1、Word 格式恩陽·首座 2#、3#樓磚砌體工程專項施工方案編制人:審核人:編制單位:中齊建設(shè)工程有限公司編制時間:二一七年三月八日完美整理目錄一、編制依據(jù)及說明 ···································
2、83;····31、編制說明···········································32、編制依據(jù)&
3、#183;············································3二、工程簡介····
4、········································· 31、參建單位·······
5、3;····································32、工程概況············
6、83;·······························33、各部位材料要求·················
7、;·····················4三、施工準(zhǔn)備···························
8、3;·················51、材料準(zhǔn)備·······························
9、83;·············52、機(jī)具準(zhǔn)備···································
10、183;·········53、人力準(zhǔn)備·······································&
11、#183;·····54、技術(shù)準(zhǔn)備···········································
12、··6四、施工工藝··············································61、工藝
13、流程·············································62、施工工藝···
14、83;·········································6五、施工要點·······
15、183;······································71、墻肢部位 100 磚施工方法········
16、83;························72、墻底部、丁字墻和轉(zhuǎn)角墻的砌筑方法· ·····················&
17、#183;83、梁下口砌體的接觸部位砌筑方法· ··························94、墻體拉結(jié)筋的設(shè)置·················
18、183;·····················95、有防水功能要求的房間砌筑方法· ························
19、183;·126、構(gòu)造柱的設(shè)置··········································1317、女兒墻砌筑大樣圖· ·
20、183;····································15 六、質(zhì)量控制措施···········
21、83;······························17 1、材料控制··················
22、·····························17 2、砌體灰縫控制···················&
23、#183;·······················17 3、砌體的平整度和垂直度控制· ······················&
24、#183;·······18 4、砂漿飽滿度的控制· ······································18 5、
