房建開發(fā)區(qū)院區(qū)項目
建筑幕墻安裝工程
專項施工方案
(格式最終版)
編制:
審核:
審批:
目錄
1編制依據(jù)................................................................................................................................1
2工程概況................................................................................................................................3
2.1工程建設(shè)概況...................................................................................................................3
2.2設(shè)計概況...........................................................................................................................3
2.3工程施工條件...................................................................................................................6
3施工安排................................................................................................................................7
3.1項目管理組織...................................................................................................................7
3.2項目管理目標(biāo)...................................................................................................................9
3.3各項資源供應(yīng)方式...........................................................................................................9
3.4施工流水段的劃分及施工工藝流程.............................................................................10
3.5工程施工重點和難點分析及應(yīng)對措施.........................................................................11
3.6新技術(shù)應(yīng)用要求.............................................................................................................12
4施工進度計劃......................................................................................................................13
5施工準(zhǔn)備與資源配置計劃..................................................................................................14
5.1施工準(zhǔn)備計劃.................................................................................................................14
5.2資源配置計劃.................................................................................................................16
6施工方法及工藝要求..........................................................................................................18
6.1測量放線方案.................................................................................................................18
6.1.1方案及技術(shù)參數(shù)......................................................................................................18
6.1.2工藝流程..................................................................................................................18
6.1.3施工要點..................................................................................................................18
6.1.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................21
6.2埋件施工方案.................................................................................................................21
6.2.1方案及技術(shù)參數(shù)......................................................................................................21
6.2.2工藝流程..................................................................................................................22
