鋼結(jié)構(gòu)框架結(jié)構(gòu)廠房投標(biāo)技術(shù)方案
目錄
1.工程概況及特點(diǎn).................................................9
1.1建筑概況...................................................9
1.2結(jié)構(gòu)概況................................................10
1.2.1基礎(chǔ)...................................................10
1.2.2主體...................................................10
1.3安裝工程概況.............................................10
1.3.1概述...................................................10
1.3.2工程概況...............................................10
1.4工程特點(diǎn)................................................11
1.4.1施工場(chǎng)地文明施工難度大.................................11
1.4.2工程特殊部位較多.......................................12
2.施工組織設(shè)計(jì)總體設(shè)想.........................................12
2.1工程建設(shè)目標(biāo).............................................12
2.1.1質(zhì)量管理目標(biāo)...........................................12
2.1.2工期管理目標(biāo)...........................................12
2.1.3安全生產(chǎn)管理目標(biāo).......................................12
2.1.4文明施工管理目標(biāo).......................................12
2.2質(zhì)量控制重點(diǎn).............................................12
3.施工部署.......................................................13
3.1組織機(jī)構(gòu).................................................13
3.1.1項(xiàng)目部的組織機(jī)構(gòu).......................................13
3.2強(qiáng)化項(xiàng)目管理.............................................14
3.2.1編制和實(shí)施項(xiàng)目管理實(shí)施計(jì)劃............................14
3.2.2貫徹落實(shí)公司的規(guī)章制度.................................14
3.2.3逐層分解指標(biāo),明確責(zé)、權(quán)、利...........................14
3.2.4嚴(yán)格執(zhí)行施工組織設(shè)計(jì)..................................15
3.2.5執(zhí)行質(zhì)量進(jìn)度公開制.....................................15
3.2.6業(yè)主滿意...............................................15
3.3項(xiàng)目管理部職責(zé)...........................................15
3.4項(xiàng)目管理部主要部門、崗位職責(zé)............................16
3.4.1項(xiàng)目經(jīng)理...............................................16
3.4.2項(xiàng)目副經(jīng)理.............................................16
3.4.3項(xiàng)目總工程師...........................................17
3.4.4項(xiàng)目部的管理職責(zé).......................................17
3.5項(xiàng)目經(jīng)理長(zhǎng)駐現(xiàn)場(chǎng)措施....................................18
3.5.1建立請(qǐng)假制度...........................................18
3.5.2建立約束機(jī)制...........................................18
3.5.3實(shí)行項(xiàng)目經(jīng)理評(píng)分制.....................................18
3.6勞務(wù)工資管理和發(fā)放措施.................................19
3.7施工組織.................................................19
3.7.1施工區(qū)、段劃分........................................19
3.7.2施工順序...............................................19
3.8資源配置.................................................21
3.8.1勞動(dòng)力安排計(jì)劃.........................................21
3.8.2工程投入的主要施工機(jī)械設(shè)備安排計(jì)劃...................22
3.8.3周轉(zhuǎn)材料配備...........................................24
3.8.4成品、半成品加工與組織.................................25
4.施工準(zhǔn)備.....................................................26
4.1現(xiàn)場(chǎng)準(zhǔn)備.................................................26
4.1.1周邊環(huán)境的了解.........................................26
4.1.2場(chǎng)地平整...............................................26
4.2技術(shù)準(zhǔn)備.................................................26
4.2.1圖紙會(huì)審...............................................26
4.2.2施工組織設(shè)計(jì)和施工方案.................................27
4.3物資準(zhǔn)備.................................................27
4.3.1編制材料計(jì)劃...........................................27
4.3.2材料供應(yīng)商選擇.........................................27
4.3.3材料進(jìn)場(chǎng)...............................................28
4.3.4材料檢測(cè)...............................................28
