文檔簡(jiǎn)介
1、Good is good, but better carries it.精益求精,善益求善。uj康定新城住2(商1)鉆孔灌注樁施工方案四川雙馬宜賓水泥制造有限公司二期建設(shè)工程廠區(qū)東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟(商1)機(jī)械沖擊鉆孔鉿灌注樁工程專項(xiàng)施工方案 四川三一 編制單位:四川三一工程建設(shè)(集團(tuán))有限公司東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)項(xiàng)目部編制時(shí)間: 2010年10月12日 機(jī)械沖鉆孔鉿灌注樁專項(xiàng)施工組織設(shè)計(jì)(方案)自審表工 程 名 稱東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟樓工程工 程 地 點(diǎn)甘孜州康定新縣城內(nèi)(榆林村)建 設(shè) 單 位甘孜州康定鍋莊城旅游置業(yè)投資有限責(zé)任公司建 筑 面 積住2棟:19997.
2、60商1棟:2807.50結(jié) 構(gòu) 類 型灌注樁基礎(chǔ),剪力墻工 程 造 價(jià)設(shè) 計(jì) 單 位成都市建筑設(shè)計(jì)研究院監(jiān) 理 單 位四川華宇工程監(jiān)理有限公司層 數(shù) 高 度13+1F(42.30M)建筑物跨度M開(kāi)、竣 工 日期2010,10,152012,7,25編 制 人梁開(kāi)成項(xiàng) 目 負(fù) 責(zé) 人祁 偉項(xiàng)目安全負(fù)責(zé)人葉 建參加會(huì)審人員簽字部 門職 務(wù)職 稱簽 名審批結(jié)論技術(shù)負(fù)責(zé)人簽字(蓋章)日期東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟(商1)機(jī)械沖擊鉆孔鉿灌注樁工程專項(xiàng)施工方案編 制 人: 審 核 人: 審 批 人: 二0一0年十月十二日 東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟(商1) 機(jī)械沖擊鉆孔鉿灌注樁工程施工方案目 錄
3、第一章 工程概況第一節(jié) 工程基本情況06第二節(jié) 工程相關(guān)情況06第二章 工程施工條件第一節(jié) 工程地形地貌條件07第二節(jié) 工程地質(zhì)構(gòu)造07第三節(jié) 工程水文條件07第三章 工程施工依據(jù)第一節(jié) 工程圖紙文件08第二節(jié) 地質(zhì)勘察文件08第三節(jié) 采用的施工標(biāo)準(zhǔn)、規(guī)范08第四章 施工準(zhǔn)備第一節(jié) 人力資源準(zhǔn)備09第二節(jié) 物資設(shè)備計(jì)劃11第三節(jié) 作業(yè)條件準(zhǔn)備11第五章 施工計(jì)劃第一節(jié) 施工計(jì)劃12第二節(jié) 工期保證措施12第三節(jié) 技術(shù)保證措施13第六章 施工組織機(jī)構(gòu)第一節(jié) 施工組織機(jī)構(gòu)14第二節(jié) 組織機(jī)構(gòu)管理16第七章 鉆孔灌注樁施工工藝及技術(shù)措施第一節(jié) 施工工藝流程18第二節(jié) 成孔工藝及技術(shù)措施19第三節(jié) 鋼
4、筋籠的制作安裝22第四節(jié) 樁芯混凝土24第五節(jié) 混凝土灌注成樁28第六節(jié) 混凝土灌注質(zhì)量檢測(cè)32第八章 工程質(zhì)量保證措施第一節(jié) 質(zhì)量控制目標(biāo)34第二節(jié) 質(zhì)量管理體系34第三節(jié) 質(zhì)量保證措施34第四節(jié) 質(zhì)量控制措施35第九章 安全生產(chǎn)保證措施第一節(jié) 安全管理目標(biāo)36第二節(jié) 安全管理組織機(jī)構(gòu)37第三節(jié) 安全管理制度38第四節(jié) 安全組織技術(shù)措施39第五節(jié) 安全施工技術(shù)措施40第六節(jié) 重點(diǎn)環(huán)節(jié)安全規(guī)程41第七節(jié) 施工現(xiàn)場(chǎng)臨時(shí)用電安全管理42第八節(jié) 施工安全風(fēng)險(xiǎn)分析44第十章 確保健康、環(huán)保、文明施工的技術(shù)措施第一節(jié) 健康、環(huán)保、文明施工目標(biāo)49第二節(jié) 文明施工組織體系50第三節(jié) 文明施工組織措施50第
5、十一章 職業(yè)健康、安全和環(huán)境保護(hù)(HSE)實(shí)施計(jì)劃第一節(jié) 方針與目標(biāo)54第二節(jié) HSE管理保證體系56第十二章 施工風(fēng)險(xiǎn)分析第一節(jié) 施工項(xiàng)目風(fēng)險(xiǎn)72第二節(jié) 風(fēng)險(xiǎn)評(píng)價(jià)與分析73第十三章 雨季施工措施第一節(jié) 雨季施工措施75第二節(jié) 成品保護(hù)75第十四章 施工平面布置第一節(jié) 平面布置原則75第二節(jié) 平面布置圖76二0一0年十月十二日編制92mitjana ponderada, mètode de mitjana de desplaçament ponderada, mètode d'identificació específica. 1, e