6.2.3施工要點..................................................................................................................22
6.2.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................25
6.3半隱框玻璃幕墻施工方案.............................................................................................25
6.3.1方案及技術(shù)參數(shù).......................................................................................................25
6.3.2工藝流程..................................................................................................................25
6.3.3施工要點..................................................................................................................26
6.3.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................30
6.4點支承玻璃幕墻施工方案.............................................................................................30
6.4.1方案及技術(shù)參數(shù)......................................................................................................30
6.4.2工藝流程..................................................................................................................30
6.4.3施工要點..................................................................................................................30
6.4.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................34
6.5金屬幕墻施工方案.........................................................................................................35
6.5.1方案及技術(shù)參數(shù)......................................................................................................35
6.5.2工藝流程..................................................................................................................35
6.5.3施工要點..................................................................................................................35
6.5.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................40
6.6雨棚施工方案.................................................................................................................41
6.6.1方案及技術(shù)參數(shù)......................................................................................................41
6.6.2工藝流程..................................................................................................................42
6.6.3施工要點..................................................................................................................42
6.6.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................42
6.7采光頂施工方案.............................................................................................................43
6.7.1方案及技術(shù)參數(shù)......................................................................................................43
6.7.2工藝流程..................................................................................................................44
6.7.3施工要點..................................................................................................................44
6.7.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................45
6.8玻璃欄板施工方案.........................................................................................................46