4.4設(shè)備準(zhǔn)備.................................................29
4.4.1設(shè)備組織...............................................29
5.協(xié)調(diào)、配合及服務(wù).............................................29
5.1與設(shè)計(jì)院的協(xié)調(diào)配合.......................................29
5.2與監(jiān)理的協(xié)調(diào)配合.........................................29
5.3與業(yè)主協(xié)調(diào)配合...........................................30
5.4與質(zhì)檢站的協(xié)調(diào)配合.......................................30
5.5與公安部門的協(xié)調(diào)配合....................................30
5.6與業(yè)主指定分包單位的協(xié)調(diào)配合...........................30
5.7與社會(huì)各界的協(xié)調(diào).........................................30
5.7.1與地方安全部門的協(xié)調(diào)配合...............................30
5.7.2與地方環(huán)境監(jiān)測(cè)單位的協(xié)調(diào)配合...........................31
5.8內(nèi)部關(guān)系的協(xié)調(diào)配合.......................................31
5.9服務(wù).....................................................31
6.土建各分部分項(xiàng)工程主要施工方案...............................32
6.1施工測(cè)量.................................................32
6.1.1平面控制...............................................32
6.1.2垂直度控制.............................................33
6.1.3標(biāo)高抄測(cè)...............................................33
6.1.4精度要求...............................................33
6.1.5沉降觀測(cè)...............................................34
6.2基礎(chǔ)工程.................................................34
6.2.1基礎(chǔ)土方...............................................34
6.2.2基礎(chǔ)施工...............................................36
6.2.3基礎(chǔ)模板...............................................36
6.2.4基礎(chǔ)鋼筋工程...........................................37
6.2.5基礎(chǔ)混凝土.............................................38
6.3主體工程.................................................39
6.3.1模板工程...............................................39
6.3.2鋼筋工程...............................................43
6.3.3混凝土工程.............................................44
6.3.4砌體結(jié)構(gòu)...............................................46
6.4保溫隔熱屋面.............................................50
6.4.1工藝流程...............................................50
6.4.2找平層.................................................50
6.4.3防水卷材施工..........................................50
6.4.4保溫層施工.............................................51
6.4.5細(xì)石砼面層施工.........................................52
6.5裝飾工程.................................................52
6.5.1室內(nèi)抹灰工程...........................................52
6.5.2外墻保溫層施工.........................................53
6.5.3乳膠漆墻面施工.......................................53
6.5.4油漆工程...............................................55
6.5.5門窗工程...............................................55
6.5.6欄桿安裝...............................................58
6.6樓地面工程...............................................58
6.6.1水泥細(xì)石砼樓地面.......................................58
6.7室外散水.................................................59
6.8腳手架工程...............................................59
6.8.1外腳手架...............................................59
6.8.2腳手架的防雷接地.......................................62
6.8.3內(nèi)腳手架...............................................62
6.8.4安全防護(hù)架.............................................62
6.8.5腳手架拆除.............................................63
7.安裝各分部分項(xiàng)工程的施工方案...............................64
7.1給排水工程施工方案.......................................64
7.1.1預(yù)埋件的安裝...........................................64
7.1.2管道施工流程...........................................64
7.1.3PP-R管安裝.............................................65
7.1.4排水管安裝.............................................66
7.1.5UPVC管專用膠粘接.....................................67
7.1.6衛(wèi)生器具的安裝方法和要求...............................68
