1、防撞護欄施工方案(Rev1#)Method Statement to crash barrier(Rev1#)工程概況Project Overview 周家梁大橋位于四川省宣漢縣南壩鎮(zhèn),距南壩鎮(zhèn)街約5km,該橋為跨越前河而設(shè),孔跨布置為6孔30m預(yù)應(yīng)力混泥土簡支T 梁(橋面連續(xù),6孔一聯(lián))橋梁全長210m。全橋兩側(cè)設(shè)置防撞墻,下部寬度0.5m,高度1.14m.混凝土結(jié)構(gòu)高度為0.863m,頂部為鋼管扶手。Zhoujialiang Bridge is situated at Nanba town, Xuanhan county, Sichuan, which is about 5 km away
2、 from downtown of Naban town(Street). This bridge ,constructed to cross over the Qianhe river, is simply supported T-shaped prestressed bridge with 6 spans of 30m (continuous deck, six spans). Total length of the bridge is 210 m. Install crash barrier on both sides, it is 0.5m wide at the bottom and
3、 1.4m high. The height of concrete structure is 0.863m, while tube guardrails installed at top of it.三、防撞護欄施工方法 Practices for Crash Barrier(一)護欄的施工護欄采用C30混凝土澆筑,全橋21m,每15m設(shè)置一道2cm斷縫,斷縫處采用油浸木板填縫。護欄內(nèi)預(yù)埋泄水孔間距4m。護欄內(nèi)外側(cè)模采用定型鋼模,由專業(yè)廠家生產(chǎn)。在澆好的橋面上用全站儀放出橋梁中心線,然后放出護欄底角線和模板控制線,整型綁扎鋼筋,清理干凈護欄底部,模板立好之后用自動精平水準(zhǔn)儀測出標(biāo)高,檢收合格
4、后進行混凝土澆筑。15m一循環(huán)。 Pour the barrier with C30 concrete. Set up a 2cm break-joint in each 15cm along the whole 21m bridge and pack those joints with oil immersed boards. Pre-embed drainage hole every 4m inside the barrier. Use formulized steel formwork produced by professional manufacturer for the outer
5、 side. Measure the center line on the finished deck with total station, then the barrier base angle line and formwork control line. Integer and bind reinforcement, clean out the bottom of barrier, measure elevation with automatic pure flat level after erecting the form, pour concrete after inspectio
6、n. Repeat it every 15m.1、 鋼筋工程Rebar Works 鋼筋的進場,要有出廠質(zhì)量保證書。沒有出廠質(zhì)量保證書的鋼筋,不能進場,對每批進場的鋼筋,嚴(yán)格按規(guī)范規(guī)定取樣試驗合格后才能使用。 鋼筋焊接,焊接頭要經(jīng)過試驗合格后,才允許正式作業(yè),在一批焊件期間,隨機抽檢,并以此作為加強焊接作業(yè)質(zhì)量的監(jiān)督考核。鋼筋安裝完成后預(yù)埋PVC管,長度50cm.為橋面排水系統(tǒng)預(yù)留孔道。Rebar should have quality certificate provided by manufacture before mobilization. Strictly perform sampl
7、ing test for each batch of rebars before put them into use.Rebar welding. After the welding joints been experimented and certified, welding operation starts. Inspect a batch of welding joints randomly as the supervision assessment to enhance welding operation quality. Pre-embed 50cm PVC after the in
8、stallation of reinforcement. Reserve drainage holes for the deck drainage system.2、模板工程Formwork Works 模板要符合結(jié)構(gòu)尺寸,保證有足夠的強度和剛度,并要裝拆方便。使用過的模板必須經(jīng)過清潔處理后才能重新拼裝使用。拆模板必須等混凝土強度達到規(guī)定的強度后才能進行,拆模板時,要保證不會引起混凝土的損壞。拆除的模板應(yīng)墊平、整齊堆放,防止扭曲變形,并及時清理干凈。模板安裝時采用簡易的吊裝設(shè)備,兩個人操作吊裝設(shè)備(計算簡下圖),將模板掛于吊裝設(shè)備力矩短的一端,兩個人在力矩長的一端施力,使模板離開地面,緩慢移動
9、吊裝設(shè)備,將模板移到安裝位置,計算吊裝設(shè)備車輪的位置安放方木,便于停止吊裝設(shè)備的移動。外模吊裝到位后用鋼筋與護欄預(yù)埋筋焊接連接。內(nèi)外模用拉桿連接,確保固定。Make sure the formwork is suitable in size, enough strength and rigidity and easy to dismantle. Removed formwork must be cleaned out before reassembled. Remove forms only on the basis of reaching the specified strength and
10、 without causing any damage to the concrete. Level up the removed forms in order and clean up in time. Operate the temporary lifting equipments (as shown below) with two person in formwork installation. Hang the form at the short-moment end, while the person exert force at the long-moment end to lif
