金屬新材料項(xiàng)目
外墻保溫施工方案
編制單位:中建x局第一建設(shè)有限公司
編制人:
日期:2023年10月
-1-
目錄
第一章編制依據(jù)....................................................5
第二章工程概況....................................................5
2.1工程建設(shè)概況表.....................................................................................................................................................5
2.2設(shè)計(jì)概況.................................................................................................................................................................6
2.3工程施工條件.........................................................................................................................................................7
第三章施工安排....................................................8
3.1項(xiàng)目管理組織.........................................................................................................................................................8
3.2各項(xiàng)資源供應(yīng)方式.................................................................................................................................................9
3.2.1勞務(wù)資源安排一覽表.....................................................................................................................................9
3.2.2工程用大宗物資供應(yīng)安排一覽表.................................................................................................................9
3.3施工流水段的劃分...............................................................................................................................................10
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施................................................................................................................10
3.5關(guān)鍵及特殊過(guò)程控制............................................................................................................................................11
3.5.1安全重大危險(xiǎn)源............................................................................................................................................11
3.5.2主控項(xiàng)目........................................................................................................................................................11
3.6項(xiàng)目管理目標(biāo)........................................................................................................................................................11
第四章施工進(jìn)度計(jì)劃...............................................12
第五章施工準(zhǔn)備與資源配置計(jì)劃.....................................12
5.1施工準(zhǔn)備計(jì)劃.......................................................................................................................................................12
5.1.1技術(shù)準(zhǔn)備.......................................................................................................................................................12
5.2資源配置計(jì)劃.......................................................................................................................................................14