7.1.7消防系統(tǒng)的安裝方法和要求...............................69
7.1.8管道支架的安裝方法和要求...............................70
7.1.9管道試驗(yàn)與管道沖洗.....................................70
7.1.10管道防腐與保溫.......................................72
7.2電氣工程施工方案.........................................72
7.2.1電氣施工流程...........................................72
7.2.2土建配合階段...........................................72
7.2.3相接階段...............................................73
7.2.4系統(tǒng)調(diào)試...............................................85
8.建筑節(jié)能及建筑保溫專項(xiàng)施工方案和措施..........................88
8.1.1外墻保溫專項(xiàng)施工方案和質(zhì)量保證措施...................88
一、基層墻體處理.............................................88
二、材料的準(zhǔn)備...............................................88
三、聚苯板的粘貼............................................88
四、保溫板粘貼過程控制要點(diǎn)..................................88
五、質(zhì)量檢驗(yàn):...............................................89
8.1.2屋面保溫專項(xiàng)施工方案和質(zhì)量保證措施....................91
9.重點(diǎn)、難點(diǎn)施工措施...........................................92
9.1.1測(cè)量放線采取的措施.....................................92
9.1.2土方開挖保證樁基質(zhì)量的施工措施.......................92
9.1.3鋼筋保護(hù)層控制不嚴(yán)的防治措施.........................93
9.1.4為確保砼成型質(zhì)量,模板采取的施工措施.................93
10.確保工程質(zhì)量的技術(shù)組織措施.................................94
10.1質(zhì)量目標(biāo)...............................................94
10.1.1質(zhì)量管理目標(biāo).........................................94
10.1.2分部分項(xiàng)工程質(zhì)量管理目標(biāo).............................94
10.1.3工程觀感質(zhì)量管理目標(biāo).................................94
10.2質(zhì)量保證管理措施.......................................94
10.2.1質(zhì)量管理保證體系網(wǎng)絡(luò).................................94
10.2.2質(zhì)量管理制度.........................................95
10.2.3編制質(zhì)量計(jì)劃、創(chuàng)優(yōu)措施...............................96
10.2.4施工過程質(zhì)量控制點(diǎn)...................................96
10.3工程質(zhì)量技術(shù)措施.......................................98
10.3.1施工組織設(shè)計(jì)審批制度.................................98
10.3.2分部、分項(xiàng)工程技術(shù)交底、復(fù)核、隱蔽工程驗(yàn)收制度.......98
10.3.3施工機(jī)械設(shè)備、監(jiān)視和測(cè)量設(shè)備的控制...................98
10.3.4原材料質(zhì)量保證措施...................................98
10.4主要分部分項(xiàng)工程質(zhì)量保證技術(shù)措施.......................99
10.4.1分部分項(xiàng)工程過程質(zhì)量控制措施.........................99
10.4.2基礎(chǔ)工程.............................................99
10.4.3主體工程.............................................100
10.4.4裝修工程.............................................102
10.4.5屋面防水施工.........................................103
10.5工程質(zhì)量通病的防治措施.................................103
10.5.1目的.................................................103
10.5.2適用范圍.............................................103
10.5.3具體措施.............................................103
10.6采用質(zhì)量預(yù)控制的科學(xué)方法...............................106
10.7開展QC小組活動(dòng)........................................107
10.7.1小組概況及活動(dòng)形式...................................107
10.7.2課題確定.............................................107
10.8計(jì)量管理...............................................108
11.確保安全生產(chǎn)的技術(shù)組織措施.................................109
11.1安全管理目標(biāo)...........................................109
11.2組織措施...............................................109
11.2.1施工現(xiàn)場(chǎng)安全組織.....................................109
11.3安全保證計(jì)劃的編制.....................................112
11.4施工過程控制...........................................112
11.4.1人員培訓(xùn).............................................112
11.4.2安全檢查.............................................112
11.4.3隱患整改.............................................113
11.4.4安全事故的處理.......................................113
11.4.5現(xiàn)場(chǎng)急救.............................................113
11.4.6施工現(xiàn)場(chǎng)的安全要求...................................114