6.8.1方案及技術(shù)參數(shù)......................................................................................................46
6.8.2工藝流程..................................................................................................................46
6.8.3施工要點..................................................................................................................46
I
6.8.4質(zhì)量標(biāo)準(zhǔn)..................................................................................................................48
6.9驗收標(biāo)準(zhǔn).........................................................................................................................48
6.10驗收程序.....................................................................................................................53
6.11驗收內(nèi)容.....................................................................................................................53
6.12驗收人員.....................................................................................................................54
7各項管理計劃......................................................................................................................55
7.1綠色施工管理計劃.........................................................................................................55
7.2資源利用管理計劃.........................................................................................................59
7.3進度管理計劃...............................................................................................................62
7.4質(zhì)量管理計劃...............................................................................................................67
7.5成品保護計劃...............................................................................................................74
7.6安全管理計劃...............................................................................................................76
7.6.1職業(yè)健康安全管理目標(biāo)..........................................................................................76
7.6.2現(xiàn)場職業(yè)健康安全管理組織機構(gòu)和職責(zé)分工......................................................76
7.6.3職業(yè)健康安全重大危險源......................................................................................79
7.6.4職業(yè)健康安全資源配置計劃..................................................................................79
7.6.5專項施工安全方案編制計劃..................................................................................79
7.6.6施工現(xiàn)場安全生產(chǎn)管理制度..................................................................................79
7.6.7職業(yè)健康安全保證措施..........................................................................................81
7.6.7.1組織措施.........................................................................................................81
7.6.7.2技術(shù)措施.........................................................................................................83
7.6.7.3監(jiān)測監(jiān)控措施.................................................................................................90
8施工管理作業(yè)人員配備和分工..........................................................................................92