5.2.1勞動(dòng)力配置計(jì)劃...........................................................................................................................................14
5.2.2機(jī)具、設(shè)備配置計(jì)劃...................................................................................................................................14
5.2.3測(cè)量計(jì)量?jī)x器配置計(jì)劃...............................................................................................................................14
第六章施工方法及工藝要求.........................................15
6.1施工工藝流程.......................................................................................................................................................15
2
6.2施工要點(diǎn)...............................................................................................................................................................15
6.2.1基層處理.......................................................................................................................................................15
6.2.2外墻抹灰.......................................................................................................................................................15
6.2.3布線、排版...................................................................................................................................................16
6.2.4貼保溫板.......................................................................................................................................................17
6.2.5巖棉板錨固...................................................................................................................................................19
6.2.6抗裂砂漿及網(wǎng)格布施工...............................................................................................................................19
6.2.7外立面涂料真石漆施工...............................................................................................................................22
6.3驗(yàn)收標(biāo)準(zhǔn)...............................................................................................................................................................31
6.4驗(yàn)收內(nèi)容...............................................................................................................................................................31
6.5驗(yàn)收人員...............................................................................................................................................................32
第七章進(jìn)度管理計(jì)劃...............................................33
7.1進(jìn)度管理計(jì)劃.......................................................................................................................................................33
7.1.1確定施工進(jìn)度控制點(diǎn)...................................................................................................................................33
7.1.2進(jìn)度管理措施...............................................................................................................................................33
