................................................................................................130
9.1確定施工進(jìn)度控制點(diǎn)...................................................................................................................130
9.2施工進(jìn)度管理組織機(jī)構(gòu)和職責(zé)分工...........................................................................................130
9.3進(jìn)度管理措施...............................................................................................................................132
10質(zhì)量管理計(jì)劃........................................................................................................................................137
10.1工程施工質(zhì)量目標(biāo)及其目標(biāo)分解.............................................................................................137
10.2項(xiàng)目質(zhì)量管理組織機(jī)構(gòu)和職責(zé)分工.........................................................................................139
10.3質(zhì)量管理制度...............................................................................................................................142
10.4質(zhì)量保證措施...............................................................................................................................144
11職業(yè)健康安全管理計(jì)劃........................................................................................................................145
11.1職業(yè)健康安全管理目標(biāo).............................................................................................................145
11.2現(xiàn)場(chǎng)職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工.........................................................................145
11.3職業(yè)健康安全重大危險(xiǎn)源.........................................................................................................149
11.4職業(yè)健康安全資源配置計(jì)劃.....................................................................................................151
11.5施工現(xiàn)場(chǎng)安全生產(chǎn)管理制度.....................................................................................................151
11.6職業(yè)健康安全保證措施.............................................................................................................152
11.6.1組織管理流程................................................................................................................152
11.6.2主要危險(xiǎn)源控制措施....................................................................................................153
11.6.3安全事故的處理............................................................................................................155
12成本管理計(jì)劃........................................................................................................................................155
項(xiàng)目專項(xiàng)施工方案
12.1施工成本目標(biāo)及其成本目標(biāo)分解.............................................................................................155
12.2現(xiàn)場(chǎng)成本管理組織機(jī)構(gòu)和職責(zé)分工.........................................................................................156
12.3施工成本控制措施.....................................................................................................................158
12.3.1人工費(fèi)的控制..................................................................................................................158
12.3.2材料的控制......................................................................................................................158
12.3.3周轉(zhuǎn)工具使用費(fèi)的控制..................................................................................................159
12.3.4機(jī)械控制..........................................................................................................................159
12.3.5現(xiàn)場(chǎng)經(jīng)費(fèi)的控制..............................................................................................................159
12.3.6工程索賠的控制..............................................................................................................159
12.3.7現(xiàn)場(chǎng)水電管理的控制......................................................................................................159
12.4風(fēng)險(xiǎn)控制措施.............................................................................................................................159
13總承包管理計(jì)劃....................................................................................................................................155
13.1總承包管理的方式、原則...........................................................................................................161
總承包管理的方式........................................................................................................................161
總承包管理的原則........................................................................................................................162
13.2對(duì)專業(yè)工程管理范圍及服務(wù)承諾...............................................................................................162
施工總承包對(duì)專業(yè)分包/專項(xiàng)發(fā)包工程的管理........................................................................162
施工總承包對(duì)專業(yè)分包/專項(xiàng)發(fā)包工程的服務(wù)........................................................................163
服務(wù)承諾及保證措施....................................................................................................................165
13.3施工總承包與建設(shè)單位監(jiān)理的配合措施...................................................................................165
施工總承包的責(zé)任以及與建設(shè)單位、監(jiān)理的關(guān)系....................................................................165
施工總承包方與建設(shè)單位的配合原則及措施............................................................................165
施工總承包方與監(jiān)理的配合措施................................................................................................166
13.4總承包各項(xiàng)管理規(guī)定和管理流程...............................................................................................166
項(xiàng)目管理制度................................................................................................................................166