8.1施工組織體系.................................................................................................................92
8.2勞動力計劃.....................................................................................................................92
8.3操作人員條件.................................................................................................................93
9應(yīng)急預(yù)案..............................................................................................................................94
9.1應(yīng)急指揮機構(gòu)及職責(zé)...................................................................................................94
II
9.2應(yīng)急救援程序...............................................................................................................95
9.3應(yīng)急處置措施...............................................................................................................96
9.4應(yīng)急物資準(zhǔn)備...............................................................................................................97
9.5應(yīng)急響應(yīng)、演練...........................................................................................................98
9.6應(yīng)急救援路線圖...........................................................................................................98
10計算書和相關(guān)圖紙............................................................................................................99
10.1計算書.........................................................................................................................99
10.2深化設(shè)計圖紙.............................................................................................................99
1編制依據(jù)
序號類別文件名稱編號
1《中華人民共和國建筑法》國家主席令第91號
2《中華人民共和國安全生產(chǎn)法》國家主席令第70號
3《中華人民共和國環(huán)境保護法》國家主席令第22號
4國家行政文件《建設(shè)工程質(zhì)量管理條例》國務(wù)院令第279號
5《建設(shè)工程安全生產(chǎn)管理條例》國務(wù)院令第393號
住房城鄉(xiāng)建設(shè)部辦公廳關(guān)于實施《危險性較大的分
6建辦質(zhì)【2018】31號
部分項工程安全管理規(guī)定》有關(guān)問題的通知
7《危險性較大的分部分項工程安全管理規(guī)定》住房城鄉(xiāng)建設(shè)部37號令
8《建設(shè)工程施工現(xiàn)場供用電安全規(guī)范》GB50194-2014
9《建設(shè)工程施工現(xiàn)場消防安全技術(shù)規(guī)范》GB50720-2011
10《建筑施工安全技術(shù)統(tǒng)一規(guī)范》GB50870-2013
11《建筑工程綠色施工規(guī)范》GB/T50905-2014
12《綠色建筑評價標(biāo)準(zhǔn)》GB/T50378-2014
13《建筑設(shè)計防火規(guī)范》GB50016-2014
14《建筑裝飾裝修工程質(zhì)量驗收標(biāo)準(zhǔn)》GB50210-2018
15《建筑工程施工質(zhì)量驗收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
16《建筑工程施工質(zhì)量評價標(biāo)準(zhǔn)》GB/T50375-2016
國家行業(yè)規(guī)范
17《建設(shè)工程文件歸檔規(guī)范》GB/T50328-2014
18《建筑幕墻》GBT21086-2007
19《金屬與石材幕墻工程技術(shù)規(guī)范》JGJ133-2001
20《玻璃幕墻工程技術(shù)規(guī)范》JGJ102-2003
21《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
22《高處作業(yè)吊籃》GB/T19155-2017
23《高處作業(yè)吊籃安裝、拆卸、使用技術(shù)規(guī)程》JB/T11699-2013
24《建筑施工工具式腳手架安全技術(shù)規(guī)范》JGJ102-2010
25《建筑施工腳手架安全技術(shù)統(tǒng)一標(biāo)準(zhǔn)》GB51210-2016
1
26《建筑機械使用安全技術(shù)規(guī)程》JGJ33-2012
《江蘇省關(guān)于推進安全生產(chǎn)領(lǐng)域改革發(fā)展的實施意
27蘇發(fā)[2017]18號
見》
關(guān)于印發(fā)《江蘇省房屋建筑和市政基礎(chǔ)設(shè)施工程危
28險性較大的分部分項工程安全管理實施細則(2019蘇建質(zhì)安[2019]378號
地方行政文件
版)》的通知
29《江蘇省關(guān)于促進建筑業(yè)改革發(fā)展的意見》蘇政發(fā)[2017]151號
30《江蘇省建筑施工特種作業(yè)人員管理暫行辦法》蘇建管質(zhì)[2009]5號
31《建設(shè)工程質(zhì)量檢測規(guī)程》DGJ32/J21—2009
32《江蘇省建筑施工安全生產(chǎn)條件評價規(guī)范》DGJ32/TJ55—2012
