新橋社區(qū)綜合體建設(shè)工程項(xiàng)目
土方開(kāi)挖、基坑支護(hù)及降水專(zhuān)項(xiàng)施工方案
編制單位:中國(guó)建筑第x工程局有限公司
編制人:
編制日期:
2023年7月發(fā)布2023年7月實(shí)施
目錄
1編制依據(jù)................................................................................................................................................................................1
2工程概況................................................................................................................................................................................2
2.1工程建設(shè)概況一覽表..............................................................................................................................................2
2.2基坑支護(hù)及降水設(shè)計(jì)概況.....................................................................................................................................2
降排水設(shè)計(jì)..............................................................................................................................................................2
基坑支護(hù)設(shè)計(jì).........................................................................................................................................................3
2.3場(chǎng)地環(huán)境與工程地質(zhì)條件.....................................................................................................................................6
2.3.1場(chǎng)地的地理位置.........................................................................................................................................6
氣象水文資料.........................................................................................................................................................6
2.3.3區(qū)域地質(zhì)概況..............................................................................................................................................6
場(chǎng)地地層巖性.........................................................................................................................................................6
水文地質(zhì)條件.........................................................................................................................................................7
周邊環(huán)境條件.........................................................................................................................................................7
3施工安排................................................................................................................................................................................9
3.1項(xiàng)目管理組織與職能分工.....................................................................................................................................9
項(xiàng)目管理組織結(jié)構(gòu)框架.......................................................................................................................................9
項(xiàng)目部人員配置及職責(zé)分工..............................................................................................................................9
3.2項(xiàng)目管理目標(biāo).........................................................................................................................................................12
3.3各類(lèi)資源供應(yīng)方式................................................................................................................................................13
3.4施工流程.................................................................................................................................................................13
施工流程................................................................................................................................................................13
施工工藝流程.......................................................................................................................................................13
4施工準(zhǔn)備與資源配置計(jì)劃...............................................................................................................................................14
4.1施工準(zhǔn)備計(jì)劃.........................................................................................................................................................14
4.2資源配置計(jì)劃........................................................................................................................................................15
5主要施工方法及工藝要求..............................................................................................................................................16