11、t the form. Move the form slowly with the equipments in position; calculate the position of equipments wheel to place timber, so as to move the equipments. Connect the external mold and reinforcements pre-embedded in crash barrier with rebar. Fix the internal and external molds with tie bar. 3、混凝土工程
12、Concrete Works 根據(jù)混凝土的強度要求準(zhǔn)確計算出混凝土的配合比,施工過程中,應(yīng)使用審批后配合比,應(yīng)派專業(yè)試驗人員到攪拌站監(jiān)督檢查混凝土配合比執(zhí)行情況,原材料、坍落度、試樣取樣、稱量衡器檢查校準(zhǔn)以及拌和時間等是否按規(guī)定進行。并經(jīng)過監(jiān)理工程師檢查批準(zhǔn)后開始澆注混凝土。Calculate the concrete mix proportion as per strength, and only use approved proportion in construction. Assign professional laboratory person to supervise the mi
13、x proportion in batching plant to make sure the raw materials, slumps, sampling test, weghing apparatus calibration and mixing time are done in accordance with provisions. Pour concrete after been inspected and approved by supervision engineer. 混泥土采用鏟車運送,制作溜槽,將混凝土送入模板中,混凝土澆注施工時,要嚴(yán)格按分層施工,所有的混凝土一經(jīng)澆注,應(yīng)
14、立即進行全面的振搗,使之形成密實、均勻整體,并注意避免發(fā)生漏振、過振現(xiàn)象。 Make downspoutings, and pour concrete transported with loader into the form, and vibrate immediately once the reinforcement been poured, to make it a compelled and homogeneous unit, and avoid any vibration missing and over vibration.五、質(zhì)量控制措施QA/QC Measures 1、建立健全
15、的質(zhì)量管理機構(gòu),確保質(zhì)量管理機構(gòu)體系的正常運作。各管理部門做到責(zé)任明確,各司其職,各負其責(zé)。Set up sound QA/QC administrative department to assure smooth operation of quality management system. Each department shall take its responsibility and obligation respectively. 2、認(rèn)真執(zhí)行技術(shù)規(guī)范,程序文件和作業(yè)文件的要求,一切工作均按技術(shù)規(guī)范、公司質(zhì)量文件要求去做。Implement technical code, progr
16、am file and job file, and finish all work as per their requirements. 3、對于工程材料的采購必須是經(jīng)過對供應(yīng)商的評審,評審?fù)ㄟ^后,上報監(jiān)理工程師審批后方可采購及采用。材料進場檢驗合格后,按要求合理堆放,并做好標(biāo)識工作,防止混用及調(diào)亂。保證材料管理井井有條,促進質(zhì)量管理。Assess the material supplier and report to supervision engineer for his approval before purchasing any engineering materials from s
17、upplier. Pile up the certified materials in good order and mark them with identification number to avoid any mixing and confusion. Promote quality management by ensuring material management in perfect order.六、安全生產(chǎn)措施Measures For Safety Production根據(jù)本工程特點,安全防護的主要對象有:高處墜落、物體打擊、垮塌、觸電、交通、設(shè)備事故、防火、防爆。除需要認(rèn)真貫
18、徹執(zhí)行有關(guān)安全生產(chǎn)規(guī)章制度、落實安全生產(chǎn)責(zé)任制外,還需要采取必要的安全技術(shù)措施,才能防患于未然。According to the project characteristics, the following objects need some attention: dropped objects, hit, collapse, electrocution, traffics, equipment failures, fireproofing & anti-explosion. Besides implementing rules and regulations for safety produ
19、ction and responsibility system for production, some technical safety measures are essential.(一)防高處墜落 Fall from Height Protection1、根據(jù)作業(yè)種類選擇合適的安全帶,護欄施工時拉設(shè)生命線,全程施工必須掛設(shè)安全帶。 Select appropriate harness as per operation category, erect lifeline in crash barrier construction, and wear harness at all operat
20、ion times.2、在橋梁底部拉設(shè)警戒線,禁止施工人員進入防止砸傷。 Barricade the under beneath areas of beam, protect constructors from being hurt by dropped objects.(二)防物體打擊 Avoid from being Stroke1、高空作業(yè)所用材料、成品、半成品均應(yīng)堆放平穩(wěn),工具應(yīng)隨手放工具袋內(nèi);傳遞物件禁止拋擲,禁止向下丟棄任何工具、材料、建筑垃圾等。Level up all materials, finished products and semi-finished products