33《建筑幕墻工程質(zhì)量驗收規(guī)程》DGJ32/J124—2011
地方規(guī)范標(biāo)準(zhǔn)
34《優(yōu)質(zhì)建筑工程施工質(zhì)量驗收評定標(biāo)準(zhǔn)》DGJ32/TJ04-2010
35《江蘇省建筑施工安全質(zhì)量標(biāo)準(zhǔn)化管理標(biāo)準(zhǔn)》DGJ32/J66-2008
36《公共建筑節(jié)能設(shè)計標(biāo)準(zhǔn)》DGJ32/J96-2010
連云港市第一人民醫(yī)院開發(fā)區(qū)院區(qū)土建及安裝施工
37合同/
合同
連云港市第一人民醫(yī)院開發(fā)區(qū)院區(qū)土建及安裝工程
38設(shè)計文件/
幕墻施工圖
連云港市第一人民醫(yī)院開發(fā)區(qū)院區(qū)土建及安裝工程
39招投標(biāo)文件/
招標(biāo)文件
40企業(yè)技術(shù)標(biāo)準(zhǔn)建筑裝飾裝修工程施工技術(shù)標(biāo)準(zhǔn)ZJQ08-SGJB210-2017
2
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱工程性質(zhì)
公共建筑
連云港市經(jīng)濟技術(shù)開發(fā)區(qū)昌圩路
建設(shè)規(guī)模工程地址
北側(cè)、環(huán)湖路西側(cè)地塊
157279m2(地上:106518m2,
總占地面積總建筑面積
地下:50761m2)
構(gòu)件式玻璃幕墻、點式玻璃幕
建設(shè)單位項目承包范圍墻、鋁板幕墻、玻璃欄桿、雨
棚、地彈門、采光頂
設(shè)計單位主要分包工程
幕墻工程
勘察單位
質(zhì)量
確保“揚子杯”,爭創(chuàng)“國優(yōu)”
合同
243日歷天,2021年9月25日-
監(jiān)理單位要求工期
2022年5月25日
中國建筑第八工程局有限公施工期間杜絕一切人身傷亡和重
總承包單位安全
司大質(zhì)量安全事故
工程主要功能或用途醫(yī)院
2.2設(shè)計概況
門診醫(yī)技樓幕墻工程建筑高度25.4m,幕墻面積約3.28萬m2。幕墻工程主要包括構(gòu)
件式玻璃幕墻(5257m2):主要位于門診醫(yī)技樓各立面;金屬板幕墻(22000m2):主要
用于各立面包梁、包柱、連廊及實體外墻飾面;效果圖見圖2.2-1。
3
圖2.2-1效果圖
主要系統(tǒng)一:構(gòu)件式玻璃幕墻
構(gòu)件式玻璃幕墻分為兩部分,分別為橫明豎隱和豎明橫隱。
豎明橫隱玻璃幕墻位于門診醫(yī)技樓一層,明框立柱采用150系列,材質(zhì)為6063-T6;隱
框橫梁采用70系列,跨度大于1.5m時材質(zhì)為6063-T6,跨度小于等于1.5m時材質(zhì)為6063-
T5;下部玻璃采用6LOW-E+12Ar+6mm均質(zhì)鋼化中空玻璃,上部玻璃采用6LOW-E+12Ar+6mm彩
釉網(wǎng)點均質(zhì)鋼化中空玻璃;下部(衛(wèi)生間)玻璃采用6LOW-E+12Ar+6mm背漆均質(zhì)鋼化中空
玻璃。節(jié)點詳見圖2.2-2及圖2.2-3。
圖2.2-2豎明橫隱玻璃幕墻橫剖節(jié)點圖2.2-3豎明橫隱玻璃幕墻豎剖節(jié)點
橫明豎隱玻璃幕墻位于門診醫(yī)技樓二層至五層。其中,門診入口上部橫明豎隱玻璃
幕墻隱框立柱采用135系列,材質(zhì)為6063-T6;明框橫梁采用70系列,材質(zhì)為6063-T5;玻璃
4
采用6LOW-E+16Ar+6mm均質(zhì)鋼化中空玻璃(板塊面積≤3平方)、8LOW-E+12Ar+8mm
均質(zhì)鋼化中空玻璃(4≤板塊面積>3平方);兩種規(guī)格玻璃混合使用;梁上下部玻璃采用
6LOW-E+12Ar+6mm彩釉網(wǎng)點均質(zhì)鋼化中空玻璃;其余位置橫明豎隱玻璃幕墻隱框立柱
采用120系列,材質(zhì)為6063-T5;明框橫梁采用70系列,材質(zhì)為6063-T5;下部玻璃采用
6LOW-E+12Ar+6mm均質(zhì)鋼化中空玻璃;上部玻璃采用6LOW-E+12Ar+6mm彩釉網(wǎng)點均
質(zhì)鋼化中空玻璃;下部(衛(wèi)生間)玻璃采用6LOW-E+12Ar+6mm背漆均質(zhì)鋼化中空玻璃。
節(jié)點詳見圖2.2-4及圖2.2-5。
圖2.2-4橫明豎隱玻璃幕墻橫剖節(jié)點圖2.2-5橫明豎隱玻璃幕墻豎剖節(jié)點
主要系統(tǒng)二:金屬板幕墻
包梁鋁板幕墻采用80*40*4熱浸鍍鋅鋼管作為立柱,橫梁采用40*40*4熱浸鍍鋅鋼管;
包柱及實體墻面位置鋁板幕墻采用100*50*4熱浸鍍鋅鋼管作為立柱,橫梁采用40*40*4熱
浸鍍鋅鋼管。鋼管材質(zhì)均為Q235。面板根據(jù)立面選用3mm鋁單板或4mm穿孔鋁板。
圖2.2-6鋁板幕墻橫剖節(jié)點
5
圖2.2-8鋁板幕墻豎剖節(jié)點1圖2.2-9鋁板幕墻豎剖節(jié)點2
2.3工程施工條件
極端最高溫度及期限40.6℃1天最大雨量及雨季時間192.1mm/天
建設(shè)地點氣溫
氣象狀況極端最低溫度及期限-18℃1天最大風(fēng)力、風(fēng)向及發(fā)生時間23.7m/s
工程水文
地質(zhì)粗糙類型B類
地質(zhì)狀況
工程用主材供應(yīng)情況可正常供應(yīng)
當(dāng)?shù)刭Y源電力供應(yīng)情況已引入
供應(yīng)情況交通情況場內(nèi)道路已硬化,場外交通便利
水資源供應(yīng)情況已引入
6
3施工安排
3.1項目管理組織
表3.1-1項目管理人員
序號部門名稱崗位名稱人員姓名備注
項目經(jīng)理楊進潤
項目部
1執(zhí)行經(jīng)理謝駿騰
領(lǐng)導(dǎo)
幕墻經(jīng)理陳尚賢
土建生產(chǎn)經(jīng)理袁賽
2工程計劃部
幕墻生產(chǎn)經(jīng)理第海清
商務(wù)經(jīng)理趙志浩
3商務(wù)合約部
幕墻商務(wù)工程師陳艅航
總工程師韓方圓
質(zhì)量總監(jiān)張忠亞
4技術(shù)質(zhì)量部
幕墻技術(shù)負責(zé)人祁昌偉
幕墻質(zhì)量主管由起凡
5安全環(huán)保部安全總監(jiān)王寧南
物資經(jīng)理朱肖
6采購管理部
幕墻物資工程師劉毓
表3.1-2幕墻主要管理人員及職責(zé)分工
序號管理職務(wù)姓名職稱(資質(zhì))職責(zé)和權(quán)限
1、履行項目承包合同,執(zhí)行質(zhì)量方針,遵守公司規(guī)定,
實現(xiàn)工程質(zhì)量目標(biāo)。組織項目質(zhì)量策劃和質(zhì)量計劃的編
制,實施及修改工作。
1項目經(jīng)理陳尚賢中級工程師2、科學(xué)組織和管理進入項目工地的人財物資源協(xié)調(diào)分承
包方之間關(guān)系,做好人力、物力和機械設(shè)備的調(diào)配與供應(yīng),
及時解決施工中出現(xiàn)的問題,保證履行與公司簽訂的承包
合同,提高綜合經(jīng)濟效益,圓滿完成任務(wù)。
1、負責(zé)設(shè)計、施工交底、技術(shù)簽證。
2、組織編制工程項目施工組織設(shè)計,包括工程進度計劃