25、磚砌體一般尺寸允許偏差值· ······························18 6、磚砌體的砂漿飽滿及檢驗方法· ············
26、3;···············19 7、成品保護(hù)·································&
27、#183;············19 8、砂漿組批原則及取樣要求· ······························20 七、現(xiàn)場安全文明施工注意事項
28、83; ····························20 1、安全施工····················
29、;···························20 2、文明施工·····················
30、183;·························202第一章編制依據(jù)及說明一、編制說明本方案主要針對恩陽·首座2#、3#樓項目砌體工程質(zhì)量、進(jìn)度編制。二、編制依據(jù)1、建筑工程施工圖紙及建筑、結(jié)構(gòu)施工總說明及施工合同。2、工程圖紙會審紀(jì)要及技術(shù)核定單。3、混凝土結(jié)構(gòu)輕質(zhì)填充墻構(gòu)造圖集( 西南 15G701-3)4、砌體工程施工質(zhì)量
31、驗收規(guī)范GB50203-20025、建筑工程施工質(zhì)量驗收統(tǒng)一標(biāo)準(zhǔn)GB50300-20136、墻體材料應(yīng)用統(tǒng)一技術(shù)規(guī)范GB 50574-20107、混凝土結(jié)構(gòu)后錨技術(shù)規(guī)程JGJ 145-2013第二章工程簡介(一)參建單位建設(shè)單位:巴中靜州置業(yè)有限責(zé)任公司;設(shè)計單位:深圳市物業(yè)國際建筑設(shè)計有限公司;監(jiān)理單位:中科標(biāo)禾工程項目管理有限公司;施工單位:中齊建設(shè)工程有限公司;(二)工程概況3#樓建筑面積 :約 31202.01 ,總高度 93 米、層數(shù)為地上31層,地下 2 層,建筑工程安全等級為二級??拐鹪O(shè)防烈度為六度。耐火等級為一級,建筑耐久年限為50 年。屋面防水等級為I 級;地下:設(shè)備房一級,
32、其它部位二級。本工程結(jié)構(gòu)采用鋼筋混凝土剪力墻結(jié)構(gòu),基礎(chǔ)采用防水板、獨立基礎(chǔ)型式。32#樓建筑面積 : 1633.17 ,總高度 15.15 米、層數(shù)為地上 3 層,地下 1 層,建筑工程安全等級為二級。抗震設(shè)防烈度為6 度一組。耐火等級為二級,建筑耐久年限為50 年。屋面防水等級為級,一道防水設(shè)防;本工程結(jié)構(gòu)采用框架結(jié)構(gòu),基礎(chǔ)采用防水板、獨立基礎(chǔ)型式。(三)各部位材料要求1、2# 樓墻體工程、墻體技術(shù)要求(1)、外圍護(hù)墻、衛(wèi)生間采用 200 厚頁巖多孔磚,用 M5水泥砂漿砌筑;電梯隔墻(非鋼筋混凝土墻處)、設(shè)備間、水電管井墻體為頁巖實心磚,其他墻體采用 100、200 厚頁巖空心磚,其余地上部
33、分的內(nèi)隔墻為 100、200 厚頁巖空心磚,用 M5混合砂漿砌筑;地下部分內(nèi)隔墻采用 200 厚頁巖多孔磚砌體,用 M5水泥砂漿砌筑。(2)、預(yù)留洞的封堵: 砌筑墻留洞待管道設(shè)備安裝完畢后, 用 C25 細(xì)石混凝土填實。(3)、無窗臺板的外墻在窗臺處澆筑 C25混凝土 100 厚( 內(nèi)配縱向2C6鋼筋 C6 拉鉤 200)兩端伸入墻內(nèi)不小于 250。(5)、門窗洞口四周采用頁巖實心磚砌筑。#(1)本工程主要墻體材料的選用:地下:地下室部分詳見地下車庫施工圖(后期設(shè)計出圖),無地下室部分± 0.00 以下墻體均采用頁巖實心磚。地上:外墻、分戶墻、廚房、衛(wèi)生間、電梯井道隔墻采用頁巖多孔磚