11.5施工過程安全控制措施...................................115
11.5.1搭設(shè)腳手架安全要求...................................115
11.5.2洞口、臨邊的防護(hù).....................................115
11.5.3內(nèi)外交通管理保障措施.................................115
11.6消防管理...............................................116
11.6.1組織措施.............................................116
11.6.2防火要求.............................................116
11.6.3消防設(shè)施的布置.......................................116
12.確保文明施工的技術(shù)組織措施...............................117
12.1目標(biāo)...................................................117
12.2現(xiàn)場(chǎng)文明施工管理.......................................117
12.2.1文明施工組織網(wǎng)絡(luò).....................................117
12.2.2文明施工崗位職責(zé).....................................117
12.2.3內(nèi)部溝通.............................................119
12.2.4場(chǎng)容場(chǎng)貌.............................................120
12.2.5施工現(xiàn)場(chǎng)標(biāo)化管理.....................................120
12.3環(huán)保施工措施...........................................122
12.3.1工作目標(biāo).............................................122
12.3.2組織管理.............................................123
12.3.3工作制度.............................................123
12.3.4管理規(guī)定.............................................123
12.4組織保證措施...........................................124
12.5技術(shù)保證措施...........................................125
13.確保工期的技術(shù)組織措施.....................................126
13.1施工工期...............................................126
13.2施工進(jìn)度計(jì)劃...........................................126
13.3進(jìn)度保證措施...........................................126
13.3.1組織保證措施.........................................126
13.3.2勞動(dòng)力保證措施.......................................127
13.3.3機(jī)械設(shè)備保證措施.....................................127
13.3.4技術(shù)保證措施.........................................127
13.3.5周轉(zhuǎn)工具保證措施.....................................127
13.3.6基礎(chǔ)工程階段保證措施.................................127
13.3.7主體工程階段保證措施.................................127
13.3.8裝飾工程階段保證措施.................................128
13.3.9水電安裝階段保證措施.................................128
13.3.10進(jìn)度計(jì)劃動(dòng)態(tài)控制措施...............................128
13.4進(jìn)度獎(jiǎng)罰措施...........................................129
13.5法定假期間保證措施.....................................129
13.6農(nóng)忙期間保證措施.......................................130
14.施工總平面布置.............................................131
14.1布置原則...............................................131
14.2生活區(qū)臨時(shí)設(shè)施布置.....................................131
14.3臨時(shí)生產(chǎn)設(shè)施布置.......................................131
14.3.1施工臨時(shí)用地圍護(hù)設(shè)置.................................131
14.3.2施工道路.............................................132
14.3.3攪拌臺(tái)設(shè)置...........................................132
14.3.4鋼筋車間.............................................132
14.3.5現(xiàn)場(chǎng)辦公室...........................................133
14.3.6其它生產(chǎn)設(shè)施.........................................133
14.3.7施工區(qū)周邊環(huán)境的保護(hù)措施.............................133
14.3.8施工現(xiàn)場(chǎng)臨時(shí)用電方案.................................133
14.3.9施工現(xiàn)場(chǎng)臨時(shí)用水方案.................................134
15.新工藝、新技術(shù)、新材料的應(yīng)用................................135
15.1新型模板...............................................135
15.2泵送砼.................................................135
15.3鋼筋直螺紋連接技術(shù).....................................135
15.4激光測(cè)距儀、全站儀.....................................135
15.5微機(jī)應(yīng)用...............................................135
16.季節(jié)性及夜間施工保證措施...................................136
16.1雨期及臺(tái)風(fēng)期施工措施...................................136
16.1.1管理措施.............................................136