5.1測(cè)量方案.................................................................................................................................................................16
5.1.1測(cè)量總體思路...........................................................................................................................................16
5.1.2測(cè)量準(zhǔn)備....................................................................................................................................................16
5.1.3測(cè)量工程施工質(zhì)量保證措施................................................................................................................17
5.2基坑降水施工方法及工藝要求.........................................................................................................................17
5.2.1基坑降水施工工藝流程.........................................................................................................................18
基坑降水主要施工方法.....................................................................................................................................18
基坑降水質(zhì)量控制措施.....................................................................................................................................20
5.3旋挖樁施工方法及工藝要求..............................................................................................................................20
5.3.1施工準(zhǔn)備....................................................................................................................................................20
5.3.2施工工藝及工序.......................................................................................................................................21
5.3.3施工方法....................................................................................................................................................21
導(dǎo)管、儲(chǔ)料斗安裝..............................................................................................................................................25
灌注混凝土...........................................................................................................................................................25
試塊制作及養(yǎng)護(hù)..................................................................................................................................................26
樁頂保護(hù)................................................................................................................................................................27
5.3.9樁檢測(cè).........................................................................................................................................................27
截樁.........................................................................................................................................................................27
旋挖樁質(zhì)量保證措施.........................................................................................................................................27
安全保證措施.......................................................................................................................................................31
常見(jiàn)事故處理及預(yù)防措施................................................................................................................................32
成品保護(hù)................................................................................................................................................................34
5.4冠梁施工方法及工藝要求..................................................................................................................................35
冠梁概述................................................................................................................................................................35
冠梁施工工序.......................................................................................................................................................35
冠梁施工要點(diǎn).......................................................................................................................................................35
5.5樁間網(wǎng)噴支護(hù)施工方法及工藝要求................................................................................................................37
5.6預(yù)應(yīng)力錨索施工方法及工藝要求.....................................................................................................................38
5.6.1施工方法與特點(diǎn).......................................................................................................................................38