6、l primer en el primer mètode: un primer inventari d'ingressos, per primera vegada com la condició prèvia, utilitzant aquests mètodes d'inventaris es basa en ingressos primer en la població els elements que el preu de cost d'alguna cosa. 2 i l'últim, fina
7、lment fora mètode: aquest mètode i FIFO mètode en canvi, suposa ingressos després de l'emissió de valors, utilitzant aquest mètode es basa en la renda final en la valoració de preu de les accions d'inventari de les existències. 3, el mètode mitjan
8、a ponderada: aquest mètode es basa en l'equilibri de mes inventari valor més preu unitat mitjana de renda mensual. 4, el mètode de mitjana mòbil ponderada: inventari es basa en les originals equilibri quantitat i ingressos existències en aquest termini de la suma, dividi
9、t per l'inventari amb l'inventari d'ingressos equilibri original i quantitat, com el preu mitjà d'inventaris. Quan canvis d'ingressos en el preu de les accions, és necessari calcular un preu mitjà ponderat. 5, el mètode d'identificació específica
10、: en cada tema o en rebre l'inventari, identificar inventari entrant al cost històric com a destinataris o el cost real sobre el tema. 93rd mètodes de valoració fàbrica inventari, matèria i altres fons de reserva com a cost previst; en curs i productes acabats, preus pel
11、 mètode d'identificació específica, el mètode de valoració que s'estableixi no es canviïn. Classificació material 94th de materials de l'empresa industrial es poden dividir en sis categories: 1, matèries primeres i els principals materials; 2, prod
12、uctes semielaborats adquirits; 3, material auxiliar, 4, combustible; 5, reparació de peces de recanvi 6, embalatge. 95th facilitat de gestió i comptabilitat dels materials, la fàbrica ha de produir categoria de material del catàleg del material fix número, nom, mida, unitats
13、 de mesura. 96th material al compte de resultats: 1, renda material es refereix a la subcontractació. En els comptes. 3, materials casolans, reciclatge de ferralla de taller ha de ser puntual en els procediments de la biblioteca, ha de ser omplert una "llista de material". 4, restant
14、retornada al magatzem al taller, cal Emplenes crèdit de botiga, el taller ha estat utilitzant, però el mes que ve ha de seguir per consumir materials, com un veritable Comptabilitat de costos es poden prendre en el mes de "compliment" aproximació a omplir aquest mes, botiga