16.1.2安全措施.............................................136
16.1.3技術(shù)措施.............................................136
16.2夜間施工措施...........................................137
16.3冬期施工技術(shù)措施.......................................137
16.3.1土方工程.............................................138
16.3.2鋼筋工程.............................................138
16.3.3砼工程...............................................138
16.4暑季施工措施...........................................138
17.降低工程成本技術(shù)措施.......................................139
17.1主要技術(shù)節(jié)約措施.......................................139
17.2進(jìn)行技術(shù)經(jīng)濟(jì)分析,優(yōu)選施工方案.........................139
17.3提高勞動(dòng)生產(chǎn)率.........................................139
17.4節(jié)約材料消耗...........................................139
17.5提高機(jī)械設(shè)備利用率.....................................139
編制依據(jù)
1.XX市XXXX有限公司二期建設(shè)工程招標(biāo)文件;
2.XX市XXXX有限公司二期建設(shè)工程設(shè)計(jì)圖紙;
3.XX市XXXX有限公司二期建設(shè)工程招標(biāo)答疑;
4.現(xiàn)行安全、文明施工的有關(guān)規(guī)定;
5.現(xiàn)場(chǎng)踏勘目測(cè)結(jié)果;
6.國(guó)家現(xiàn)行施工技術(shù)規(guī)范、規(guī)程、標(biāo)準(zhǔn)。
1.工程概況及特點(diǎn)
XX市XXXX有限公司二期建設(shè)工程,位于XX市XX區(qū)工業(yè)園區(qū)緯二路18
號(hào)。
本標(biāo)段施工內(nèi)容包括4#、5#廠房以及綜合樓土建、水電安裝工程。
建設(shè)單位:XX市XXXX有限公司
設(shè)計(jì)單位:XX市現(xiàn)代建筑設(shè)計(jì)研究院有限公司
1.1建筑概況
本標(biāo)段工程建筑面積約10854.38m2,其中4#、5#廠房都為3595m2,綜合
樓為3664.38m2。
建筑樓層:4#、5#廠房均為兩層,綜合樓三層局部四層。
本工程設(shè)計(jì)基準(zhǔn)年限為50年,建筑主體結(jié)構(gòu)安全等級(jí)為二級(jí)?!?.000
為室內(nèi)地坪標(biāo)高,相當(dāng)于絕對(duì)標(biāo)高詳見總圖,室內(nèi)外高差廠房為150mm,綜合
樓為300mm。
建筑類別及耐火等級(jí):耐火等級(jí)為二級(jí)
抗震設(shè)防烈度:六度。
結(jié)構(gòu)類型:框架結(jié)構(gòu)體系。
地面做法:(廠房)地一:水泥砂漿地面;
地二:地磚地面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿地面
樓面做法:(廠房)樓一:水泥砂漿樓面;
樓二:地磚樓面;(用于衛(wèi)生間)
(綜合樓)水泥砂漿樓面;
內(nèi)墻做法:(廠房)內(nèi)墻一:乳膠漆墻面
內(nèi)墻二:瓷磚墻面(用于衛(wèi)生間)
(綜合樓)乳膠漆墻面
外墻做法:(廠房)水泥砂漿抹灰,乳膠漆飾面;
(綜合樓)水泥砂漿抹灰,巖棉板保溫層,抗裂砂漿壓入一層
耐堿玻纖網(wǎng)格布,乳膠漆飾面;
頂棚做法:素水泥漿一道,混合砂漿抹灰,乳膠漆罩面;
門窗:塑鋼窗、防火鋼門安裝。
屋面做法:廠房為20厚1:3水泥砂漿找平層、40厚聚苯乙烯擠塑板、20厚1:3
水泥砂漿找平層、SBS改性瀝青防水卷材。
綜合樓為最薄處30厚粉煤灰陶粒砼找坡層、40厚擠塑聚苯板、20
厚水泥砂漿找平層、刷一層基層處理劑、4厚高聚物改性瀝青防水卷材、50厚
C30細(xì)石砼,內(nèi)配φ4@150雙向鋼筋。
1.2結(jié)構(gòu)概況
1.2.1基礎(chǔ)
基礎(chǔ)砼墊層C10,獨(dú)立基礎(chǔ)、條形基礎(chǔ)廠房均采用C25泵送商品砼,綜合
樓均采用C30泵送商品砼。
1.2.2主體
框架柱、梁、板:結(jié)構(gòu)強(qiáng)度等級(jí)為廠房C25、綜合樓C30泵送商品砼;
構(gòu)造柱:為C20非泵送商品砼;圈梁、過梁:為C20非泵送商品砼
砌體結(jié)構(gòu):-0.060以下采用MU20混凝土磚M10水泥砂漿砌筑;-0.060
以上外墻采用承重砼砌塊,M7.5混合砂漿砌筑,內(nèi)墻采用砼空心砌塊,M5混
合砂漿砌筑,女兒墻采用砼空心砌塊,M7.5混合砂漿砌筑。
1.3安裝工程概況
1.3.1概述
本工程主要工作內(nèi)容為:給排水管道、電氣等工程的安裝。
1.3.2工程概況
A.給排水工程
包括給水系統(tǒng)、消火栓消防系統(tǒng)、排水系統(tǒng)、雨水系統(tǒng)等安裝;
給水系統(tǒng):本工程由市政管網(wǎng)供水
污水系統(tǒng):采用雨污分流制,糞便污水經(jīng)化糞池處理后與其它生活廢水
排入室外污水管網(wǎng);
雨水系統(tǒng):主樓采用重力流排水系統(tǒng)排至室外,與場(chǎng)地及道路雨水匯合
排入市政雨水管網(wǎng)。
室內(nèi)給水管采用PP-R管,熱熔連接;
消火栓消防管采用內(nèi)外熱浸熱鍍鋅鋼管,管徑大于等于DN100采用卡箍
連接,管徑小于DN100采用絲扣連接。
污水管采用UPVC排水管,粘接。
雨水管、冷凝水管采用UPVC塑料排水管,膠結(jié)。
B.電氣工程
包括配電設(shè)計(jì)、照明設(shè)計(jì)、防雷接地系統(tǒng);
電力配電系統(tǒng):
低壓配電電壓為380/300V三相四線制,采用放射式與樹干式相結(jié)合供電
方式;
照明系統(tǒng):
本工程電纜電線均采用阻燃電線電纜;
接地型式采用TN-C-S系統(tǒng),利用建筑物基礎(chǔ)主鋼筋作共同接地裝置。
防雷與接地:
防直擊雷:采用在屋頂明設(shè)避雷帶和其它地方暗設(shè)避雷帶組成混合接閃
器,引下線做法商品砼柱內(nèi)電焊成一體的四根不小于φ10的主筋作防雷引下
線。
所有接地均利用基礎(chǔ)及基礎(chǔ)梁中的鋼筋焊接溝通后連成一整體作為統(tǒng)一
接地體,形成共用接地系統(tǒng)。
1.4工程特點(diǎn)
1.4.1施工場(chǎng)地文明施工難度大
根據(jù)現(xiàn)場(chǎng)實(shí)地觀測(cè),本工程施工現(xiàn)場(chǎng)內(nèi),施工中要特別注重文明施工,
以最小的影響來確保場(chǎng)內(nèi)的正?;顒?dòng)。另外,現(xiàn)場(chǎng)臨建設(shè)施、材料堆放場(chǎng)地、
大型機(jī)械設(shè)備布置必須進(jìn)行合理的規(guī)劃和布局,施工順序也必須進(jìn)行全局的
策劃和組織,來保證場(chǎng)地受施工干擾最小。
1.4.2工程特殊部位較多
本工程屋面及衛(wèi)生間的防水處理等,都必須制定相應(yīng)的技術(shù)措施,確保
工程質(zhì)量符合設(shè)計(jì)與規(guī)范要求。
2.施工組織設(shè)計(jì)總體設(shè)想
2.1工程建設(shè)目標(biāo)
2.1.1質(zhì)量管理目標(biāo)
符合國(guó)家質(zhì)量驗(yàn)收標(biāo)準(zhǔn),一次性驗(yàn)收合格
2.1.1.1各分部工程質(zhì)量管理目標(biāo)
分部工程、分項(xiàng)工程一次性驗(yàn)收合格
2.1.1.2工程觀感質(zhì)量管理目標(biāo)
觀感評(píng)定:好
2.1.2工期管理目標(biāo)
工期:370個(gè)日歷天
2.1.2.1工程竣工管理目標(biāo)
工程竣工一次驗(yàn)收合格率100%