5.6.2施工工藝流程...........................................................................................................................................38
5.7鋼腰梁施工方法及工藝要求..............................................................................................................................39
5.7.1施工方案....................................................................................................................................................39
5.7.2施工工藝要求...........................................................................................................................................40
5.7.3安全環(huán)保措施...........................................................................................................................................41
5.8基坑臨邊防護(hù)施工方法及工藝要求................................................................................................................41
5.9土方開(kāi)挖施工方法及工藝要求.........................................................................................................................41
技術(shù)準(zhǔn)備工作.......................................................................................................................................................41
土石方開(kāi)挖的總體安排.....................................................................................................................................42
土石方施工采取的措施.....................................................................................................................................42
降排水措施...........................................................................................................................................................42
開(kāi)挖過(guò)程中的注意事項(xiàng).....................................................................................................................................43
電梯井、集水坑土方開(kāi)挖要求.......................................................................................................................43
基坑馬道設(shè)置.......................................................................................................................................................43
車(chē)輛沖洗水源.......................................................................................................................................................43
土方開(kāi)挖及回填要求.........................................................................................................................................44
土方開(kāi)挖控制措施..............................................................................................................................................44
5.10基坑監(jiān)測(cè)方案.......................................................................................................................................................44
監(jiān)測(cè)目的................................................................................................................................................................44
監(jiān)測(cè)內(nèi)容................................................................................................................................................................45
監(jiān)測(cè)報(bào)警值及異常情況下的監(jiān)測(cè)措施.........................................................................................................45
基準(zhǔn)點(diǎn)、監(jiān)測(cè)點(diǎn)布設(shè).........................................................................................................................................45
監(jiān)測(cè)頻率................................................................................................................................................................46
6質(zhì)量管理計(jì)劃..................................................................................................................................................................48
6.1工程施工質(zhì)量目標(biāo)...............................................................................................................................................48
6.2質(zhì)量管理組織機(jī)構(gòu)及職責(zé).................................................................................................................................48
6.2.1質(zhì)量管理組織機(jī)構(gòu)..................................................................................................................................48
6.2.2組織機(jī)構(gòu)成員質(zhì)量職責(zé).........................................................................................................................48