15、crèdit fins al proper mes per preparar la "recollir". 97è número material de la comptabilitat: 1 es refereixen principalment al taller, material emès requisitioning, gestió utilitzant, delegat de l'emissió i venda de materials material extern. 2, el taller
16、 per a la producció necessita utilitzant una varietat de materials o administracions utilitzant una varietat de materials han de ser basat en un pla (pressupost) i ordre de producció i fixa, pels departaments responsable que omplint "Billde superfície convergeixen amb el paviment
17、 llis. (2) comprovar la construcció Cambra gallines ciment base de formigó en el seu conjunt. Excavació de rasa quan comprovi la ubicació exacta del pou, quan s'aboca a Guan Ji, Ji de Jing Jing amplada serà comprovat una vegada regat prou. (3) la fabricació seleccio
18、nat pati, treure terra, plana, plantilles de disseny, reforç, segons collocació etiqueta prefabricades de disseny, salut, a força de disseny hissar a l'obra després d'installació. (4) Connexió de canonades i arquetes d'HDPE: tubs amb maó o formigó
19、arquetes connexió, utilitzar un pinzell o cotó toca la paret de la superfície exterior de la canonada net i uniformement recobert amb adhesiu PVC, llavors objecte de dúmping en una capa de sorra seca i gruixuda a la part superior, curar 10-20min, va formar la capa intermediari Ru
20、gositat superficial. Depenent de la longitud de la capa d'intermediari en funció de la longitud de la canonada construir dins d'un clavegueram i inspeccions de cua a la paret del pou amb morter de ciment. Mig nivell interfície construcció eines i materials necessaris per satis
21、fer les necessitats en la taula següent. Eina de construcció capa intermediari interfície feina i eina de projectes de treball material taula i handsaw material tub trencat i ploma universal i volum peus neteja cara cotó base superfície processament raspall de cabell fent ma
22、terial sorra aspre capa intermediari, i canonada Dang de PVC enganxosa rebuda l'agent està situat a baixes i pantà i les aigües subterrànies mica alta de lots Shi, de liquidació no uniforme adaptat basat, comprovar bé i canonada de connexió, primer utilitzat 0.
23、8 metres de tub curt i ben de comprovació de connexió, llavors una altra vegada i tot arrel tub connexió, Maó maçoneria o formigó abocament part posat comprovació hidrosfera, accessoris i comprovació bé fase collecció de morter superfície plena,
24、 Assegura que la combinació de canonades i morter de ciment en cas de fuita d'encreuament. Segellat coll material i material de canonada igual, per alta temperatura mètode de soldadura i tub fusionen, la seva posició a la paret Central, tram axial de trapezi, una alçada de no