7.2質(zhì)量管理計(jì)劃.......................................................................................................................................................34
7.2.1質(zhì)量控制目標(biāo)分解.......................................................................................................................................34
7.2.2質(zhì)量標(biāo)準(zhǔn).......................................................................................................................................................35
7.2.3質(zhì)量管理小組...............................................................................................................................................36
7.2.4質(zhì)量控制計(jì)劃...............................................................................................................................................37
7.2.5質(zhì)量通病防治...............................................................................................................................................37
7.3安全管理計(jì)劃.......................................................................................................................................................38
7.3.1職業(yè)健康安全管理分解目標(biāo).......................................................................................................................38
7.3.2職業(yè)健康安全管理組織機(jī)構(gòu)和職責(zé)分工...................................................................................................38
7.3.3職業(yè)健康安全重大危險(xiǎn)源...........................................................................................................................38
7.3.4職業(yè)健康安全資源配置計(jì)劃.......................................................................................................................39
7.3.6職業(yè)健康安全保證措施...............................................................................................................................40
3
7.4環(huán)境及綠色施工管理計(jì)劃...................................................................................................................................41
7.4.1綠色施工管理職責(zé).......................................................................................................................................41
7.4.2環(huán)境及綠色施工保證措施...........................................................................................................................41
7.5成品保護(hù)管理計(jì)劃...............................................................................................................................................42
7.5.1成品保護(hù)管理組織和職責(zé)分工...................................................................................................................42
7.5.2成品保護(hù)計(jì)劃及保證措施...........................................................................................................................42
第x章應(yīng)急預(yù)案...................................................42