文件控制........................................................................................................................................167
記錄控制........................................................................................................................................168
監(jiān)視和測(cè)量裝置的管理規(guī)定........................................................................................................168
技術(shù)管理規(guī)定................................................................................................................................169
文明施工CI形象達(dá)標(biāo)管理規(guī)定..................................................................................................169
機(jī)具設(shè)備管理規(guī)定........................................................................................................................170
材料管理規(guī)定................................................................................................................................170
現(xiàn)場(chǎng)水電管理規(guī)定........................................................................................................................171
穿插和配合施工管理規(guī)定............................................................................................................172
保衛(wèi)與消防管理規(guī)定....................................................................................................................173
合同和預(yù)決算管理規(guī)定................................................................................................................174
竣工及驗(yàn)收管理規(guī)定....................................................................................................................175
回訪保修管理規(guī)定........................................................................................................................175
安全管理制度................................................................................................................................177
14成品保護(hù)計(jì)劃........................................................................................................................................177
14.1鋼筋工程成品保護(hù).......................................................................................................................177
14.2模板工程成品保護(hù).....................................................................................................................178
14.3混凝土工程成品保護(hù).................................................................................................................179
14.4裝飾裝修工程成品保護(hù).............................................................................................................180
14.5砌體成品保護(hù)措施.....................................................................................................................181
項(xiàng)目專項(xiàng)施工方案
14.6防水工程成品保護(hù)措施.............................................................................................................181
14.7電氣工程成品保護(hù)措施.............................................................................................................181
14.8暖通空調(diào)工程成品保護(hù)措施.....................................................................................................183
14.9給排水工程成品保護(hù)措施.........................................................................................................184
14.10交工前成品和設(shè)備保護(hù)措施.....................................................................................................185
15節(jié)能減排管理計(jì)劃................................................................................................................................185
15.1節(jié)能減排管理目標(biāo).....................................................................................................................185
15.2節(jié)能降耗管理機(jī)構(gòu)和職責(zé)分工.................................................................................................186
15.3資源節(jié)約及利用計(jì)劃及保證措施.............................................................................................189
15.4節(jié)能降耗管理措施.....................................................................................................................189
15.5節(jié)約用水.....................................................................................................................................191
16新技術(shù)應(yīng)用計(jì)劃......................................................................................................................................191
17信息化施工管理......................................................................................................................................192
17.1協(xié)商...............................................................................................................................................193
17.2內(nèi)部溝通與交流...........................................................................................................................193
17.2.1內(nèi)部溝通與交流的主要內(nèi)容..........................................................................................193
17.2.2內(nèi)部溝通與交流的實(shí)施..................................................................................................193
17.3外部溝通與交流...........................................................................................................................193
17.3.1外部溝通與交流的對(duì)象及內(nèi)容................................
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024版房屋買賣定金合同(含智能家居生態(tài)圈建設(shè))模板3篇
- 2024年度服務(wù)器租賃合同(含災(zāi)備中心服務(wù))3篇
- 2024版導(dǎo)演與影視制作公司聘用合同模板3篇
- 2024年承包土地租賃合同(含農(nóng)業(yè)品牌建設(shè))
- 湖南公路工程施工監(jiān)理合同(35篇)
- 2024版幼兒園安保服務(wù)外包合同3篇
- 2024年度委托代建合同(房地產(chǎn))3篇
- 2024「成都上灶師父招聘及餐飲行業(yè)經(jīng)營(yíng)管理合同」2篇
- 2024版智能家居房屋抵押借款合同范本細(xì)則3篇
- 2024年版教育機(jī)構(gòu)學(xué)生食堂海鮮供貨合同3篇
- 完整版場(chǎng)記單模板
- 實(shí)木家具工藝標(biāo)準(zhǔn)(全流程)
- 高一語(yǔ)文必修一4篇古文 詞類活用(課堂PPT)
- 商業(yè)發(fā)票Commercial Invoice模板2
- OPERA系統(tǒng)培訓(xùn)ppt課件
- 電鍍工藝-電鍍鎳
- 幼小銜接中幼兒園與小學(xué)合作的國(guó)內(nèi)外研究現(xiàn)狀分析
- 110Kv輸變電工程電氣安裝技術(shù)交底
- 錄屏軟件Camtasia_Studio使用教程
- 工廠常用英語(yǔ)
- 海上平臺(tái)場(chǎng)址工程地質(zhì)勘察規(guī)范
評(píng)論
0/150
提交評(píng)論