21、 and put tools into toolbox; prohibit to pass ant object by throwing, or drop any tool, material and construction waste from height.2、凡進入施工現(xiàn)場人員必須正確佩戴安全帽。 Wear safety helmet for anyone onsite.3、各類施工、加工機具自身的安全保護裝置必須齊全有效。 Complete all valid safety protection devices for processing and constructing mach
22、ines.4、作業(yè)人員高空使用工具時,為防滑落,應(yīng)用繩子將工具系牢,牢掛在固定構(gòu)件或人體上。Fasten tools with rope and anchor them to fixed elements or body when working at height to avoid tools skidding.(四)防觸電 Electrocution Prevention1、施工現(xiàn)場臨時電線路、設(shè)施的安裝和使用必須符合建設(shè)部頒發(fā)的建設(shè)工程施工現(xiàn)場供用電安全規(guī)范(GB5019493)的規(guī)定,具體要求如下:The installation and application of temp ele
23、ctrical circuits and facilities must conform to requirements in Construction Site Electricity Safety Codes (GB5019493).2、施工現(xiàn)場專用中性點接地的電力線路,必須實行三相五線制,如引入的電源為三相五線制時,在引入的第一級開關(guān)的零線端子處,做好重復(fù)接地,工作零線和保護零線同時從重復(fù)接地處引出,重復(fù)接地電阻值不大于10。Use neutral point grounded cables at site, and must implement three-phase five-wir
24、e system. If the power is within the system, reground at the end of null line of first-grade switch. Extend the work null line and protection null line from the regrounding point where the resistance is not more than 10.3、施工配電系統(tǒng)按施工組織設(shè)計要求設(shè)總配電箱,分配電箱,開關(guān)箱,實行分級配電,開關(guān)箱必須裝漏電保護器。(漏電保護器應(yīng)符合GB682986標(biāo)準(zhǔn))。Set up c
25、onstruction distribution system in alignment with technical scheme demands, including distribution box, switch box; and carry out power distribution classification and install earth leakage protective device in distribution box. ( earth leakage protective device shall fits GB682986 Standard ).4、導(dǎo)線穿坑
26、、洞、棚或過路時應(yīng)穿管保護,嚴(yán)禁亂拉亂扯把線等。Protect cables passing through pits, holes, sheds and roads with tubes, and forbid to erect cables in a mass.5、當(dāng)施工現(xiàn)場臨時用電與甲方共用一供電系統(tǒng)時,要根據(jù)甲方的要求做保護接零或作保護接地,嚴(yán)禁一部分接地另一部分接零。Conduct protection to null line or earth line when sharing the power supply system with another party accordin
27、g to its requirements; strictly prohibit partly earthed.6、低壓干線的架設(shè)、配電箱、熔絲等要根據(jù)現(xiàn)場條件,依據(jù)規(guī)程規(guī)范進行布置,應(yīng)設(shè)在干燥、通風(fēng)、操作方便及常溫場所,露天應(yīng)有防雨設(shè)施。Deploy secondary main cables, distribution box and fuse wire as per site conditions and codes at dry, ventilated, easy operational and room temperature areas, and take waterproofin
28、g measures in open fields.7、手持電動工具應(yīng)選用類電動工具,并裝額定電流不大于15,動作時間小于0.1s的漏電保護器,若使用類工具時還應(yīng)作保護接零。露天潮濕場所金屬架上,嚴(yán)禁使用類手持電動工具。Select hand-hold motor-driven machines, and put earth leakage protective device with its less than 15rated currency and its less than 0.1s action time. Proper earth it if machines used, and
29、forbid to use it on metal frame in humid open fields. 8、電焊機一、二次應(yīng)用接線并加罩防護,二次線應(yīng)用線板、線鼻子接牢,露天存放應(yīng)有良好的防雨、防潮設(shè)施。Ensure the welder is firstly and secondly wired and protected with a cover. Fix the secondary wiring with line panel and line coupler. Store it in good waterproofing and damp proofing facilities.(
30、五)防火、防爆 Fireproofing and Anti-explosion1、氣瓶應(yīng)有防震圈、安全帽,存放地點有明顯標(biāo)志,并有防火防爆措施。Cylinders shall wear shock proofing ring and safety cap, mark obvious signs at storing place, and take fire proofing and anti-explosion measures.2、可燃與助燃氣瓶安全距離應(yīng)大于5m,與作業(yè)距離大于10m。Safety space from combustible cylinder to combustion-