25、 menys de 50mm, 20 mm d'amplada superior, cal fondre base ample de 30mm, cara al voltant de la paret al final d'un sòlid estanca. 9.3.3.8 drenatge HDPE tub rasa backfill (1) canonades abans backfill netejar les escombraries a la canonada i manteniment assegurar la canonada drenatge clar
26、. Mentre els residus del tanc, netejar d'objectes durs com pedres, maons, ranura Expulsor després de l'aigua en la backfill. (2) backfill rasa en canonada backfill simetria bilateral, ompliment uniformement classificava sorra backfill per la carretera llit 0.3M, Aixeta d'aigua, el p
27、es sec de no menys de 16t/M3. (3) la competents compactar backfill zona de no menys de 96% (normes de compactació de la llum), backfill compacitat de sòl per a un fus horari diferent amplada de conducte no menys del 94%. (4) quan la canalització, ésElectricity lines, equipment in
28、spections, found hidden in time for rectification, maintenance, and security. 9, do not use an open flame in the classroom, prohibit burning stove, lit candles, mosquito repellent, no smoking, and banning messy wiring. Without using any household appliances is not allowed. 10, live on campus faculty
29、 members, must lead by example, and educate families and children ready to fire. 11, household use of gas in schools, to master proper usage, pay attention to the leak-proof, explosion-proof, fireproof, closing valve after use to ensure security. 12, dining room must be qualified, and annual testing
30、 of pressure vessels, to regularly check, the canteen workers must be certified, strictly by operation operation, gas tank and stove safety distance of 1.5 meters, to prevent accidents. 13, the adverse consequences caused by ignoring fire safety regulations, will be punished, until investigated for
31、legal responsibility. Song Lin Xiang Liu Jia ping elementary school March 2016 Xiang Liu Jia ping elementary school, pine slopes surrounding safety management system 1 teachers and students, the surrounding area of the school governance covers personal and food hygiene, cultural events and other asp
32、ects, integrated governance shall obtain wide support and full cooperation of the community. On the surrounding environment in schools should be closely monitored. 2, school work at the same time, should pay attention to the safety management of school environment, should take the initiative to cont