34、,其他墻體為頁巖空心磚砌體。(2)填充墻材料:a、外隔墻、衛(wèi)生間、廚房隔墻采用強(qiáng)度等級MU10頁巖多孔磚其余內(nèi)隔墻采用強(qiáng)度等級MU5頁巖空心磚。4b、砌筑砂漿:± 0.000 以下用 M5 水泥砂漿,± 0.000 以上用M5混合砂漿。c、無窗臺板的外墻在窗臺處澆筑100 厚、同墻寬的 C25鋼筋混凝土壓頂 ( 配筋 : 縱向 2C6、拉鉤 C6200),兩端伸入墻內(nèi)不小于250。d、與填充砌體連接的GZ在砌體砌筑完成后澆筑混凝土,接縫處砌體留馬牙磋。e、梁、板下部有構(gòu)造柱時,在與構(gòu)造柱對應(yīng)位置的梁、板下部預(yù)埋鋼筋,數(shù)量和直徑同構(gòu)造柱縱筋。 構(gòu)造柱平面布置圖(詳附圖)。第三
35、章施工準(zhǔn)備一、材料準(zhǔn)備材料要求:砌體所用磚體材料其齡期應(yīng)超過 28 天,進(jìn)場后按品種、規(guī)格分別堆放整齊。材料尺寸誤差在規(guī)范允許范圍以內(nèi),誤差較大的不允許采用。磚砌體砌筑前應(yīng)提前澆水濕潤。各種磚的品種、規(guī)格、強(qiáng)度必須符合設(shè)計要求,有出廠合格證、進(jìn)場試驗報告。二、機(jī)具準(zhǔn)備應(yīng)配備砂漿攪拌機(jī)、磅秤、手推車、垂直運輸設(shè)備、卷尺、檢測尺、水平尺、托線板、線墜、瓦刀、白線、灰桶、掃帚等。三、人力準(zhǔn)備泥工班組必須根據(jù)進(jìn)度要求組織好勞動力,應(yīng)配備技術(shù)水平較高的技術(shù)工人,普工應(yīng)與技工配置適當(dāng)。一個班組技術(shù)工人不少于 15 人,對各班組每日完成工作量進(jìn)行控制, 在保證施工進(jìn)度的前提下必須確保工程質(zhì)量。四、技術(shù)準(zhǔn)備5
36、1、砌體施工前,項目部應(yīng)對砌體施工圖進(jìn)行仔細(xì)審閱,形成技術(shù)交底并逐層交底下去。對于圖紙上的疑問應(yīng)提前與甲方、監(jiān)理、設(shè)計院進(jìn)行溝通。2、對具有施工難點的部位,施工人員要認(rèn)真向技術(shù)負(fù)責(zé)人、甲方、設(shè)計院進(jìn)行詢問, 以確定具體做法。 禁止擅自采用違反操作規(guī)程、方案及技術(shù)交底要求的施工方法。第四章施工工藝一、工藝流程施工準(zhǔn)備放線磚預(yù)排模數(shù)砌體砌筑梁底斜磚補砌澆筑構(gòu)造柱二、施工工藝1、在砌筑前應(yīng)先進(jìn)行場地清理,并澆適量水進(jìn)行濕潤。在拌制砂漿的時候, 為了增加砂漿的和易性, 可在拌制過程中摻入適量外加劑。2、在材料準(zhǔn)備完畢后預(yù)先用干磚進(jìn)行預(yù)排模數(shù)。砌塊砌筑時,應(yīng)采用“三一”砌筑方法,即“一塊磚、一鏟灰、一揉
37、壓”。3、砌塊垂直、水平灰縫厚度嚴(yán)格照規(guī)范要求,砂漿飽滿度應(yīng)超過 80%。4、填充墻采用錯縫搭砌,在砌體砌筑200 墻每 500MM高時設(shè)置2A6.5 拉結(jié)筋一道(第一道拉結(jié)筋為430mm高),100 墻每 500MM高時設(shè)置 2A6.5 拉結(jié)筋一道。拉結(jié)筋錨入磚墻700MM,端部設(shè) 90°彎鉤。5、砌體砌筑至梁底或板底時,應(yīng)留200mm高的空隙,等砌體收縮穩(wěn)定后(一般為7 天)再用實心磚斜砌擠緊,并用砂漿填實。66、在墻體墻長大于5M及室外約束支座處均應(yīng)設(shè)置構(gòu)造柱。在遇到構(gòu)造柱的位置時,應(yīng)砌筑成馬牙槎形狀,并清理干凈槎內(nèi)砂漿,等砌體收縮穩(wěn)定后再支模澆筑混凝土。構(gòu)造柱砼應(yīng)采用插入式振