2.1.3安全生產(chǎn)管理目標(biāo)
2.1.3.1安全生產(chǎn)目標(biāo)
杜絕死亡、重傷事故
輕傷事故控制在5%以內(nèi)
2.1.3.2安全生產(chǎn)過程目標(biāo)
事故隱患控制率在95%以上
整改率控制在100%
2.1.4文明施工管理目標(biāo)
2.1.4.1文明工地目標(biāo)
確?!笆屑?jí)文明工地”。
2.2質(zhì)量控制重點(diǎn)
砼結(jié)構(gòu)施工
衛(wèi)生間防滲
屋面防水細(xì)部節(jié)點(diǎn)施工
平面及垂直度度控制
安裝與土建交叉施工的質(zhì)量控制
3.施工部署
3.1組織機(jī)構(gòu)
本工程采用公司、項(xiàng)目管理部二級(jí)管理模式。成立“XX市XXXX有限公司
二期建設(shè)工程項(xiàng)目經(jīng)理部”,代表公司進(jìn)行工程施工組織和管理,全面負(fù)責(zé)
整個(gè)工程的進(jìn)度、安全、質(zhì)量、成本控制四大指標(biāo),抓好優(yōu)質(zhì)服務(wù)及現(xiàn)場(chǎng)文
明施工等。
3.1.1項(xiàng)目部的組織機(jī)構(gòu)
在公司內(nèi)抽調(diào)一批具有較高專業(yè)知識(shí)和業(yè)務(wù)能力、經(jīng)驗(yàn)豐富的施工骨干
力量組成項(xiàng)目管理部的項(xiàng)目班子和管理層。項(xiàng)目部設(shè)項(xiàng)目經(jīng)理一名、項(xiàng)目總
工程師一名、項(xiàng)目副經(jīng)理一名,下設(shè)質(zhì)保部、技術(shù)部、工程部、物項(xiàng)部、經(jīng)
營(yíng)部、人勞部、財(cái)務(wù)部、安保部、資料室。
項(xiàng)目組織機(jī)構(gòu)網(wǎng)絡(luò)圖
項(xiàng)目經(jīng)理
項(xiàng)目總工程師項(xiàng)目副經(jīng)理
3.2強(qiáng)化項(xiàng)目管理
3.2.1編制和實(shí)施項(xiàng)目管理實(shí)施計(jì)劃
工程開工前,項(xiàng)目經(jīng)理組織項(xiàng)目部相關(guān)管理人員編制項(xiàng)目管理實(shí)施規(guī)劃。
編制前,必須對(duì)施工合同和施工條件進(jìn)行分析,對(duì)項(xiàng)目管理目標(biāo)責(zé)任書
進(jìn)行分析。
在實(shí)施過程中,每隔一個(gè)月進(jìn)行一次檢查,必要時(shí)增加檢查頻率,發(fā)現(xiàn)
偏差,及時(shí)調(diào)整。確保本工程順利進(jìn)展。
3.2.2貫徹落實(shí)公司的規(guī)章制度
在項(xiàng)目施工過程中,必須貫徹執(zhí)行公司的各項(xiàng)規(guī)章制度,主要有:
《項(xiàng)目施工管理細(xì)則》
《項(xiàng)目施工質(zhì)量責(zé)任制》
《項(xiàng)目施工安全生產(chǎn)責(zé)任制》
《項(xiàng)目施工用戶滿意責(zé)任制》
《項(xiàng)目施工資金使用管理制度》
3.2.3逐層分解指標(biāo),明確責(zé)、權(quán)、利
項(xiàng)目開工前,公司與項(xiàng)目經(jīng)理簽訂本項(xiàng)目承包合同,明確項(xiàng)目經(jīng)理及項(xiàng)
目部的責(zé)、權(quán)、利,項(xiàng)目部與項(xiàng)目管理人員及生產(chǎn)班組簽訂施工協(xié)議,分解
項(xiàng)目各項(xiàng)指標(biāo),明確參與施工人員的職責(zé)、權(quán)利及獎(jiǎng)勵(lì)和處罰,把績(jī)效與經(jīng)
濟(jì)收入掛鉤,進(jìn)一步強(qiáng)化職工的責(zé)任心、事業(yè)心,從而保證項(xiàng)目正常實(shí)施。
3.2.4嚴(yán)格執(zhí)行施工組織設(shè)計(jì)
施工組織設(shè)計(jì)經(jīng)公司總工和業(yè)主、監(jiān)理批準(zhǔn)后,必須嚴(yán)格執(zhí)行,任何人
不得隨意修改施工組織設(shè)計(jì)或不按施工組織設(shè)計(jì)施工,如需要修改施工組織
設(shè)計(jì),必須至少提前一周報(bào)請(qǐng)?jiān)瓕徟块T審批,經(jīng)批準(zhǔn)后方可按修改后的施
工組織設(shè)計(jì)執(zhí)行。
3.2.5執(zhí)行質(zhì)量進(jìn)度公開制
工程開工前,將工程質(zhì)量目標(biāo)、進(jìn)度計(jì)劃張貼上墻,施工過程中,根據(jù)
每一分部完成情況,填寫對(duì)照表,找出原因,以便及時(shí)整改。
3.2.6業(yè)主滿意
通過強(qiáng)化項(xiàng)目管理,來達(dá)到工期短、質(zhì)量好、成本低及安全的目標(biāo),從
而最終生產(chǎn)出令業(yè)主滿意的產(chǎn)品。
3.3項(xiàng)目管理部職責(zé)
對(duì)公司總部負(fù)責(zé),向公司總部報(bào)告工程實(shí)施過程中的一切重大事宜;
負(fù)責(zé)工程項(xiàng)目的施工管理和各項(xiàng)工作的具體實(shí)施;
編制項(xiàng)目各項(xiàng)計(jì)劃,包括資金計(jì)劃和執(zhí)行機(jī)構(gòu)開支預(yù)算;
編制項(xiàng)目質(zhì)量保證計(jì)劃和技術(shù)方案,并報(bào)公司審批后負(fù)責(zé)落實(shí)和實(shí)施;
編制項(xiàng)目安全文明施工組織管理方案,報(bào)公司審批后落實(shí);
做好現(xiàn)場(chǎng)生產(chǎn)組織管理工作,保證質(zhì)量、工期和安全目標(biāo)的實(shí)現(xiàn);
具體負(fù)責(zé)項(xiàng)目的各分部交驗(yàn)工作,以及竣工驗(yàn)收負(fù)責(zé)工程創(chuàng)優(yōu)的各項(xiàng)工
作;
3.4項(xiàng)目管理部主要部門、崗位職責(zé)
3.4.1項(xiàng)目經(jīng)理
3.4.1.1項(xiàng)目經(jīng)理的崗位職責(zé)
是項(xiàng)目管理部的法定代表人,與公司一道討論并決定承包項(xiàng)目部的一切
重大事宜,審核并批準(zhǔn)項(xiàng)目執(zhí)行機(jī)構(gòu)的各類計(jì)劃、方案、報(bào)告和制度;
與公司經(jīng)理一道,牽頭負(fù)責(zé)項(xiàng)目管理部與業(yè)主和政府機(jī)構(gòu)的聯(lián)絡(luò)工作;
全面主持項(xiàng)目執(zhí)行機(jī)構(gòu)的日常工作,是項(xiàng)目實(shí)施過程的全職組織者和指
揮者;
決定項(xiàng)目的各種獎(jiǎng)勵(lì)分配方案并報(bào)公司備案;
擬訂項(xiàng)目執(zhí)行機(jī)構(gòu)組織和人員配制,提請(qǐng)公司聘任或解聘項(xiàng)目主要崗位
人員;
處理項(xiàng)目實(shí)施中的重大緊急事件,并及時(shí)向公司報(bào)告;
負(fù)責(zé)與業(yè)主、監(jiān)理、設(shè)計(jì)等的協(xié)調(diào)和溝通的組織領(lǐng)導(dǎo)工作;組織和領(lǐng)導(dǎo)
創(chuàng)優(yōu)工作。
3.4.1.2項(xiàng)目經(jīng)理的主要業(yè)績(jī)
項(xiàng)目經(jīng)理近幾年的主要業(yè)績(jī):見商務(wù)標(biāo)
3.4.2項(xiàng)目副經(jīng)理
3.4.2.1項(xiàng)目副經(jīng)理的崗位職責(zé)
落實(shí)項(xiàng)目質(zhì)量保證計(jì)劃、各類施工技術(shù)方案、安全文明、施工組織管理
方案;
配合項(xiàng)目經(jīng)理,組織編制項(xiàng)目執(zhí)行機(jī)構(gòu)的勞資分配制度和其它管理制度;
配合項(xiàng)目經(jīng)理,組織編制項(xiàng)目實(shí)施的各類進(jìn)度計(jì)劃、預(yù)算、報(bào)表;
協(xié)助項(xiàng)目經(jīng)理工作,具體負(fù)責(zé)項(xiàng)目基礎(chǔ)、土建、鋼結(jié)構(gòu)、裝修、機(jī)電等
施工生產(chǎn)的技術(shù)、質(zhì)量、安全、進(jìn)度的組織、控制和管理工作,以及協(xié)助項(xiàng)
目經(jīng)理分管計(jì)劃協(xié)調(diào)、安全文明、質(zhì)量保證、行政、保安等部門的工作;