33、act the district police station, the village Committee, Correctional Centre, Township government, business management and other departments to do a good job management. 3, teacher on duty with the exception of inspections in schools, should also pay attention to environmental inspections near the ca
34、mpus, found that the jobless migrants from rural areas, for example, harassment of students and a variety of accidents, according to different situations reported school officials or the police station in a timely manner, to protect the safety of students. 4, every day before school, teachers remind
35、 students, pay attention to traffic safety. 5, should educate students to respect social ethics, and various regulations, maintaining public order, and fight the bad guys, and grasp the correct ways and means of maintaining and improving students ' self-care ability. 6, the establishment of emer
36、gency rescue teams of teachers in schools, on high alert and deployed. Song Lin Xiang Liu Jia ping elementary school March 2016 song Lin Xiang Liu Jia ping primary school teachers and students organizations out of safety management system organization activities between teachers and students, to dra
37、w up a precise plan and security measures must be signed by the school officials to review the programme of activities agreed upon Correctional Center agreed to implement. Organization to the field relatively far or activities require approval by the Deputy Director of the Education Bureau in charge
38、 of security. 2, each activity should have a specific responsibility, pay attention to the persons age, physical match. Route 3, activities, location, field surveys should be carried out in advance. 4, activities for the means of transport should explain the situation to the school to comply with ve
39、hicle, safety requirements, before the line for repairs. 5, each activity must have security, emergency response plan for accidents. 6, picnics, hiking, picnic to pay attention to fire prevention, food poisoning, prevention of fall accidents 7, the activities near the rivers, reservoirs, no measures
40、 or do not meet the security requirements of the Organization and not let students into the water四川三一工程建設(shè)(集團(tuán))有限公司 共93頁(yè),第92頁(yè) 東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)項(xiàng)目部四川三一 東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟(商1) 機(jī)械沖擊鉆孔鉿灌注樁工程施工方案第一章 工程概況第一節(jié) 工程基本情況1.1工程概況東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)西側(cè)邊坡支護(hù)、基礎(chǔ)工程機(jī)械沖孔鋼筋混凝土灌注樁工程,位于甘孜州康定新縣城內(nèi)(榆林村),東側(cè)紅線緊鄰康磨公路,西側(cè)紅線緊鄰一市政規(guī)劃道路,規(guī)劃道路外側(cè)為折多河,交通較為