6.2.3質(zhì)量管理制度...........................................................................................................................................50
6.2.4質(zhì)量保證措施...........................................................................................................................................52
7安全管理計(jì)劃..................................................................................................................................................................54
7.1安全管理方針、目標(biāo)..........................................................................................................................................54
7.1.1安全管理方針...........................................................................................................................................54
7.1.2安全管理目標(biāo)...........................................................................................................................................54
7.1.3安全管理體系...........................................................................................................................................54
7.2安全管理制度........................................................................................................................................................54
8進(jìn)度管理計(jì)劃..................................................................................................................................................................55
8.1施工進(jìn)度控制點(diǎn)...................................................................................................................................................56
8.2施工進(jìn)度管理職責(zé)分工......................................................................................................................................56
8.3施工進(jìn)度管理措施...............................................................................................................................................56
8.4夜間、農(nóng)忙、節(jié)假日施工保障措施...............................................................................................................57
8.5雨季施工保障措施...............................................................................................................................................58
8.6外部環(huán)境保障措施...............................................................................................................................................60
9成品保護(hù)計(jì)劃......................................................................................................................................................................60
9.1成品保護(hù)組織機(jī)構(gòu)...............................................................................................................................................61
9.2成品保護(hù)的崗位職責(zé)..........................................................................................................................................62
9.3成品保護(hù)的管理制度..........................................................................................................................................62
9.4各參建單位成品保護(hù)的責(zé)任劃分...................................................................................................................63
9.5對(duì)地上、地下設(shè)施和周?chē)ㄖ善繁Wo(hù)......................................................................................................64
10環(huán)境保護(hù)及綠色施工措施.........................................................................................................................................64
10.1施工環(huán)保管理目標(biāo)............................................................................................................................................65
施工環(huán)保管理目標(biāo)..............................................................................................................................................65
施工環(huán)??刂浦笜?biāo)..............................................................................................................................................65
10.2施工環(huán)境保護(hù)體系............................................................................................................................................66
10.2.1環(huán)境保護(hù)組織機(jī)構(gòu)................................................................................................................................66