8.1應(yīng)急指揮機(jī)構(gòu)及職責(zé)............................................................................................................................................42
8.1.1應(yīng)急領(lǐng)導(dǎo)小組主要職責(zé):...........................................................................................................................43
8.1.2現(xiàn)場(chǎng)聯(lián)絡(luò)組職責(zé)...........................................................................................................................................43
8.1.3現(xiàn)場(chǎng)保衛(wèi)組...................................................................................................................................................43
8.1.4現(xiàn)場(chǎng)救護(hù)組...................................................................................................................................................44
8.1.5緊急搶險(xiǎn)組...................................................................................................................................................44
8.2事故風(fēng)險(xiǎn)分析.......................................................................................................................................................44
8.3預(yù)防與預(yù)警...........................................................................................................................................................44
8.3.1危險(xiǎn)源監(jiān)控...................................................................................................................................................44
8.3.2預(yù)警行動(dòng).......................................................................................................................................................44
8.3.3應(yīng)急處置措施...............................................................................................................................................44
8.3.4突發(fā)情況應(yīng)急措施.......................................................................................................................................45
8.4新型冠狀肺炎疫情防控應(yīng)急預(yù)案........................................................................................................................47
8.4.1防疫指揮機(jī)構(gòu)及職責(zé)...................................................................................................................................47
8.4.2應(yīng)急響應(yīng)流程...............................................................................................................................................49
8.4.3入場(chǎng)人員管理措施.......................................................................................................................................50
8.4.4日常工作防疫措施.......................................................................................................................................51
4
第一章編制依據(jù)
序號(hào)類別文件名稱編號(hào)
《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)
1住建部令第37號(hào)
國(guó)家行政文定》
件《危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)建辦質(zhì)(2018)31
2
定》有關(guān)問(wèn)題的通知號(hào)
3《建筑節(jié)能工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50411-2023