31、supporting cylinders is 5m, and more than 10m away from operation areas.(六)消防設(shè)備 Fire Fighting Apparatus1起重吊裝 Lifting and Rigging施工機械應(yīng)按照施工總平面圖規(guī)定的位置線路設(shè)置,不得侵占場內(nèi)道路。施工機械進場安裝后需經(jīng)過安全檢查,合格后方能使用。起重符合GB606785起重機械安全規(guī)程規(guī)定,確保安全限位裝置齊全有效。超限吊裝設(shè)備應(yīng)制定切實可行的吊裝方法和技術(shù)措施,保證吊裝安全。Deploy cables of machines on the basis of constr
32、uction site-plan without occupying on-site accesses. Conduct safety inspection after machine mobilization and operate them with certification. Conform to Safety Rules for Lifting Appliances GB6067-85 and make sure inhibiting devices are safe and valid. Formulate practicable lifting and technical mea
33、sures when lifting overloads to assure web slings safety.a.起重機嚴(yán)禁超載吊裝,滿載工作時,左右回轉(zhuǎn)范圍不得超過90,嚴(yán)禁橫吊,以免傾翻。較大型設(shè)備的吊裝及場地窄小,障礙嚴(yán)重的起重作業(yè)要編制施工方案,安全技術(shù)保證措施要可靠詳盡。Overloading of the crane is strictly prohibited. Keep 90slewing scope from side to side to avoid overturning by forbidding to lift transversely during full l
34、oad. Format MS with detailed safety engineering measures when using large equipment, concerning with narrow space, lifting and rigging with serious obstructions.b.電動卷揚機應(yīng)安裝在視野寬闊,距起吊物15m以外的位置。固定必須牢固,防止吊物時產(chǎn)生傾復(fù)與滑動尾部的封繩必須正確的鎖固在錨樁上。Electric winch shall be installed 15m away from the lifted object with a o
35、pen view. Firmly fixed to prevent any overturning when performing lifting and wire rope skidding at tail must be anchored on piles. c.手拉葫蘆吊鉤、鏈條等主要受力件不得損壞。提升過程中,拽動手拉葫蘆鏈條用力應(yīng)均勻和緩,禁止用力猛使鏈條跳動或卡環(huán)。No damage to load carrying elements to hand-hold chains hoists and chains. Pull the hoist chain to balance the
36、 force to avoid chains up & down or blocked in lifting process.d.千斤頂必須放在結(jié)實可行的基礎(chǔ)上,防止重物滑動。每臺起重能力不得小于載荷的1.2倍,頂升高度不得超過有效頂程。Store jacks on solid foundations to avert skidding. Jack-up capacity for each jack shall not less than 1.2 times of its rated capacity and the jacking height shall not exceed valid one.e.各種起重機械按規(guī)范規(guī)定配備可行有效的安全裝置。Fit out safety devices for all hoisting machines according to the code.f.嚴(yán)格遵守“十不吊”:斜拉斜掛不吊;超負荷或物體重量不明不吊;安全裝置失靈不吊;捆綁、吊掛不牢或不平衡不吊;指揮信號不明、光線暗淡、視物不清不吊;吊件帶棱角、缺口無措施不吊;吊件上有人或添置物不吊;吊件埋在地下、重
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 人人文庫網(wǎng)僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準(zhǔn)確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 《成本與管理會計(英文)》課件-3.1Cost flows in manufacturing business
- 音樂課介紹課件
- 高效節(jié)能電機項目招投標(biāo)方案(模板)
- 2025年果酒及配制酒項目發(fā)展計劃
- 2025年鋼結(jié)構(gòu)用H型鋼項目發(fā)展計劃
- 2025年太陽能電池用多晶硅、非晶硅項目合作計劃書
- 2025年互聯(lián)網(wǎng)醫(yī)療平臺在線問診服務(wù)質(zhì)量優(yōu)化報告
- 2025年工業(yè)互聯(lián)網(wǎng)平臺漏洞掃描技術(shù)在物聯(lián)網(wǎng)安全防護中的應(yīng)用研究
- 時尚零售行業(yè)快時尚模式下的品牌合作與聯(lián)合營銷報告
- 智慧城市的公共交通數(shù)據(jù)分析報告
- 合同公司變更協(xié)議書范本
- 文學(xué)概論考試要點試題及答案
- 2024–2025年中國數(shù)據(jù)標(biāo)注產(chǎn)業(yè)深度分析報告
- 學(xué)校粉刷門窗協(xié)議書
- 2025-2031年中國材料預(yù)浸料行業(yè)市場深度研究及發(fā)展趨勢預(yù)測報告
- 法人更換免責(zé)協(xié)議書
- 2025-2030年中國鄉(xiāng)村振興戰(zhàn)略行業(yè)市場發(fā)展分析及前景趨勢與投融資發(fā)展研究報告
- 小球彈簧(蹦極、蹦床)模型-高考物理一輪復(fù)習(xí)模型及解題技巧(解析版)
- 氫能分解與轉(zhuǎn)化技術(shù)創(chuàng)新-全面剖析
- 2025-2030天文望遠鏡行業(yè)市場深度調(diào)研及發(fā)展趨勢與投資戰(zhàn)略研究報告
- 2025年小學(xué)教師資格考試《綜合素質(zhì)》邏輯推理能力測評題庫(附答案)
評論
0/150
提交評論