10.2.2環(huán)境保護(hù)崗位職責(zé)................................................................................................................................66
10.3環(huán)境保護(hù)管理流程............................................................................................................................................67
10.4現(xiàn)場(chǎng)文明施工.....................................................................................................................................................67
11基坑施工應(yīng)急預(yù)案.......................................................................................................................................................69
11.1總體原則...............................................................................................................................................................69
11.2應(yīng)急工作部署.....................................................................................................................................................69
11.3應(yīng)急搶險(xiǎn)組織機(jī)構(gòu).............................................................................................................................................69
11.4基坑工程應(yīng)急救援預(yù)案...................................................................................................................................70
11.5安全生產(chǎn)事故應(yīng)急救援預(yù)案...........................................................................................................................71
11.6項(xiàng)目周邊應(yīng)急配套及線路圖...........................................................................................................................72
項(xiàng)目周?chē)o應(yīng)急救援配套情況.......................................................................................................................72
救援路線圖...........................................................................................................................................................73
11.7文物保護(hù)應(yīng)急預(yù)案............................................................................................................................................73
12驗(yàn)收要求.........................................................................................................................................................................74
12.1驗(yàn)收標(biāo)準(zhǔn)...............................................................................................................................................................74
12.2驗(yàn)收程序...............................................................................................................................................................77
12.3驗(yàn)收內(nèi)容...............................................................................................................................................................77
12.4驗(yàn)收人員...............................................................................................................................................................78
1編制依據(jù)
文件名稱(chēng)編號(hào)
危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定住建部【2018】37號(hào)
建筑基坑工程監(jiān)測(cè)技術(shù)標(biāo)準(zhǔn)GB50497-2023
工程測(cè)量規(guī)范GB50026-2007
建筑工程施工現(xiàn)場(chǎng)供用電安全規(guī)范GB50194-2014
建筑工程施工質(zhì)量驗(yàn)收統(tǒng)一標(biāo)準(zhǔn)GB50300-2013
建筑工程施工質(zhì)量評(píng)價(jià)標(biāo)準(zhǔn)GB/T50375-2006
建筑工程綠色施工評(píng)價(jià)標(biāo)準(zhǔn)GB/T50640-2010
建筑工程施工現(xiàn)場(chǎng)消防安全技術(shù)規(guī)范GB50720-2011
國(guó)
建筑基坑支護(hù)技術(shù)規(guī)程JGJ120-2012
家
標(biāo)建筑邊坡工程技術(shù)規(guī)范GB50330-2013
準(zhǔn)建筑樁基技術(shù)規(guī)范JGJ94-2008
建筑變形測(cè)量規(guī)范JGJ8-2016
施工現(xiàn)場(chǎng)臨時(shí)用電安全技術(shù)規(guī)程JGJ46-2005
建筑施工安全檢查標(biāo)準(zhǔn)JGJ59-2011
JGJ/T111-2016
管井技術(shù)規(guī)范GB50296-2014
混凝土結(jié)構(gòu)設(shè)計(jì)規(guī)范GBJ50010-2010
混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范GB50204-2015
建筑深基坑工程施工安全技術(shù)規(guī)范JGJ311-2013
鋼筋焊接及驗(yàn)收規(guī)程JGJ18-2012
《建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收規(guī)范》GB50202-2018
文件名稱(chēng)編號(hào)
建筑工程資料管理規(guī)程JGJ/T185-2009
地
DB51/T5072-2011
方成都地區(qū)基坑工程安全技術(shù)規(guī)范
標(biāo)
準(zhǔn)四川省危險(xiǎn)性較大的分部分項(xiàng)工程安全管理規(guī)定實(shí)施細(xì)則/
地勘報(bào)告/
基坑支護(hù)設(shè)計(jì)施工圖紙/
1
2工程概況
2.1工程建設(shè)概況一覽表
工程名稱(chēng)新橋社區(qū)綜合體工程性質(zhì)民用建筑
本工程擬建文化活動(dòng)中心為地上
3~5F,設(shè)三層地下室(局部一
建設(shè)規(guī)模層)?!?.00標(biāo)高為511.10m,基工程地址
坑深度6.1~17.1m,采用框架結(jié)
構(gòu),獨(dú)立基礎(chǔ)。
總占地面積9116平方米總建筑面積約3.2萬(wàn)平方米
施工總承包合同內(nèi)的主體結(jié)構(gòu)、水電安
建設(shè)單位項(xiàng)目承包范圍
裝、粗裝飾等全部?jī)?nèi)容
設(shè)計(jì)單位主要分包工程基坑支護(hù)、降水及土方工程