具體負(fù)責(zé)項(xiàng)目質(zhì)量、工期,安全目標(biāo)的管理監(jiān)督工作;
配合項(xiàng)目經(jīng)理,管理經(jīng)營(yíng)部、財(cái)務(wù)部和物資采購部的工作
負(fù)責(zé)工程的竣工交驗(yàn)工作;
在項(xiàng)目經(jīng)理的配合下,負(fù)責(zé)組織協(xié)調(diào)后方生產(chǎn)資源和技術(shù)服務(wù)的支持工
作;
協(xié)助總工程師進(jìn)行新材料、新技術(shù)、新工藝在本工程的推廣應(yīng)用和技術(shù)
總結(jié)工作
3.4.3項(xiàng)目總工程師
3.4.3.1項(xiàng)目總工的崗位職責(zé)
協(xié)助項(xiàng)目經(jīng)理管理和領(lǐng)導(dǎo)技術(shù)部工作;
具體負(fù)責(zé)項(xiàng)目質(zhì)量保證計(jì)劃、各類施工技術(shù)方案和安全文明施工組織管
理方案的編制及其檢查和落實(shí)工作;
負(fù)責(zé)總體和階段進(jìn)度計(jì)劃的編制、分解、協(xié)調(diào)和落實(shí)工作
負(fù)責(zé)項(xiàng)目質(zhì)量目標(biāo)、進(jìn)度、目標(biāo)、安全文明施工目標(biāo)和質(zhì)量獎(jiǎng)目標(biāo)的策
劃、組織、管理和落實(shí)工作;
組織相關(guān)部門和人員代表項(xiàng)目經(jīng)理部參與與業(yè)主、監(jiān)理或設(shè)計(jì)方等就施
工方案、技術(shù)、設(shè)計(jì)、質(zhì)量等方面的問題的會(huì)議、討論或磋商;
主持施工組織設(shè)計(jì)和重大技術(shù)方案和測(cè)量方案的編制與修訂并負(fù)責(zé)把
關(guān);
組織進(jìn)度計(jì)劃的編制并監(jiān)督落實(shí),負(fù)責(zé)土建與水電安裝工作之間在進(jìn)度
安排方面的配合和協(xié)調(diào);
參與項(xiàng)目質(zhì)量策劃并督促技術(shù)方案和施工組織設(shè)計(jì)主要內(nèi)容的落實(shí)工
作;
對(duì)新技術(shù)、新工藝和新材料在本工程的推廣和使用進(jìn)行指導(dǎo);
協(xié)助項(xiàng)目經(jīng)理并組織創(chuàng)優(yōu)工作;
竣工圖、竣工資料、技術(shù)總結(jié)等工作的指導(dǎo)和審核;
負(fù)責(zé)組織對(duì)工人的崗前培訓(xùn)工作,并審查培訓(xùn)效果;
負(fù)責(zé)工程的技術(shù)資料整理工作
3.4.4項(xiàng)目部的管理職責(zé)
主要部門的崗位職責(zé)
3.4.4.1技術(shù)部
協(xié)助項(xiàng)目總工程師工作,負(fù)責(zé)項(xiàng)目施工的技術(shù)準(zhǔn)備工作;
編制項(xiàng)目質(zhì)量保證計(jì)劃、安全文明、施工方案。及時(shí)向總工返饋信息,
參與施工方案修訂工作。
具體負(fù)責(zé)現(xiàn)場(chǎng)總平面的布置方案及其調(diào)整方案;
協(xié)助安全文明施工、質(zhì)量體系運(yùn)行和爭(zhēng)創(chuàng)質(zhì)量獎(jiǎng)工作;
負(fù)責(zé)編制工程的物資需求計(jì)劃;
負(fù)責(zé)技術(shù)資料收集整理工作,項(xiàng)目階段交驗(yàn)和竣工交驗(yàn);
負(fù)責(zé)新技術(shù)、新材料、新工藝在本項(xiàng)目的推廣應(yīng)用和科技成果的總結(jié)工
作;
3.4.4.2質(zhì)保部
協(xié)助項(xiàng)目副經(jīng)理工作,負(fù)責(zé)項(xiàng)目的全面質(zhì)量管理;
參與編制項(xiàng)目質(zhì)量保證計(jì)劃,負(fù)責(zé)編制安全文明施工組織管理方案和管
理制度并監(jiān)督實(shí)施;
負(fù)責(zé)安全生產(chǎn)和文明施工的日常檢查、監(jiān)督、消除隱患等管理;
負(fù)責(zé)管理落實(shí)質(zhì)量記錄的整理存檔工作,協(xié)助項(xiàng)目總工程師進(jìn)行竣工資
料的編制工作;
負(fù)責(zé)項(xiàng)目質(zhì)量保證計(jì)劃并負(fù)責(zé)監(jiān)督實(shí)施、過程控制、日常管理;
負(fù)責(zé)項(xiàng)目全員質(zhì)量保證體系和質(zhì)量方針的培訓(xùn)教育工作;
負(fù)責(zé)分部分項(xiàng)工程工序質(zhì)量檢查和質(zhì)量評(píng)定工作;
負(fù)責(zé)質(zhì)量目標(biāo)的分解落實(shí),編制質(zhì)量獎(jiǎng)懲責(zé)任制度并負(fù)責(zé)日常管理;
負(fù)責(zé)工程創(chuàng)優(yōu)和評(píng)獎(jiǎng)的策劃、組織、資料準(zhǔn)備和日常管理工作;
3.5項(xiàng)目經(jīng)理長(zhǎng)駐現(xiàn)場(chǎng)措施
3.5.1建立請(qǐng)假制度
項(xiàng)目經(jīng)理若離開現(xiàn)場(chǎng),在一天以內(nèi),應(yīng)以書面形式請(qǐng)假,經(jīng)現(xiàn)場(chǎng)總監(jiān)及
甲方代表批準(zhǔn),離開前,必須將其工作交給現(xiàn)場(chǎng)副經(jīng)理代管,方可離開。
3.5.2建立約束機(jī)制
資格預(yù)審文件和投標(biāo)文件中明確的項(xiàng)目經(jīng)理和技術(shù)員或施工員、質(zhì)量員、
安全員等不得擅自變更,如未經(jīng)發(fā)包人同意,開工時(shí)或施工過程中變更,發(fā)
包人有權(quán)解除合同,并追究由此帶來的發(fā)包人一切損失。項(xiàng)目經(jīng)理本人每天
至少8小時(shí),每周不少于3天在本工程施工現(xiàn)場(chǎng)工作。且必須參加每周召開
會(huì)例會(huì)(有事須請(qǐng)假)。
3.5.3實(shí)行項(xiàng)目經(jīng)理評(píng)分制
公司已建立項(xiàng)目經(jīng)理評(píng)分制,總共10分,根據(jù)評(píng)分進(jìn)行年度考核,作為
評(píng)選公司優(yōu)秀項(xiàng)目經(jīng)理及年終獎(jiǎng)的根本依據(jù),其中業(yè)主意見占5分,若業(yè)主
反映項(xiàng)目經(jīng)理無故或不請(qǐng)假就離開現(xiàn)場(chǎng),每次扣0.5分。
3.6勞務(wù)工資管理和發(fā)放措施
我單位將嚴(yán)格遵守《中華人民共和國(guó)勞動(dòng)法》,認(rèn)真貫徹《關(guān)于切實(shí)解決
建筑業(yè)企業(yè)拖欠農(nóng)民工工資問題的通知》文件精神,以及江蘇省和XX市《市
政府關(guān)于進(jìn)一步做好解決建設(shè)工程中拖欠工程款和拖欠民工工資工作的若干
意見》等一系列文件精神,切實(shí)做好此項(xiàng)工作。
無論工程款支付怎樣,我公司將按照下列措施執(zhí)行:
A.如果在工程款按合同支付情況下,將在每月30日全額支付勞務(wù)人員當(dāng)
月工資;
B.如果工程款未按合同支付時(shí),將在每月30日支付勞務(wù)人員生活費(fèi)850
元;
C.在節(jié)假日和學(xué)生開學(xué)前,將支付勞務(wù)人員所完工程量的100%。
3.7施工組織
3.7.1施工區(qū)、段劃分
3.7.1.1施工區(qū)、段的劃分原則
整個(gè)標(biāo)段由二棟廠房和一棟綜合樓組成,施工時(shí),以各棟主體結(jié)構(gòu)施工
為主導(dǎo)工序。精心組織施工區(qū)域內(nèi),空間立體交叉有節(jié)奏流水作業(yè),做到工
序銜接緊密;安裝工程穿插于土建施工過程中,與土建工程施工交叉進(jìn)行。
3.7.1.2施工區(qū)、段劃分
按照設(shè)計(jì)圖中建筑物的布局,結(jié)合結(jié)構(gòu)的設(shè)計(jì)劃分施工區(qū)段,為保證工
期將整個(gè)標(biāo)段劃分成二大施工區(qū)域(4#及5#廠房、綜合樓),組織二班人馬,
進(jìn)行平行作業(yè)。以便各施工區(qū)內(nèi)部產(chǎn)生流水,縮短工期。
3.7.2施工順序
施工準(zhǔn)備
定位放線
土方開挖
基礎(chǔ)施工
主體結(jié)構(gòu)