技術(shù)負責(zé)和技術(shù)方案,制定安全生產(chǎn)和質(zhì)量保證措施,并組織實
2祁昌偉助理工程師
人施。
3、全面控制、及時報告工程的安裝進度和質(zhì)量情況。
4、協(xié)助項目經(jīng)理做好項目工程的驗收工作。
1、組織調(diào)整施工人員、機械、工具。
2、對工程的施工生產(chǎn)、進度計劃、現(xiàn)場總平面協(xié)調(diào)及管
理全面負責(zé),確保工程施工順利進行。
3、對工程施工與其他各指定分包之間的施工生產(chǎn)進行協(xié)
3生產(chǎn)經(jīng)理第海清助理工程師調(diào)。
4、負責(zé)施工中各專業(yè)工種之間和其它專業(yè)項目的協(xié)調(diào)及
配合,并組織實施結(jié)構(gòu)各專業(yè)管理人員、施工日常工作
的落實,組織各分項工程的施工、驗收工作等,及時解
決施工中出現(xiàn)的各種問題。
1、主持做好單位工程成本核算,做好工程用料、人工費
7
的分析,結(jié)合工程項目開展定額分析活動,核定各種資
源消耗情況,對工程預(yù)算情況提出建議和意見,并及時
反饋給公司領(lǐng)導(dǎo)。
商務(wù)工程陳艅航/2、參與在建項目的預(yù)算和竣工后的決算工作,審核在建
4師項目已完工程月度用款計劃和月度付款額。
3、參與各類合同的洽談,掌握市場價格信息,對工程造
價作出評價分析。
4、參與投標(biāo)文件、標(biāo)書編制和合同評審,收集各工程項
目的造價資料,參與工程建設(shè)、工程預(yù)算談判及工程驗
收工作。
1、組織對進場材料進行質(zhì)量和數(shù)量驗收,提供材質(zhì)證
明,需要進行復(fù)試的及時會同施工員辦理。
2、材料進場前應(yīng)把材料樣品及生產(chǎn)許可證、產(chǎn)品合格
物資工程證、出廠證、檢驗情況等以材料申報表形式報監(jiān)理及建
6劉毓/
師設(shè)單位認(rèn)可,封樣后再行購買進場。
3、負責(zé)材料和工具的管理,建立料具領(lǐng)、發(fā)、退手續(xù)和
限額領(lǐng)料制度,建立料具帳卡,做到帳卡相符,按時填
報有關(guān)報表。
1、對職工進行進場或上崗前安全教育和文明施工教育,
并經(jīng)常深入現(xiàn)場檢查指導(dǎo)安全和文明施工,發(fā)現(xiàn)問題及
時糾正或提出整改意見,必要時簽發(fā)書面通知,限期整
7安全主管//
改。
2、組織開展創(chuàng)建“標(biāo)化工地”或“文明工地”的達標(biāo)活動,
監(jiān)督有關(guān)防漏水、防漏電、環(huán)保、衛(wèi)生等措施的實施。
1、配合技術(shù)負責(zé)人、技術(shù)員做好竣工資料的歸檔工作。
2、通過網(wǎng)絡(luò)辦公平臺及時傳遞管理信息,并做好相關(guān)記
由起凡
8資料員助理工程師錄。
(兼職)
3、做好項目部、上級和外部文件、資料簽收、登記、保
管、傳遞工作。
1、對其管理的單位工程(施工區(qū)域或?qū)I(yè))范圍內(nèi)的安
全、生產(chǎn)、文明施工全面負責(zé)。
2、嚴(yán)格執(zhí)行專項安全方案,按施工技術(shù)措施和安全技術(shù)
操作規(guī)程要求,結(jié)合工程特點,以書面方式向班組進行
安全技術(shù)交底,履行簽字手續(xù),做好交底記錄。
3、對臨邊、洞口防護設(shè)施、消防設(shè)施及器材、危險性較
大的分部分項工程提出驗收申請,并參加驗收。
專業(yè)工程第海清
9助理工程師4、參加危險作業(yè)審核、安生生產(chǎn)例會、安全檢查,對管
師(兼職)
轄范圍內(nèi)的安全隱患制定整改措施,落實整改。
5、負責(zé)對危險性較大分部分項工程施工的現(xiàn)場指導(dǎo)和管
理。
6、負責(zé)對管轄范圍內(nèi)的特種作業(yè)人員開展定期安全教
育,督促指導(dǎo)班組開展班前安全活動并做好記錄。
7、發(fā)生生產(chǎn)安全事故,立即向項目經(jīng)理報告,組織搶救
傷員和人員疏散,并保護好現(xiàn)場,配合事故調(diào)查,認(rèn)真
8
落實防范措施。
1、接受設(shè)計、施工交底、簽證,做好施工隊的施工工序
交底。
10質(zhì)量主管由起凡助理工程師2、熟悉施工現(xiàn)場、施工內(nèi)容、施工工藝流程。
3、全面控制、報告項目工程安裝進度和質(zhì)量。
4、做好第一手資料的收集、整理工作,填寫質(zhì)量日記。
3.2項目管理目標(biāo)
項目管理目標(biāo)名稱目標(biāo)值
工期243日歷天,2021年9月25日-2022年5月25日
質(zhì)量目標(biāo)確?!皳P子杯”,爭創(chuàng)“國優(yōu)”
安全目標(biāo)施工期間杜絕一切人身傷亡和重大質(zhì)量安全事故
文明施工目標(biāo)省級文明示范工地
CI目標(biāo)滿足公司相應(yīng)規(guī)范要求
3.3各項資源供應(yīng)方式
1、勞務(wù)資源安排一覽表
施工項目專業(yè)施工隊資質(zhì)開始施工分包分包商
建設(shè)工期責(zé)任人
名稱名稱要求時間方式選擇方式
江蘇安泰勞務(wù)勞務(wù)資質(zhì)項目選擇公司陳尚賢、陳
幕墻安裝2021.9.25243天勞務(wù)
服務(wù)有限公司不分等級批準(zhǔn)艅航
2、工程用大宗物資供應(yīng)安排一覽表
物資名稱采購單位擬選供應(yīng)商采購地點要求進場時間責(zé)任人
天津友發(fā)、江陳尚賢、
鋼材中國建筑第八工程局有限公司天津、江蘇2021.9
蘇國強劉毓
陳尚賢、
鋁型材中國建筑第八工程局有限公司山東華建山東2021.9
劉毓
陳尚賢、
玻璃中國建筑第八工程局有限公司臺玻、信義江蘇2022.1
劉毓
陳尚賢、
鋁板中國建筑第八工程局
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 藥用植物鑒賞課程設(shè)計
- 植物檢疫學(xué)課程設(shè)計
- 英文散文選讀課程設(shè)計
- 素描班幾何圖形課程設(shè)計
- 火電項目風(fēng)險與防范
- 自述機械課程設(shè)計過程
- 縣社會穩(wěn)定風(fēng)險評估工作檔案資料明細
- 《刑罰的消滅》課件
- 托班吸管創(chuàng)意課程設(shè)計
- 互聯(lián)網(wǎng)業(yè)務(wù)員用戶維護總結(jié)
- 金融模擬交易實驗報告
- 國家開放大學(xué)電大本科《古代小說戲曲專題》2023期末試題及答案(試卷號:1340)
- 加德納多元智能理論教學(xué)課件
- 北師大版數(shù)學(xué)八年級上冊全冊教案
- 現(xiàn)代文閱讀之散文
- 從業(yè)人員在安全生產(chǎn)方面的權(quán)利和義務(wù)
- 新開模具清單
- 抗菌藥物臨床應(yīng)用指導(dǎo)原則(2023年版)
- 2023年軍政知識綜合題庫
- 2023-2024學(xué)年福建省福州市小學(xué)語文 2023-2024學(xué)年六年級語文期末試卷期末評估試卷
- YY 0286.1-2019專用輸液器第1部分:一次性使用微孔過濾輸液器
評論
0/150
提交評論