合質(zhì)量合格,爭(zhēng)創(chuàng)四川省優(yōu)質(zhì)結(jié)構(gòu)
同
總承包單位中國(guó)建筑第x工程局有限公司工期540日歷天
要
求安全爭(zhēng)創(chuàng)四川省安全文明標(biāo)化工地
工程主要功能
社區(qū)文化活動(dòng)中心
或用途
2.2基坑支護(hù)及降水設(shè)計(jì)概況
1、該工程設(shè)三層地下室(局部為一層),±0.000標(biāo)高為511.10m,設(shè)計(jì)場(chǎng)地平整后
標(biāo)高按504.90m~511.00m考慮,基坑開(kāi)挖深度最大為17.10m;基坑開(kāi)挖線與地下室基礎(chǔ)
邊線預(yù)留1.20m工作面,基坑周長(zhǎng)333.98m,基坑開(kāi)挖面積約5777.89m2。
2、本基坑安全等級(jí)為一級(jí)(一層以及一層和三層地下室交界處為二級(jí))。設(shè)計(jì)采用
機(jī)械旋挖灌注樁(懸壁樁)、機(jī)械旋挖灌注樁+預(yù)應(yīng)力錨索(錨拉樁)、局部采用放坡網(wǎng)噴
相結(jié)合的支護(hù)結(jié)構(gòu)體系。
3、本基坑采用管井降水措施,沿基坑頂部布設(shè)14口降水井,井深30.0m,間距約
25.0m。
降排水設(shè)計(jì)
1、地下水控制
根據(jù)場(chǎng)地工程地質(zhì)、水文地質(zhì)條件、基坑開(kāi)挖深度及周邊環(huán)境情況,設(shè)計(jì)采用基坑四
周管井降水、集水明排相結(jié)合的降排水方案?;又苓叢贾媒邓?,降水井間距約25m,
井深30.0m,降水井上部井壁管5m,下部進(jìn)濾管22.5m,底部沉砂管2.5m。成井規(guī)格:降
水井內(nèi)徑不小于300mm,成孔直徑不小于560mm;降水井施工完成后注意井口防護(hù),防治
2
雜物掉進(jìn)井內(nèi),發(fā)生停電時(shí),應(yīng)緊急轉(zhuǎn)換至備用電源,保證降水井的正常工作。
2、地表水控制
(1)距基坑上口外邊沿0.5m處設(shè)置240mm磚砌擋水臺(tái),高度300mm,1:2.5水泥砂
漿雙面抹灰,上做100mm高C20細(xì)石混凝土壓頂,并設(shè)置1100mm高護(hù)欄(總高度
1400mm)護(hù)欄采用外徑48mm、壁厚3.5mm鋼管(無(wú)嚴(yán)重銹蝕、彎曲、壓扁、裂紋),鋼管
入土深度不小于30cm。
(2)擋水臺(tái)外側(cè)設(shè)置排水溝,排水溝寬深300×300mm,以防雨水進(jìn)入基坑。
(3)根據(jù)支護(hù)設(shè)計(jì),基坑擋水臺(tái)至圍擋邊均采用混凝土硬化,按照?qǐng)龅厥褂霉δ艽_定
硬化厚度。
基坑支護(hù)設(shè)計(jì)
本基坑安全等級(jí)為一級(jí)(一層以及一層和三層地下室交界處為二級(jí))。采用機(jī)械旋挖
灌注樁(懸壁樁)、機(jī)械旋挖灌注樁+預(yù)應(yīng)力錨索(錨拉樁)的支護(hù)結(jié)構(gòu)體系?;又ёo(hù)平
面布置圖及分段設(shè)計(jì)匯總?cè)缦拢?/p>
3
圖2.1基坑支護(hù)平面布置圖
4
5
2.3場(chǎng)地環(huán)境與工程地質(zhì)條件
2.3.1場(chǎng)地的地理位置
511.32m~512.20m,高差0.88m,整體較為平坦。
氣象水文資料
947mm。豐水期為6~9月份,降水量占全年降水量74%,枯水期1~3月份,其余為
平水期。相對(duì)濕度多年年平均為82%,多年年平均蒸發(fā)量為1020.50mm。
多年年平均氣溫16.2℃,極端最高氣溫為37.3℃,極端最低氣溫-5.9℃。
多年年平均風(fēng)速為1.35m/s,最大風(fēng)速14.8m/s,極大風(fēng)速為27.4m/s(1961年6月
2日),最多風(fēng)向?yàn)楸奔氨睎|風(fēng)向,多年年平均風(fēng)壓力為140Pa,最大風(fēng)壓力為250Pa。
2.3.3區(qū)域地質(zhì)概況
成都平原在地質(zhì)構(gòu)造體系上位于華夏系龍門(mén)山隆起褶帶和新華系龍泉山褶皺帶之
間。老第三系,隨著青藏高原的上升,龍泉山和龍門(mén)山也跟隨隆起,但地面高差不大,待
進(jìn)入早更新世,龍門(mén)山急劇抬升,龍泉山亦隨著抬升,平原兩側(cè)坳陷形成,粗顆粒的卵礫
石土堆積其間。早更新世晚期至中更新世早期,龍門(mén)山、龍泉山繼續(xù)抬升,整個(gè)平原普遍
下沉,中更新世晚期,新構(gòu)造運(yùn)動(dòng)更加劇烈。龍門(mén)山、龍泉山加速抬升過(guò)程中,原在的一
些主要斷裂繼續(xù)加強(qiáng)活動(dòng),成都坳陷解體,東部邊緣構(gòu)造帶和西部邊緣構(gòu)造帶上升,局部
成為臺(tái)地,中央凹陷和邊緣構(gòu)造帶的部分地段繼續(xù)沉降,接受上更新統(tǒng)沉積,最終形成了
成都平原現(xiàn)今的構(gòu)造輪廓和地貌景觀。
成都平原所處地殼為一穩(wěn)定地塊,東距龍泉山褶帶約60公里,兩側(cè)距龍門(mén)山褶帶約
30公里,龍門(mén)山斷裂帶于2008年5月12日發(fā)生8級(jí)強(qiáng)震,成都地區(qū)震感強(qiáng)烈,但未造
成重大破壞,從區(qū)域構(gòu)造上看,場(chǎng)地所處區(qū)域構(gòu)造穩(wěn)定性相對(duì)較好,擬建場(chǎng)區(qū)內(nèi)未發(fā)現(xiàn)滑
坡、坍塌等不良地質(zhì)現(xiàn)象。
場(chǎng)地地層巖性
ml
根據(jù)本次勘察資料,場(chǎng)地上覆第四系人工填土(Q4),其下由第四系全新統(tǒng)沖洪積
al+pl
(Q4)成因的粉土、砂及卵石組成。地層從上至下描述如下:
(1)雜填土①1:色雜;松散;干燥~稍濕;由混凝土塊、磚瓦、卵石、炭渣等建筑
垃圾組成,含少量粘性土,系新近填土,堆積時(shí)間3~6年。該層場(chǎng)地內(nèi)均有分布,層厚
0.50m~3.20m。
(2)素填土①2:褐黃、褐灰色;松散~稍密;稍濕;以粉土為主,含少量雜質(zhì)及植
6
物根系,堆填時(shí)間在6~8年。該層場(chǎng)地內(nèi)局部地段分布,層厚1.00m~1.50m。
(3)粉土②:黃褐色;中密;濕~很濕。含鐵錳質(zhì)、氧化鐵和少許云母碎片。該層
在場(chǎng)地內(nèi)大部分地段分布,層厚0.90m~3.60m。
(4)細(xì)砂③:褐灰、褐青色,濕,松散;以長(zhǎng)石、石英顆粒為主,含少量云母粉和
暗色礦物,局部混有少量卵石及圓礫。呈層狀分布于卵石層頂板上,局部地段含泥較重,
層厚1.00m~2.80m。
(5)中砂④:褐灰、褐青色,濕~飽和,稍密;以長(zhǎng)石、石英為主,局部地段含少
量粘性土、圓礫。呈透鏡狀或?qū)訝罘植加诼咽瘜又?,層?.60m~2.30m。
(6)卵石⑤:褐青、褐灰色等,濕~飽和。主要以花崗巖、砂巖及石英巖等組成,
強(qiáng)~微風(fēng)化,一般粒徑2~10cm,大者可達(dá)15cm以上,隙間充填砂、圓礫等,局部地段
含少量粘性土;卵石層頂板埋深2.60m~6.70m,標(biāo)高505.12m~508.94m。據(jù)N120動(dòng)探試
驗(yàn),卵石層密實(shí)度可分為松散、稍密、中密及密實(shí)四個(gè)亞層:
松散卵石⑤1:褐青色、褐灰色;排列十分混亂,絕大部份不接觸;卵石含量50~
55%,層厚1.40m~8.90m;
稍密
溫馨提示
- 1. 本站所有資源如無(wú)特殊說(shuō)明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁(yè)內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒(méi)有圖紙預(yù)覽就沒(méi)有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫(kù)網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 二零二五版石材鋼架施工項(xiàng)目信息化管理合同4篇
- 2025版木結(jié)構(gòu)家居定制設(shè)計(jì)與制造合同4篇
- 2025版國(guó)際港口勞務(wù)合作合同范本3篇
- 2025版美容院安全管理制度與應(yīng)急預(yù)案合同3篇
- 2025年度木工企業(yè)戰(zhàn)略規(guī)劃與投資合作合同4篇
- 便利店顧客體驗(yàn)優(yōu)化與交互設(shè)計(jì)考核試卷
- 二零二五版新能源儲(chǔ)能技術(shù)研發(fā)與投資合同匯編4篇
- 2025版工業(yè)涂料工程承攬合同范本2篇
- 2025版實(shí)習(xí)員工實(shí)習(xí)期間勞動(dòng)防護(hù)用品供應(yīng)合同3篇
- 2025年借殼上市合同簽署草約規(guī)例范
- 2024-2030年中國(guó)海泡石產(chǎn)業(yè)運(yùn)行形勢(shì)及投資規(guī)模研究報(bào)告
- 動(dòng)物醫(yī)學(xué)類(lèi)專(zhuān)業(yè)生涯發(fā)展展示
- 2024年同等學(xué)力申碩英語(yǔ)考試真題
- 消除“艾梅乙”醫(yī)療歧視-從我做起
- 非遺文化走進(jìn)數(shù)字展廳+大數(shù)據(jù)與互聯(lián)網(wǎng)系創(chuàng)業(yè)計(jì)劃書(shū)
- 2024山西省文化旅游投資控股集團(tuán)有限公司招聘筆試參考題庫(kù)附帶答案詳解
- 科普知識(shí)進(jìn)社區(qū)活動(dòng)總結(jié)與反思
- 加油站廉潔培訓(xùn)課件
- 現(xiàn)金日記賬模板(帶公式)
- 消化內(nèi)科專(zhuān)科監(jiān)測(cè)指標(biāo)匯總分析
- 混凝土結(jié)構(gòu)工程施工質(zhì)量驗(yàn)收規(guī)范
評(píng)論
0/150
提交評(píng)論