38、搗,但應(yīng)避免振動棒與砌體接觸。 構(gòu)造柱鋼筋均采用主體結(jié)構(gòu)時預(yù)留和植筋技術(shù),設(shè)置4C12 主筋,箍筋為C6.5200,上部錨入梁底部,形成一個整體。7、砌筑時每層磚均應(yīng)拉水平線,隨砌筑高度而上升,以控制灰縫的水平度。8、墻體各種預(yù)留洞、預(yù)埋件等,應(yīng)按設(shè)計要求留置,避免事后剔鑿。第五章施工要點一、墻肢部位砌100 磚垛施工方法由于個別設(shè)置在門洞口處的磚垛較小,在今后房屋使用過程中,經(jīng)常開關(guān)門對磚垛的穩(wěn)定性是一個考驗。 根據(jù)這一個特點, 我們采用頁巖磚砌筑, 由于磚垛不能錯縫搭砌, 所以每隔 500mm高在墻肢上植 2C6.5 拉結(jié)筋。在砌筑時要保證砂漿的強(qiáng)度,特別是磚砌體在與砼接觸部位灰縫的飽滿度
39、(如下圖) 。7植筋 26.5100頁巖磚二、墻底部、丁字墻和轉(zhuǎn)角墻的砌筑方法墻底部應(yīng)砌燒結(jié)普通磚其高度不宜小于180mm。丁字墻和墻體轉(zhuǎn)角的交接處若特殊情況沒有設(shè)置構(gòu)造柱時應(yīng)交錯搭砌,如錯縫長度不能滿足 1/3 磚,且不小于150mm時,豎向每 400mm應(yīng)設(shè)置 26 拉結(jié)鋼筋,每邊伸入墻內(nèi)不小于1000mm并設(shè) 180°彎鉤。8三、梁下口砌體的接觸部位的砌筑方法由于砂漿的收縮性,如果一次性砌筑至梁底,以后磚砌體與梁下口會形成一條水平裂縫。所以我們要求在填充墻砌筑至梁底的時候,應(yīng)留一定的空隙, 待填充墻砌筑完后至少應(yīng)間隔 7 天,再用頁巖實心磚斜砌擠緊,在補砌時,要求砂漿一定要飽滿
40、 ( 詳下圖 ) 。四、墻體拉結(jié)筋的設(shè)置1、施工工藝:定位鉆孔清孔鋼筋除銹植筋膠配料植筋固化保護(hù)檢查驗收2、施工要求砌體主要作填充、 隔斷作用,因此在拉結(jié)筋設(shè)置多數(shù)是一邊錨入9砼內(nèi),一邊錨入砌體內(nèi)。在沒有預(yù)埋拉結(jié)筋的情況下 , 我們采用植筋技術(shù)。采用電鉆在砼中每隔 500mm間距的位置鉆 2 個孔 , 并用小型空壓機(jī)把孔內(nèi)的灰塵吹干凈, 植筋材料為圓鋼, 按要做規(guī)格預(yù)先進(jìn)行下料,并按要求留搭接,按 50鋼筋錯位搭接,注膠后立即種植筋鋼筋,將鋼筋按順時針的方向緩慢旋進(jìn)孔內(nèi),確保植入深度,留有足夠的時間粘合劑固化。 做完每到工序, 必須經(jīng)甲方及監(jiān)理檢查驗收合格后才能進(jìn)行下道工序施工。3、質(zhì)量要求鉆
41、孔質(zhì)量主控項目(1)鉆孔孔徑符合設(shè)計要求及有關(guān)規(guī)定。(2)鉆孔內(nèi)應(yīng)清理干凈,無粉塵;植筋膠產(chǎn)品要求孔道干燥的要保持孔道干燥。一般項目(1)鉆孔位置應(yīng)符合設(shè)計(構(gòu)造)要求和砌塊模數(shù)。(2)鉆孔深度允許偏差為( +20mm,0mm),水平度允許偏差為 5mm,位置允許偏差為 5mm。拉結(jié)筋“植筋法”施工質(zhì)量主控項目(1)植筋膠質(zhì)量應(yīng)符合要求。拉結(jié)筋無銹蝕,表面無雜質(zhì)。(2)鉆孔內(nèi)植筋膠應(yīng)飽滿,固化良好,拉結(jié)筋要錨牢錨實。一般項目(1)拉結(jié)筋的位置、尺寸、彎鉤、間距應(yīng)符合設(shè)計或構(gòu)造要求。10(2)拉結(jié)筋施工質(zhì)量應(yīng)符合設(shè)計或規(guī)范要求。3. 抗拔試驗植筋 48 小時后即可達(dá)到強(qiáng)度要求, 請有資質(zhì)的檢測單