41、便利。本工程由四川三一工程建設(shè)(集團(tuán))有限公司總承包。設(shè)計(jì)基礎(chǔ)型式為:機(jī)械沖(鉆)孔鋼筋混凝土灌注樁基礎(chǔ)。建筑物基礎(chǔ)樁(225根/住2棟+80根/商1棟),樁徑為8001200,總延米約為12000米,樁身混凝土強(qiáng)度等級(jí)為C30,樁端持力層部分地段為中密碎石土、部分地段為密實(shí)碎石土(具體依據(jù)施工勘察資料進(jìn)行確定),具體設(shè)計(jì)情況詳見(jiàn)設(shè)計(jì)圖紙。住2棟靠折多河側(cè)AB段邊坡高度6.50M長(zhǎng)度約74.00M,BC段邊坡高度6.00M長(zhǎng)度約55.00M,抗滑移樁設(shè)計(jì)數(shù)量為60根。樁基礎(chǔ)工程施工:總控制工期要求的最后完成時(shí)間為2012年7月20日,工程施工質(zhì)量達(dá)到合格。第二節(jié) 工程相關(guān)情況1.2工程相關(guān)情況
42、受業(yè)主委托,我公司根據(jù)招投標(biāo)文件資料及雙方所簽署的施工合同的相關(guān)內(nèi)容及條款等,需完成施工測(cè)量放點(diǎn)、機(jī)械成孔清孔、鋼筋籠的制作與安裝(包括原材料的采購(gòu)與檢驗(yàn))、水下混凝土澆筑、泥漿外運(yùn)等工作?;炷猎牧系牟少?gòu)與檢驗(yàn)、混凝土的拌合與運(yùn)輸、場(chǎng)地內(nèi)控制點(diǎn)資料的提供與指定、泥漿外泄場(chǎng)地的提供及相關(guān)費(fèi)用等均由業(yè)主負(fù)責(zé)。為了保證本工程樁基施工的順利實(shí)施,確保工程施工質(zhì)量及施工過(guò)程中機(jī)具設(shè)備及施工人員的安全,特編制此專項(xiàng)施工方案指導(dǎo)工程施工。第二章 工程施工條件第一節(jié) 工程地形地貌條件2.1地形地貌條件場(chǎng)地位于四川盆地西緣山地和青藏高原的過(guò)渡地帶。地勢(shì)由西北向東南傾斜,由東部高山峽谷區(qū)、西北丘狀高原區(qū)和西部
43、高原深谷區(qū)組成總體地勢(shì)東高西低,東側(cè)紅線緊鄰康磨公路,西側(cè)紅線緊鄰一市政規(guī)劃道路,規(guī)劃道路外有一河流(折多河)。目前擬建場(chǎng)地各建筑分區(qū)已平整至設(shè)計(jì)標(biāo)高。第二節(jié) 工程地質(zhì)構(gòu)造2.2地層巖性巖土組成主要為:第四系全新統(tǒng)人工堆積層(Q4ml)、第四系全新統(tǒng)坡洪積層(Q4dl+pl)、第四系全新統(tǒng)殘積層(Q4el)和二疊系下統(tǒng)(P1)巖層組成,具體詳見(jiàn)施工勘察資料。第三節(jié) 工程水文條件2.3水文地質(zhì)條件2.3.1地表水:場(chǎng)地內(nèi)無(wú)地表水流經(jīng)。2.3.2地下水類型:場(chǎng)地地下水主要為上層滯水,下部少量基巖巖溶水。上層滯水主要賦存于場(chǎng)地地勢(shì)較低地段、近地表填土層中,水量一般較小,在地勢(shì)較低、較平地段具相對(duì)統(tǒng)一
44、自由水位,其余地段零星分布,受大氣降水、地表水補(bǔ)給,排泄方式以地面蒸發(fā)為主?;鶐r巖溶水主要賦存于基巖層裂隙、溶蝕孔洞中,水量受裂隙、溶蝕連通性及水源補(bǔ)給條件影響,基本無(wú)統(tǒng)一地下水位。根據(jù)廠區(qū)一線基礎(chǔ)施工情況,基巖巖溶水一般在破碎、巖溶發(fā)育地段巖石中水量較大,受大氣降水、地表水補(bǔ)給,排泄方式以地下滲流、蒸發(fā)為主。場(chǎng)地地下水無(wú)穩(wěn)定水位。第三章 工程施工依據(jù)第一節(jié) 工程圖紙文件3.1工程圖紙成都市建筑設(shè)計(jì)研究院設(shè)計(jì),由甘孜州康定鍋莊城旅游置業(yè)投資有限責(zé)任公司提供給我公司的東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)住2棟基礎(chǔ)平面圖(結(jié)施2/30)、商1棟基礎(chǔ)平面圖及基礎(chǔ)說(shuō)明(結(jié)施2/27)、東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)總平
45、面圖。第二節(jié) 地質(zhì)勘察文件3.2地勘文件中國(guó)建筑西南勘察設(shè)計(jì)研究院有限公司地質(zhì)勘察,由甘孜州康定鍋莊城旅游置業(yè)投資有限責(zé)任公司提供給我公司的東方阿爾卑斯情歌風(fēng)情小鎮(zhèn)(二期)巖土工程勘察報(bào)告A2010-084和A2011-012。第三節(jié) 采用的施工標(biāo)準(zhǔn)、規(guī)范3.3采用的施工標(biāo)準(zhǔn)、規(guī)范3.3.1工程建設(shè)標(biāo)準(zhǔn)強(qiáng)制性條文-房屋建筑工程部分;3.3.2建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范(GB50007-2002);3.3.3建筑樁基技術(shù)規(guī)范(JGJ94-2008);3.3.4建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收規(guī)范(GB50202-2002);3.3.5工程測(cè)量規(guī)范(GB50026-93);3.3.6混凝土結(jié)構(gòu)工程施工驗(yàn)收規(guī)