4《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-2013
5《建筑裝飾裝修工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50210-2018
國(guó)家行業(yè)規(guī)
6范《外墻外保溫工程技術(shù)標(biāo)準(zhǔn)》JGJ144-2023
7《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-2016
《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(附條
8JGJ46-2005
文說(shuō)明)》
9設(shè)計(jì)文件施工圖紙
第二章工程概況
2.1工程建設(shè)概況表
xx金屬新材料產(chǎn)業(yè)項(xiàng)目一期工程性
工程名稱廠房
工程質(zhì)
建設(shè)規(guī)模(造工程地
1.6億元整高新區(qū)
價(jià))址
總建筑
總占地面積25.1萬(wàn)平方米86329.25平方米
面積
地基與基礎(chǔ)、樁基檢測(cè)、結(jié)
構(gòu)、建筑、給排水、強(qiáng)電、弱
電、暖通、消防、公共部位精
項(xiàng)目承
建設(shè)單位裝修、室外道路及綜合管網(wǎng)系
包范圍
統(tǒng)、電梯、設(shè)備基礎(chǔ)等工程以
及總包施工圖紙以內(nèi)其它專業(yè)
的預(yù)留預(yù)埋。
5
設(shè)計(jì)單位中凡國(guó)際工程設(shè)計(jì)有限公司
主要分包工程電梯、精裝修、園林綠化等
泰安中化明達(dá)工程勘察有限
勘察單位質(zhì)量合格
公司合
監(jiān)理單位同工期730天
總承包單位中建x局第一建設(shè)有限公司要安全不發(fā)生重大安全事故
求綠色
質(zhì)量監(jiān)督單位高新區(qū)/
施工
工程主要功能
廠房、辦公
或用途
2.2設(shè)計(jì)概況
研發(fā)樓、綜合辦公樓外墻建筑做法一覽表
工序建筑做法(從內(nèi)至外)
基層墻面基層處理
抹灰層20厚DPM20砂漿找平層;墻體不同材料交界處加300寬鋼絲網(wǎng);
50厚擠塑聚苯板(防火等級(jí)B1級(jí)),層間設(shè)置300高玻璃巖棉
保溫層板,底部設(shè)置鋼托
15厚抹面膠漿,中間壓入一層耐堿玻纖網(wǎng)格布
膩?zhàn)优涮啄退佔(zhàn)臃直榕?抹平
滾刷真石漆底漆
真石漆噴涂真石漆
滾刷真石漆罩面漆二遍,含分隔縫處理
車間3偏跨外墻建筑做法一覽表
工序建筑做法(從內(nèi)至外)
基層墻面基層處理
抹灰層20厚DPM20砂漿找平層;墻體不同材料交界處加300寬鋼絲網(wǎng);
50厚擠塑聚苯板(防火等級(jí)B1級(jí)),層間設(shè)置300高玻璃巖棉
保溫層
板,底部設(shè)置鋼托
6
工序建筑做法(從內(nèi)至外)
15厚抹面膠漿,中間壓入一層耐堿玻纖網(wǎng)格布
膩?zhàn)优涮啄退佔(zhàn)臃直榕?抹平
滾刷抗堿底漆
外墻涂料
噴涂外墻涂料兩遍,分隔縫處理
節(jié)點(diǎn)及特殊部位構(gòu)造做法
序號(hào)節(jié)點(diǎn)及特殊部位參照施工圖紙或配圖
1女兒墻內(nèi)側(cè)25厚膠粉聚苯顆粒保溫砂漿
2混凝土雨棚30厚玻化微珠保溫砂漿
3空調(diào)板等外挑構(gòu)件30厚?;⒅楸厣皾{
4外窗收口部位外墻深化圖
設(shè)備機(jī)位百葉遮蔽范圍內(nèi)頂板、側(cè)頂板與底板采用30厚?;⒅楸?/p>
5板、底板及墻面,空調(diào)室外挑板及外溫砂漿,側(cè)板保溫做法同外墻保溫
挑板,鋼筋混凝土雨篷。做法,真石漆采用平涂漆
6外窗上口聚合物抗裂砂漿做鷹嘴
7外窗下口30厚?;⒅楸厣皾{5%外找坡
8外墻線條處150厚擠塑板
2.3工程施工條件
1、砌筑工程全部施工完成。
2、主體結(jié)構(gòu)驗(yàn)收完成。
3、吊籃安裝完成,作業(yè)區(qū)域安全防護(hù)到位,具體施工要求詳見(jiàn)吊籃專項(xiàng)施
工方案。
4、材料及機(jī)具已到位,確保滿足施工進(jìn)度要求。
5、勞動(dòng)力準(zhǔn)備就緒,生活設(shè)施齊全,住宿安排合理。
6、參與施工的人員已進(jìn)行了技術(shù)、安全和文明施工的交底。
7
第三章施工安排
3.1項(xiàng)目管理組織
xx金屬新材料項(xiàng)目管理人員及職責(zé)分工
序號(hào)職務(wù)姓名職稱職責(zé)和權(quán)限
1、履行與業(yè)主簽訂的工程總承包合同與書(shū)
面承諾。
3、負(fù)責(zé)施工所需人、財(cái)、物的組織管理與
中級(jí)控制。
1項(xiàng)目經(jīng)理莊新龍
工程師4、負(fù)責(zé)分包進(jìn)度、質(zhì)量、安全、文明等綜
合協(xié)調(diào)。
5、針對(duì)吊籃工程實(shí)施過(guò)程中的問(wèn)題組織專
題討論和方案論證,處理專業(yè)分包的管理
和協(xié)調(diào)問(wèn)題,保證吊籃工程的有效實(shí)施。
1、全面負(fù)責(zé)項(xiàng)目的技術(shù)管理工作,負(fù)責(zé)吊
籃施工方案的編制和方案的交底。
2、全面負(fù)責(zé)吊籃施工的技術(shù)、質(zhì)量管理,
中級(jí)
2項(xiàng)目總工秦家順竣工驗(yàn)收。
工程師
3、主持項(xiàng)目部例會(huì)并根據(jù)現(xiàn)場(chǎng)實(shí)際工程進(jìn)
度及時(shí)調(diào)整施工計(jì)劃,并進(jìn)行資源再分
配。
1、協(xié)助項(xiàng)目經(jīng)理工作,具體負(fù)責(zé)物資設(shè)備
采購(gòu)和商務(wù)合約管理工作。
2、在項(xiàng)目經(jīng)理的領(lǐng)導(dǎo)下,對(duì)施工管理的重
3商務(wù)經(jīng)理張新榮工程師要或重大決策進(jìn)行研究,形成決議,并分
別予以落實(shí)。
3、負(fù)責(zé)施工現(xiàn)場(chǎng)的各種物資資源管理。
4、負(fù)責(zé)分包商工作的協(xié)調(diào)。
1、負(fù)責(zé)工程質(zhì)量的現(xiàn)場(chǎng)監(jiān)督檢查和質(zhì)量驗(yàn)
收。
2、負(fù)責(zé)一般不合格品的處置,發(fā)現(xiàn)嚴(yán)重不
4質(zhì)量工程師高志剛工程師合格品及時(shí)報(bào)告技術(shù)負(fù)責(zé)人,并負(fù)責(zé)處置
后的質(zhì)量驗(yàn)收與評(píng)定。
3、對(duì)勞務(wù)分包和施工班組提出質(zhì)量獎(jiǎng)罰。