42、位對植筋情況進(jìn)行現(xiàn)場抗拔抽檢, 抗拔力要求在鋼筋的設(shè)計強(qiáng)度以上為植筋錨固合格。植筋抽檢數(shù)量按每組 /3000 根。按每一個部位,每種規(guī)格均分別抽檢。4、成品保護(hù)加強(qiáng)成品保護(hù)交底教育。結(jié)構(gòu)表面拉結(jié)筋位置定位彈線后和鉆孔、 清孔完成后要嚴(yán)禁人為污染。加工好的拉結(jié)筋要架起存放, 上方要有擋雨設(shè)施, 存放地要通風(fēng)防潮良好,防止銹蝕。配膠攪拌時要均勻攪拌, 防止膠液從容器中濺出, 造成結(jié)構(gòu)成品污染。注膠時要控制好膠液的注入量, 防止注入過多, 致使植入拉結(jié)筋時擠出的膠液過多,污染結(jié)構(gòu)表面。拉結(jié)筋在植筋完成后,植筋膠固化前防止擾動和人為碰撞。填充墻砌體施工前,拉結(jié)筋不得進(jìn)行任意彎折、拆卸。11五、有防水功
43、能要求的房間砌筑方法1、衛(wèi)生間、廚房等用水房間四周的非鋼筋混凝土墻體在墻根處澆筑 200 高 C20混凝土止水導(dǎo)墻,厚度同墻厚。 (詳下圖)122、砌筑時灰縫砂漿飽滿,避免形成假縫影響防水質(zhì)量。六、構(gòu)造柱的設(shè)置1、構(gòu)造柱的設(shè)置按設(shè)計圖紙進(jìn)行布置,填充墻長度5m時在墻中部設(shè)置構(gòu)造柱,構(gòu)造柱間距不大于20 倍墻厚且不大于4m。構(gòu)造柱的位置的砌體應(yīng)砌筑成馬牙槎狀,并清理干凈槎內(nèi)的砂漿及其他雜物。留槎的部位采用頁巖磚砌筑,構(gòu)造柱鋼筋采用植筋預(yù)留鋼筋技術(shù)。(如圖一)6.5 拉結(jié)筋地面標(biāo)高構(gòu)造柱圖一構(gòu)造柱大樣圖132、過梁、腰帶的設(shè)置( 1)門、窗洞過梁,當(dāng)跨度 <2.1m 時按西南 15G701-
44、3,過梁按荷載等級 1 級選用,過梁寬度同墻厚。( 2)填充墻高度 4m時,半層高處或門窗上口設(shè)通長過梁,梁截面為墻厚× 100mm,配筋 4C12,C6 200 圈梁鋼筋錨入兩端柱內(nèi)。填充墻高度 6m時,沿墻高每 2m設(shè)置現(xiàn)澆腰帶 ( 詳下圖 ) 。14七、女兒墻砌筑大樣圖(一) 2#樓女兒墻大樣圖15(二) 3#樓女兒墻大樣圖16第六章質(zhì)量控制措施一、材料控制1、現(xiàn)場采用原材料必須是滿足28 天后的產(chǎn)品,進(jìn)場后抽樣送檢,合格后方可用于施工。2、拌制砌筑砂漿:現(xiàn)場采用砂漿攪拌機(jī)拌合砂漿,嚴(yán)格按照配合比配制。3、砂漿配合比用重量比,計量精度為:水泥±2%、砂及摻合料±5%。4、體砌筑 24 小時后澆水養(yǎng)護(hù)保證砂漿強(qiáng)
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 2024年七年級歷史下冊 第16課 明朝的科技、建筑與文學(xué)說課稿 新人教版
- 2025瓷磚買賣合同
- Unit 3 Family Matters Understanding ideas Like Father,Like Son 說課稿 -2024-2025學(xué)年高中英語外研版(2019)必修第一冊
- 2024-2025學(xué)年高中語文 第三課 第4節(jié) 咬文嚼字-消滅錯別字說課稿2 新人教版選修《語言文字應(yīng)用》
- 21 古詩三首 第一課時 說課稿-2024-2025學(xué)年統(tǒng)編版語文四年級上冊
- 2025購銷合同范本
- 森林安全監(jiān)管方案
- 企業(yè)派駐合同范例
- 網(wǎng)狀吊索拱橋施工方案
- 黔東南綠化草坪施工方案
- 新生兒黃疸早期識別課件
- 醫(yī)藥營銷團(tuán)隊建設(shè)與管理
- 新生兒氣管插管操作評分標(biāo)準(zhǔn)
- 二年級數(shù)學(xué)上冊口算題100道(全冊完整)
- 冷軋工程專業(yè)詞匯匯編注音版
- 小升初幼升小擇校畢業(yè)升學(xué)兒童簡歷
- 第一單元(金融知識進(jìn)課堂)課件
- 五年級語文閱讀訓(xùn)練20篇專項訓(xùn)練帶答案解析
- 介入導(dǎo)管室護(hù)士述職報告(5篇)
- GB/T 37062-2018水產(chǎn)品感官評價指南
- 零件的工藝分析及毛坯選擇
評論
0/150
提交評論