46、范(GB50204-2002);3.3.7建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)(GB50300-2001);3.3.8建筑樁基檢測(cè)技術(shù)規(guī)范(JGJ106-2003);3.3.9土方與爆破工程施工及驗(yàn)收規(guī)范GBJ201-83;3.3.10普通混凝土拌合物性能試驗(yàn)方法標(biāo)準(zhǔn)(GB/T50080-2002);3.3.11普通混凝土力學(xué)性能試驗(yàn)方法標(biāo)準(zhǔn)(GB/T50081-2002);3.3.12混凝土強(qiáng)度檢驗(yàn)評(píng)定標(biāo)準(zhǔn)(GBJ107-87);3.3.13混凝土外加劑應(yīng)用技術(shù)規(guī)范(GBJ50119-2003);3.3.14混凝土質(zhì)量控制標(biāo)準(zhǔn)(GB50164-92);3.3.15普通混凝土配合比設(shè)計(jì)規(guī)定(JGJ55
47、-2000);3.3.16混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范(GB50010-2002);3.3.17建設(shè)抗震設(shè)計(jì)規(guī)范(GB50011-2001);3.3.18鋼筋焊接及驗(yàn)收規(guī)程(JGJ18-2003);3.3.19鋼筋機(jī)械連接通用技術(shù)規(guī)程(JGJ107-2003);3.3.20特種作業(yè)人員安全管理規(guī)則(GBJ306-85);3.3.21建筑施工門式鋼管腳手架安全技術(shù)規(guī)范(JGJ128-2000);3.3.22建筑施工安全檢查標(biāo)準(zhǔn)(JGJ59-99);3.3.23施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(JGJ46-2005);3.3.24建筑機(jī)械使用安全技術(shù)規(guī)程(JGJ33-2001);3.3.25焊接與切割安全(GB
48、9448-99);3.3.26建筑工程冬期施工規(guī)程(JGJ104-97);3.3.27建設(shè)工程施工現(xiàn)場(chǎng)供用電安全規(guī)范(GB50194-1993 2001版);3.3.28電氣裝置安裝工程接地裝置施工及驗(yàn)收規(guī)范(GB50169-92);3.3.29建筑電氣工程施工質(zhì)量驗(yàn)收規(guī)范(GB50303-2002);3.3.30建設(shè)工程文件歸檔整理規(guī)范(GB/T50328-2001)。第四章 工程施工準(zhǔn)備第一節(jié) 人力資源準(zhǔn)備4.1.1人力資源準(zhǔn)備4.1.1.1項(xiàng)目部設(shè):項(xiàng)目經(jīng)理1人,主持全面項(xiàng)目管理工作;設(shè)技術(shù)負(fù)責(zé)人1人,主持項(xiàng)目全面技術(shù)管理工作;設(shè)專職安全員1人,主持現(xiàn)場(chǎng)施工安全全面管理工作;設(shè)專職質(zhì)檢員
49、1人,專職負(fù)責(zé)現(xiàn)場(chǎng)施工質(zhì)量驗(yàn)收和管理工作;設(shè)資料員1人,負(fù)責(zé)收集和整理樁基礎(chǔ)施工過(guò)程技術(shù)資料的歸檔工作。4.1.1.2施工現(xiàn)場(chǎng)設(shè):項(xiàng)目經(jīng)理1人,專職負(fù)責(zé)住2棟和商1棟樁基礎(chǔ)施工管理工作;設(shè)技術(shù)負(fù)責(zé)人1人,專職負(fù)責(zé)樁基礎(chǔ)施工過(guò)程中安全與工程技術(shù)管理工作;設(shè)專職質(zhì)檢員1人,專職負(fù)責(zé)現(xiàn)場(chǎng)分項(xiàng)施工質(zhì)量驗(yàn)收;每臺(tái)鉆機(jī)設(shè)機(jī)長(zhǎng)1人,專職對(duì)本機(jī)的施工安全和施工質(zhì)量全面負(fù)責(zé)。4.1.1.3施工作業(yè)人員配備計(jì)劃:針對(duì)本項(xiàng)目工程,經(jīng)我公司本工程項(xiàng)目班組分析決定,擬投入各工種人員計(jì)劃如下表所示,在實(shí)際施工過(guò)程中,根據(jù)工程施工需要進(jìn)行優(yōu)化調(diào)整,以確保工程項(xiàng)目的順利實(shí)施及施工工期。各工種投入人員計(jì)劃表序號(hào)作業(yè)班組組建班組
50、人數(shù)(人/班組)備注1鉆孔灌注樁班組2班502鋼筋班組2班123混凝土班組3班94其他班組3班125項(xiàng)目部16合計(jì)994.1.2施工技術(shù)準(zhǔn)備4.1.2.1認(rèn)真熟悉現(xiàn)場(chǎng)的工程地質(zhì)和水文地質(zhì)資料,收集場(chǎng)區(qū)內(nèi)地下障礙物、管網(wǎng)等相關(guān)資料。4.1.2.2對(duì)現(xiàn)場(chǎng)施工人員進(jìn)行圖紙和施工方案交底,專業(yè)工種應(yīng)進(jìn)行短期專業(yè)技術(shù)培訓(xùn)。4.1.2.3組織現(xiàn)場(chǎng)所有管理人員和施工人員學(xué)習(xí)有關(guān)安全文明施工規(guī)程、業(yè)主的相關(guān)管理程序,增強(qiáng)職工安全、文明施工和環(huán)境保護(hù)意識(shí)。4.1.2.4進(jìn)行測(cè)量基準(zhǔn)交底、復(fù)測(cè)及驗(yàn)收工作。4.1.2.5其他技術(shù)準(zhǔn)備工作第二節(jié) 物資設(shè)備計(jì)劃4.2物資設(shè)備計(jì)劃針對(duì)本項(xiàng)目工程,經(jīng)我公司本工程項(xiàng)目班組分析