4、負(fù)責(zé)巖棉板等材料的質(zhì)量,保溫施工質(zhì)
8
量監(jiān)督、檢查工作。
1、參與危險(xiǎn)源辨識(shí)、風(fēng)險(xiǎn)評(píng)價(jià)與控制策
劃,參與環(huán)境因素的識(shí)別與評(píng)價(jià)。
2、參與吊籃工程職業(yè)健康安全與環(huán)境管理
規(guī)劃、管理方案及技術(shù)措施方案的制定,
落實(shí)相關(guān)責(zé)任。
助理
5安全總監(jiān)岳仁瑞3、巡回進(jìn)行吊籃工程職業(yè)健康安全/環(huán)境
工程師
管理檢查,對(duì)關(guān)鍵特性參數(shù)定期進(jìn)行監(jiān)
測(cè),發(fā)現(xiàn)問(wèn)題下達(dá)整改通知單,并對(duì)整改
情況進(jìn)行驗(yàn)證。
4、負(fù)責(zé)吊籃工程職業(yè)健康安全/環(huán)境應(yīng)急
準(zhǔn)備檢查,按應(yīng)急預(yù)案進(jìn)行響應(yīng)
1、編制施工技術(shù)交底;
2、監(jiān)督檢查各施工工序;
劉宗武
3、按分工實(shí)施施工過(guò)程及其產(chǎn)品的監(jiān)視和
6專業(yè)工程師龍厚濤工程師
測(cè)量。
丁磊
4、負(fù)責(zé)分管專業(yè)的施工生產(chǎn)調(diào)度與協(xié)調(diào),
及時(shí)溝通有關(guān)信息。
1、負(fù)責(zé)工程項(xiàng)目的物資控制,包括經(jīng)上級(jí)
授權(quán)對(duì)物資供應(yīng)商進(jìn)行評(píng)價(jià)、實(shí)施招標(biāo)采
物資工程師助理工購(gòu)、做好進(jìn)場(chǎng)物資的驗(yàn)證和記錄、物資保
10衣明彤
材料工程師程師管、標(biāo)識(shí)等;
2、監(jiān)督檢查分包商自行采購(gòu)物資的控制,
負(fù)責(zé)不合格物資的處置和記錄。
1、審核分包簽證,辦理分包結(jié)算;
11商務(wù)工程師張新榮工程師2、參與項(xiàng)目經(jīng)濟(jì)活動(dòng)分析,及時(shí)溝通相關(guān)
信息。
3.2各項(xiàng)資源供應(yīng)方式
3.2.1勞務(wù)資源安排一覽表
單體名稱專業(yè)施工隊(duì)名稱開(kāi)始施工時(shí)間工期勞動(dòng)力安排責(zé)任人
研發(fā)樓濟(jì)南文洋2023.11.160天60劉宗武
綜合辦公樓濟(jì)南文洋2023.11.660天50丁磊
車間3濟(jì)南文洋2023.11.1145天50龍厚濤
3.2.2工程用大宗物資供應(yīng)安排一覽表
9
物資名稱規(guī)格型號(hào)單位數(shù)量責(zé)任人
擠塑聚苯板(XPS板)1200×600×50㎡8000
半硬質(zhì)巖礦棉板TR7.5-1200×300×50㎡400
膠粘劑/㎡/
聚合物抹面膠漿/㎡/
耐堿玻璃纖維網(wǎng)格布160g/㎡㎡25000
衣明彤
錨固釘φ8×142mm個(gè)/
灰白色、米黃色、灰黑
真石漆涂料㎡25000
色
柔性耐水膩?zhàn)?5kg/袋kg2000
3.3施工流水段的劃分
本工程各施工段相對(duì)獨(dú)立,原則上可以同時(shí)進(jìn)行施工。各施工區(qū)段具體施
工順序,根據(jù)現(xiàn)場(chǎng)主體結(jié)構(gòu)的完成時(shí)間、總體建筑施工部署、建筑形象展示要
求等及時(shí)介入施工。本工程施工區(qū)段施工順序?yàn)椋貉邪l(fā)樓→綜合辦公樓→車間
3。
3.4工程施工重點(diǎn)和難點(diǎn)分析及應(yīng)對(duì)措施
重點(diǎn)和難
序號(hào)具體分析應(yīng)對(duì)措施責(zé)任人
點(diǎn)
編制與實(shí)際工程密切相
符的施工技術(shù)方案,外
工藝較多,施工部位
保溫工藝墻施工前對(duì)作業(yè)人員進(jìn)
1劃分繁瑣,不利于施秦家順
較多行詳細(xì)的施工技術(shù)交
工
底,并對(duì)關(guān)鍵位置施工
過(guò)程進(jìn)行旁站監(jiān)督。
編制與實(shí)際工程密切相
收邊、收口對(duì)每個(gè)工
符的施工技術(shù)方案,外
程來(lái)說(shuō)都是施工的重各區(qū)專業(yè)工
收邊、收墻施工前對(duì)作業(yè)人員進(jìn)
2點(diǎn),收邊收口的好壞程師、質(zhì)量
口行詳細(xì)的施工技術(shù)交
直接影響施工的質(zhì)工程師
底,并對(duì)關(guān)鍵位置施工
量。
過(guò)程進(jìn)行旁站監(jiān)督。
高處作業(yè)容易引發(fā)高做好對(duì)進(jìn)場(chǎng)施工作業(yè)人各區(qū)專業(yè)工
3高處作業(yè)出墜落、高空墜物等員的安全技術(shù)交底,每程師、安全
安全事故天對(duì)施工作業(yè)人員進(jìn)行工程師、技
10
重點(diǎn)和難
序號(hào)具體分析應(yīng)對(duì)措施責(zé)任人
點(diǎn)
班前教育,加強(qiáng)過(guò)程監(jiān)質(zhì)量工程師
督
施工期間面臨冬季施提前注意天氣變化,
飾面層質(zhì)秦家順
4工,外涂飾層施工質(zhì)當(dāng)天施工應(yīng)避開(kāi)低溫時(shí)
量高志剛
量易受到影響段
3.5關(guān)鍵及特殊過(guò)程控制
3.5.1安全重大危險(xiǎn)源
可能導(dǎo)致的
序號(hào)危險(xiǎn)源管理措施
事故
未佩戴好個(gè)機(jī)械傷害、項(xiàng)目部加強(qiáng)管理,對(duì)工人進(jìn)行安全教育,
1人勞動(dòng)保護(hù)物體打擊、安全員每日進(jìn)行巡視,為佩戴好個(gè)人勞動(dòng)
用品高空墜落保護(hù)用品不得進(jìn)入施工現(xiàn)場(chǎng)
1)輕拿慢放,規(guī)范作業(yè),注意安全。
2違章作業(yè)物體打擊
2)持證上崗,加強(qiáng)過(guò)程管控。
外墻保溫施
3高處墜落加強(qiáng)對(duì)吊籃使用的日常管理。
工
3.5.2主控項(xiàng)目
主控項(xiàng)目:
基層墻體:個(gè)各種穿墻洞已封堵;
檢查數(shù)量:全數(shù)檢查;
墻體平整,塵土、污垢、油漬清理干凈,基層干燥;
檢查數(shù)量:全數(shù)檢查;
保溫板保溫系統(tǒng)性能指標(biāo):
用于保溫工程的材料、構(gòu)配件等,其品種、規(guī)格應(yīng)符合設(shè)計(jì)及規(guī)范要求;
保溫板及巖棉板的導(dǎo)熱系數(shù)、密度、強(qiáng)度、吸水量、憎水率、燃燒性能、