砌體結(jié)構(gòu)屋面防水預(yù)留預(yù)埋
門窗安裝樓地面內(nèi)裝飾
外裝飾安裝
系統(tǒng)測(cè)試調(diào)試
工程竣工
3.7.2.1施工流程
第一施工區(qū)(4#及5#廠房)→第二施工區(qū)(綜合樓)
3.7.2.2施工段的施工順序
按分部分項(xiàng)工程組織流水施工,其順序?yàn)椋憾ㄎ环啪€→土方開挖→基礎(chǔ)
模板、鋼筋、商品砼→主體結(jié)構(gòu)模板、鋼筋、商品砼→砌體結(jié)構(gòu)→屋面防水
→門窗→內(nèi)裝飾→外裝飾→樓地面→安裝工程→室外→竣工
施工順序的穿插
主體結(jié)構(gòu)一層模板拆除后,即可穿插內(nèi)部結(jié)構(gòu)及安裝工程的施工,以減
少空間和時(shí)間上的損失,確保項(xiàng)目建設(shè)工期。每一個(gè)施工段均本著“先地下
后地上”、“先土建后安裝”“先主體后裝修”的原則組織施工。
每一階段都必須完成規(guī)定的工作內(nèi)容,為下一階段創(chuàng)造條件。
安裝工程的插入應(yīng)遵循的原則為:先土建后安裝,先主管后支管,在土建施
工主體時(shí),預(yù)留、預(yù)埋好預(yù)埋洞、預(yù)埋件。下部可穿插施工一些給水的施工,
土建室內(nèi)裝修的同時(shí),安裝全面進(jìn)入安裝階段。
3.8資源配置
3.8.1勞動(dòng)力安排計(jì)劃
根據(jù)本工程施工需要,由人勞部對(duì)作業(yè)人員從技能、責(zé)任心、工作經(jīng)驗(yàn)、
身體素質(zhì)、持證情況等方面選擇合格勞動(dòng)力,及時(shí)組織進(jìn)行施工,人勞部必須
在工程開工前落實(shí)作業(yè)人員。特殊作業(yè)人員必須持有效證件方能上崗,持證率
100%,必要時(shí)進(jìn)行考試,做到好中選優(yōu)。
3.8.1.1勞動(dòng)力投入計(jì)劃
根據(jù)工程的結(jié)構(gòu)形式、建筑構(gòu)造和工作量及工期要求,編制勞動(dòng)力投入計(jì)
劃。
3.8.1.2勞動(dòng)力進(jìn)場(chǎng)計(jì)劃
根據(jù)施工進(jìn)度網(wǎng)絡(luò)計(jì)劃要求編制勞動(dòng)力投入計(jì)劃,按勞動(dòng)力投入計(jì)劃及時(shí)
組織作業(yè)人員進(jìn)入施工現(xiàn)場(chǎng)。
主要?jiǎng)趧?dòng)力投入計(jì)劃表
按工程施工階段投入勞動(dòng)力情況
工種基礎(chǔ)主體裝修、安裝
收尾階段
施工階段施工階段施工階段
木工3050105
砼工3045205
瓦工15301510
抹灰工254010
鋼筋工303052
架子工420105
動(dòng)力司機(jī)4664
電工620206
油漆工004015
焊工4442
起重工3330
水工210106
調(diào)試工0004
普工15303015
合/p>
3.8.1.3人員培訓(xùn)教育
對(duì)參加施工的作業(yè)人員及時(shí)進(jìn)行進(jìn)場(chǎng)三級(jí)教育。
培訓(xùn)后進(jìn)行書面測(cè)試,合格后方可上崗作業(yè)。
3.8.2工程投入的主要施工機(jī)械設(shè)備安排計(jì)劃
根據(jù)本工程施工的結(jié)構(gòu)類型特點(diǎn),配置合適的大、中、小型施工機(jī)械設(shè)備,
以滿足工程進(jìn)度的需要。
3.8.2.1垂直運(yùn)輸設(shè)備
現(xiàn)場(chǎng)設(shè)置2臺(tái)QTZ40固定式塔吊負(fù)責(zé)工程施工的垂直運(yùn)輸。同時(shí)負(fù)責(zé)鋼筋
原材和模板半成品的吊運(yùn)。
廠房主體砼施工到封頂、綜合樓主體砼施工到二層后在4#廠房和綜合樓附
近各安裝井架各一臺(tái),以滿足填充材料等小型材料上下。
為滿足施工及進(jìn)度要求,砼澆筑采用砼固定泵泵送。
3.8.2.2水平運(yùn)輸設(shè)備
◆配備FC-1型機(jī)動(dòng)翻斗車1臺(tái),負(fù)責(zé)砂漿,砼及零星建材的運(yùn)輸。
◆配備12t自卸車2輛,負(fù)責(zé)砂、石等建材的運(yùn)輸。
◆樓層內(nèi)水平運(yùn)輸采用手推架子車。
3.8.2.3土方機(jī)械設(shè)備
配備履帶式反鏟挖土機(jī)0.5m3二臺(tái)進(jìn)行土方開挖;在清槽施工時(shí),配備
履帶式反鏟挖土機(jī)0.5m3一臺(tái),用于開挖地梁基坑。
3.8.2.4砂漿機(jī)械設(shè)備
現(xiàn)場(chǎng)配備砼攪拌機(jī)350L2臺(tái),負(fù)責(zé)零星砼、砂漿的攪拌,主體砼采用商品
砼,砼輸送泵及運(yùn)輸設(shè)備由廠家按照我方要求配備。
3.8.2.5鋼筋機(jī)械設(shè)備
配備鋼筋切斷機(jī)2臺(tái),鋼筋彎曲機(jī)2臺(tái),卷?xiàng)顧C(jī)2臺(tái),鋼筋調(diào)直機(jī)2臺(tái),
鋼筋套絲機(jī)2臺(tái),電渣壓力焊機(jī)2臺(tái),鋼筋對(duì)焊機(jī)2臺(tái)。
3.8.2.6其它機(jī)械設(shè)備
木工機(jī)械,測(cè)量設(shè)備,裝載機(jī)等詳見主要施工機(jī)械設(shè)備計(jì)劃表。
計(jì)劃投入的主要施工機(jī)械設(shè)備表
額定生產(chǎn)
序
機(jī)械或設(shè)備型號(hào)國(guó)別制造備
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請(qǐng)下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請(qǐng)聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會(huì)有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲(chǔ)空間,僅對(duì)用戶上傳內(nèi)容的表現(xiàn)方式做保護(hù)處理,對(duì)用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對(duì)任何下載內(nèi)容負(fù)責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請(qǐng)與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時(shí)也不承擔(dān)用戶因使用這些下載資源對(duì)自己和他人造成任何形式的傷害或損失。
最新文檔
- 西南地區(qū)2025年度啤酒企業(yè)環(huán)境保護(hù)與合規(guī)合同3篇
- 2025年度網(wǎng)絡(luò)安全服務(wù)臨時(shí)工聘用合同大全4篇
- 2025年物業(yè)管理公司住宅小區(qū)物業(yè)維修基金使用效果評(píng)估及監(jiān)管服務(wù)采購合同3篇
- 二零二五年度高級(jí)酒店客房承包經(jīng)營(yíng)合同范本3篇
- 二零二五年融資協(xié)議違約金支付規(guī)定2篇
- 二零二五年智能廚房設(shè)備供應(yīng)與工地食堂承包合同3篇
- 2025年消防系統(tǒng)安全評(píng)估與整改服務(wù)合同3篇
- 二零二五年度工業(yè)地產(chǎn)長(zhǎng)期使用協(xié)議2篇
- 設(shè)計(jì)公司股權(quán)轉(zhuǎn)讓合同2025版:股權(quán)轉(zhuǎn)讓后的公司管理權(quán)變更2篇
- 二零二五版租賃房屋租賃期限變更合同范本2篇
- 公路工程施工現(xiàn)場(chǎng)安全檢查手冊(cè)
- 公司組織架構(gòu)圖(可編輯模版)
- 1汽輪機(jī)跳閘事故演練
- 陜西省銅川市各縣區(qū)鄉(xiāng)鎮(zhèn)行政村村莊村名居民村民委員會(huì)明細(xì)
- 禮品(禮金)上交登記臺(tái)賬
- 北師大版七年級(jí)數(shù)學(xué)上冊(cè)教案(全冊(cè)完整版)教學(xué)設(shè)計(jì)含教學(xué)反思
- 2023高中物理步步高大一輪 第五章 第1講 萬有引力定律及應(yīng)用
- 青少年軟件編程(Scratch)練習(xí)題及答案
- 浙江省公務(wù)員考試面試真題答案及解析精選
- 系統(tǒng)性紅斑狼瘡-第九版內(nèi)科學(xué)
- 全統(tǒng)定額工程量計(jì)算規(guī)則1994
評(píng)論
0/150
提交評(píng)論