51、決定,擬投入設(shè)備計(jì)劃如下表所示,在實(shí)際施工過(guò)程中,根據(jù)實(shí)際需要,我方可適當(dāng)對(duì)設(shè)備進(jìn)行優(yōu)化調(diào)整,以確保工程項(xiàng)目的順利實(shí)施及施工工期。投入設(shè)備計(jì)劃表序號(hào)機(jī)械裝備(試驗(yàn)儀器)名稱型號(hào)規(guī)格數(shù)量國(guó)別產(chǎn)地額定功率備注1沖擊鉆機(jī)CZ-6D8臺(tái)河北宏源機(jī)械廠75KW2電焊機(jī)BX1-400J10臺(tái)成都電焊機(jī)廠15KW3鋼筋切斷機(jī)GQ40型2臺(tái)成都倍特15KW4鋼筋調(diào)直機(jī)GT6-122臺(tái)成都倍特11KW5鋼筋彎曲機(jī)GW40型2臺(tái)成都倍特20KW6對(duì)焊機(jī)U-1002臺(tái)成都倍特20KW7全站儀RTS-8222臺(tái)瑞 得8砼試模150×150×150mm10組成都量具廠9泥漿比重計(jì)07050支成都量具
52、廠10塌落度儀160220mm2套成都量具廠11泥漿泵3PNL15臺(tái)自貢市工業(yè)泵股份有限公司22KW12清水泵QS-25-20-313臺(tái)自貢市工業(yè)泵股份有限公司1.1KW13裝載機(jī)ZL301臺(tái)中國(guó)成工14挖掘機(jī)EC240B1臺(tái)沃爾沃建筑設(shè)備限公司15汽車式吊車QY-161臺(tái)瀘州起重機(jī)廠16附屬機(jī)具若干第三節(jié) 作業(yè)條件準(zhǔn)備4.3作業(yè)條件準(zhǔn)備4.3.1施工場(chǎng)地應(yīng)堅(jiān)實(shí)穩(wěn)固,并具備機(jī)械、人員操作條件。4.3.2施工用水、用電接至施工場(chǎng)區(qū),并滿足機(jī)械及成孔要求。4.3.3混凝土攪拌站、混凝土輸送、混凝土澆注機(jī)械試運(yùn)轉(zhuǎn)完畢,鋼筋進(jìn)場(chǎng)檢驗(yàn)合格,鋼筋骨架安放設(shè)備滿足要求。4.3.4測(cè)量控制網(wǎng)(高程、坐標(biāo)點(diǎn))已
53、建立,樁位放線工作完成,或復(fù)測(cè)驗(yàn)收合格。4.3.5泥漿池按總平布設(shè)完畢,運(yùn)輸車配備到位。4.3.6所有機(jī)具設(shè)備通過(guò)業(yè)主驗(yàn)收,人員經(jīng)過(guò)業(yè)主入場(chǎng)教育及安全培訓(xùn),所有人員的PPE均已備齊。第五章 施工計(jì)劃第一節(jié) 施工計(jì)劃5.1工期計(jì)劃5.1.1工期計(jì)劃:本工程計(jì)劃施工工期為130天。5.1.2施工進(jìn)度橫道圖(冬季停工及地質(zhì)變化,延誤工期順延)沖孔鉿灌注樁工程施工進(jìn)度橫道圖 施工天數(shù)工作內(nèi)容2010年10月25日開(kāi)工,最后完成時(shí)間為2012年7月25日331010101010101014施工準(zhǔn)備放線,材料送檢沖孔樁基施工基坑開(kāi)挖、清樁樁基檢測(cè)第二節(jié) 工期保證措施5.2組織保障措施 5.2.1組織精干高水平
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年度大型建筑鋼材項(xiàng)目集中采購(gòu)合同
- 2024年銷售人員業(yè)績(jī)合同2篇
- 2025年度個(gè)人二手房買賣協(xié)議書(shū)范本:二手房交易法律咨詢合同
- 2025年度內(nèi)部員工股權(quán)激勵(lì)計(jì)劃變更與股權(quán)轉(zhuǎn)讓合同
- 二零二五年度奶粉行業(yè)市場(chǎng)分析報(bào)告定制合同
- 二零二五年度培訓(xùn)中心教師教學(xué)資源共享聘用合同
- 2025年度私人旅行規(guī)劃服務(wù)合同2篇
- 2025版抹灰班組安全生產(chǎn)責(zé)任制考核合同4篇
- 2025年度自動(dòng)駕駛汽車測(cè)試場(chǎng)租賃合同范本3篇
- 二零二五年度民間借貸裁判觀點(diǎn)與法律適用合同4篇
- 醫(yī)師定期考核 (公共衛(wèi)生)試題庫(kù)500題(含答案)
- 基因突變和基因重組(第1課時(shí))高一下學(xué)期生物人教版(2019)必修2
- 內(nèi)科學(xué)(醫(yī)學(xué)高級(jí)):風(fēng)濕性疾病試題及答案(強(qiáng)化練習(xí))
- 音樂(lè)劇好看智慧樹(shù)知到期末考試答案2024年
- 辦公設(shè)備(電腦、一體機(jī)、投影機(jī)等)采購(gòu) 投標(biāo)方案(技術(shù)方案)
- 案卷評(píng)查培訓(xùn)課件模板
- 2024年江蘇省樣卷五年級(jí)數(shù)學(xué)上冊(cè)期末試卷及答案
- 人教版初中英語(yǔ)七八九全部單詞(打印版)
- 波浪理論要點(diǎn)圖解完美版
- 金融交易數(shù)據(jù)分析與風(fēng)險(xiǎn)評(píng)估項(xiàng)目環(huán)境敏感性分析
- 牛頓環(huán)與劈尖實(shí)驗(yàn)論文
評(píng)論
0/150
提交評(píng)論