酸堿系數(shù)等膠粘劑、抹面膠漿的拉伸粘結(jié)強(qiáng)度;
保溫板的厚度,與各構(gòu)造層之間的粘結(jié),錨栓數(shù)量、位置、深度、拉拔力,
收口處及飾面層的防水處理;
檢查數(shù)量:全數(shù)檢查;
3.6項(xiàng)目管理目標(biāo)
11
項(xiàng)目管理目標(biāo)名稱目標(biāo)值
外墻工期60天
1)工藝執(zhí)行率100%;
質(zhì)量目標(biāo)2)工程竣工一次驗(yàn)收合格率100%;
3)成品保護(hù)完好率100%;
零傷亡,無(wú)安全事故發(fā)生
1)安全防護(hù)用品正確配備率100%;
安全文明目標(biāo)
2)安全防護(hù)措施執(zhí)行率100%;
3)無(wú)觸電事故、坍塌事故及重傷事故發(fā)生。
在施工過(guò)程中減少噪音排放,無(wú)路面污染
1)施工現(xiàn)場(chǎng)噪聲達(dá)標(biāo)排放;
綠色施工目標(biāo)
2)施工現(xiàn)場(chǎng)固體廢棄物分類收集安全處置;相關(guān)方無(wú)
環(huán)問(wèn)題投訴。
第四章施工進(jìn)度計(jì)劃
樓號(hào)開(kāi)始日期施工時(shí)間完工日期吊籃位置吊籃臺(tái)數(shù)
研發(fā)樓2023.10.2660天2023.12.25分批搭設(shè)32
綜合辦公樓2023.11.160天2023.12.20分批搭設(shè)24
車間3偏跨2023.11.660天2023.1.5分批搭設(shè)10
第五章施工準(zhǔn)備與資源配置計(jì)劃
5.1施工準(zhǔn)備計(jì)劃
5.1.1技術(shù)準(zhǔn)備
表5.1.1-1技術(shù)文件準(zhǔn)備計(jì)劃一覽表
配備數(shù)
序號(hào)文件名稱文件編號(hào)持有人
量
1《建筑節(jié)能工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50411-20232秦家順
2《建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)》GB50300-20132秦家順
3《建筑裝飾裝修工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)》GB50210-20182秦家順
12
4《外墻外保溫工程技術(shù)標(biāo)準(zhǔn)》JGJ144-20232秦家順
6《建筑施工高處作業(yè)安全技術(shù)規(guī)范》JGJ80-20162秦家順
《施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)范(附秦家順
7JGJ46-20052
條文說(shuō)明)》
8《施工現(xiàn)場(chǎng)機(jī)械設(shè)備檢查技術(shù)規(guī)范》JGJ160-20162秦家順
9《建筑機(jī)械使用安全技術(shù)規(guī)程》JGJ33-20122秦家順
《建筑施工工具式腳手架安全技術(shù)規(guī)秦家順
10JGJ202-20102
范》
表5.1.1-2施工試驗(yàn)檢驗(yàn)計(jì)劃表
工程部檢驗(yàn)時(shí)
序號(hào)檢驗(yàn)項(xiàng)目單位檢驗(yàn)頻率責(zé)任人
位間
導(dǎo)熱系數(shù),垂直于同廠家同品種5000
1巖棉板表面的抗拉強(qiáng)度,塊㎡/次,每次隨機(jī)使用前劉宗武
酸度系數(shù)3塊
密度、導(dǎo)熱系數(shù)、同廠家同品種
擠塑聚
2壓縮強(qiáng)度、尺寸穩(wěn)塊20000㎡/次,每次使用前劉宗武
苯板
定性、燃燒性能隨機(jī)3塊
同廠家同品種5000
標(biāo)準(zhǔn)狀態(tài)和耐水拉㎡/次,每次隨機(jī)
抹面膠
3伸粘結(jié)強(qiáng)度(與巖Kg抽取5袋,每袋使用前劉宗武
漿
棉條),抗沖擊性2k,總計(jì)不少于
10k
標(biāo)準(zhǔn)狀態(tài)拉伸粘結(jié)同廠家同品種5000
強(qiáng)度(與水泥砂㎡/次,每次隨機(jī)
4膠粘劑漿),標(biāo)準(zhǔn)狀態(tài)拉Kg抽取5袋,每袋使用前劉宗武
伸粘結(jié)強(qiáng)度(與巖2k,總計(jì)不少于
棉條)10k
耐堿斷裂強(qiáng)力、耐
5玻纖網(wǎng)㎡每5000㎡抽取5㎡使用前劉宗武
堿斷裂強(qiáng)力保留率
同廠家同品種每
抗拉承載力標(biāo)準(zhǔn)5000㎡1次,每次
6錨栓個(gè)使用前劉宗武
值、錨盤(pán)剛度隨機(jī)5箱,每箱2
個(gè)共計(jì)10個(gè)
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 2025年度離婚案件訴訟支持合同4篇
- Module9(教學(xué)設(shè)計(jì))-2024-2025學(xué)年外研版(三起)英語(yǔ)四年級(jí)上冊(cè)
- 2024-2030年中國(guó)航空航天工業(yè)軟件行業(yè)發(fā)展監(jiān)測(cè)及發(fā)展趨勢(shì)預(yù)測(cè)報(bào)告
- 合同范本 視頻制作
- 2025年白花菜項(xiàng)目可行性研究報(bào)告
- 木材改性機(jī)行業(yè)深度研究報(bào)告
- 城市軌道交通論文題目
- 湖北重點(diǎn)項(xiàng)目-鹽化工循環(huán)經(jīng)濟(jì)產(chǎn)業(yè)園項(xiàng)目可行性研究報(bào)告(撰寫(xiě)大綱)
- 2025年創(chuàng)意產(chǎn)業(yè)園商鋪?zhàn)赓U合作協(xié)議
- 2025年增韌稀釋劑行業(yè)深度研究分析報(bào)告
- 貸款的培訓(xùn)課件
- 《雷達(dá)干擾技術(shù)概述》課件
- 新概念英語(yǔ)青少版入門(mén) A-Unit-1課件(共98張)
- 中國(guó)金融書(shū)法家協(xié)會(huì)入會(huì)申請(qǐng)表
- 廣西易多收生物科技有限公司河池化工廠綠色節(jié)能生產(chǎn)升級(jí)項(xiàng)目環(huán)境影響報(bào)告書(shū)
- 北京市海淀區(qū)九年級(jí)英語(yǔ)第二學(xué)期期末練習(xí)(初三中考二模)試卷講評(píng)-客觀題
- (完整版)園藝產(chǎn)品貯藏與加工
- 中國(guó)古典文獻(xiàn)-第七章-文獻(xiàn)目錄
- 學(xué)前教育大專畢業(yè)論文3000字
- 注塑領(lǐng)班簡(jiǎn)歷樣板
- 骨骼肌-人體解剖學(xué)-運(yùn)動(dòng)系統(tǒng)
評(píng)論
0/150
提交評(píng)論